Letter Sequence Meeting |
|---|
EPID:L-2018-RNW-0002, Enclosure 4 - Non-Proprietary Reference Documents and Redacted Versions of Proprietary Reference Documents (Public Version) (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement
Administration
- Withholding Request
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: L-2018-154, Subsequent License Renewal Application Safety Review Requests for Additional Information (RAI) Set 2 Responses, L-2018-175, Subsequent License Renewal Application, Safety Review Requests for Additional Information (RAI) Set 5 Responses, L-2018-176, Subsequent License Renewal Application, Responses to the August 2018 NRC On-Site Regulatory Audit Follow-Up Items, L-2018-187, Subsequent License Renewal Application Revision to SLRA Section 3.5.2.2.2.6, Reduction of Strength and Mechanical, Properties of Concrete Due to Irradiation, L-2019-037, Subsequent License Renewal Application Safety Review Requests for Additional Information (RAI) Set 9 Responses, ML17338A134, ML17338A139, ML17360A054, ML18003A047, ML18037A824, ML18037A828, ML18037A829, ML18074A252, ML18080A175, ML18081A239, ML18081A257, ML18081A270, ML18081A278, ML18086A705, ML18087A433, ML18113A142, ML18160A012, ML18173A087, ML18183A445, ML18214A171, ML18230B482, ML18232A576, ML18299A114, ML18341A024, ML19032A536, ML19050A400, ML19162A072, ML19162A097, ML19162A117, ML19162A343, ML19200A070, ML19326C114, ML22073A122
|
MONTHYEARML19326C1141972-07-19019 July 1972 SLR Tech Specs from Authority File Project stage: Other L-2017-097, Request for Withholding Information from Public Disclosure Re Subsequent License Renewal Notification2017-05-17017 May 2017 Request for Withholding Information from Public Disclosure Re Subsequent License Renewal Notification Project stage: Withholding Request ML18080A1642017-05-25025 May 2017 U.S. Nuclear Regulatory Commission Approval of Florida Power & Light Company Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML18081A2862017-08-23023 August 2017 Notice of Forthcoming Closed Teleconference to Discuss Pre-application Activities Related to the Anticipated Submittal of a Subsequent License Renewal Application from an Unnamed Plant - Scoping and Screening Methodology Project stage: Meeting ML18080A1782017-08-23023 August 2017 Notice of Forthcoming Closed Teleconference to Discuss Pre-application Activities Related to the Anticipated Submittal of a Subsequent License Renewal Application from an Unnamed Plant - Neutron Fluence Calculations Project stage: Meeting ML18080A1702017-08-23023 August 2017 Notice of Forthcoming Closed Teleconference to Discuss Pre-Application Activities Related to the Anticipated Submittal of a Subsequent License Renewal Application from an Unnamed Plant -Environmental Topics and SAMA Project stage: Meeting ML18080A1662017-08-23023 August 2017 Notice of Forthcoming Closed Meeting to Discuss Pre-application Activities Related to the Anticipated Submittal of a Subsequent License Renewal Application from an Unnamed Plant - Reactor Vessel Internals Project stage: Meeting ML18080A1722017-09-0505 September 2017 Official Use Only - Proprietary Information - Unnamed Plant Meeting Prep for Environmental Pre-Application Call - Resent to Include an Additional Topic Project stage: Meeting ML18081A2342017-10-23023 October 2017 Notice of Teleconference to Discuss Pre-Application Activities for the Anticipated Submittal of a Subsequent License Renewal Application for an Unnamed Plant - Reactor Vessel Internals, Neutron Fluence, and Environmentally Assisted Fatigue Project stage: Meeting ML18081A2572017-11-0101 November 2017 Notice of Forthcoming Closed Telecon to Discuss Pre-Application Activities Related to the Anticipated Submittal of a Subsequent License Renewal Application from an Unnamed Plant - GALL SLR Requirements for Assessment of Concrete Degradation Project stage: Other ML18081A2702017-11-17017 November 2017 Notice of Closed Telecon to Discuss Pre-Application Activities Related to the Anticipated Submittal of a Subsequent License Renewal Application from an Unnamed Plant - GALL SLR Requirements for Cable and Electrical Aging Management Programs Project stage: Other ML18080A1682017-12-21021 December 2017 Summary of Pre-Application Meeting Between the NRC and FPL to Discuss AMP XI.M16A, PWR Vessel Internals Associated with the Turkey Point Units 3 and 4, Subsequent License Renewal Application Project stage: Meeting ML18081A0252017-12-28028 December 2017 September 11, 2017, Summary of Pre-Application Meeting That Was Scheduled to Be Held Between NRC and FPL to Discuss Neutron Fluence Associated with the Turkey Point Subsequent License Renewal Application Project stage: Meeting ML18080A1752018-01-0505 January 2018 Summary of Closed Pre-Application Telecon Held on September 7, 2017, Between NRC and FPL to Discuss the Environmental Report Associated with the Turkey Point Subsequent License Renewal Application Project stage: Other ML18081A2782018-01-0505 January 2018 Summary of Closed Pre-Application Telecon Held on November 21, 2017, Between NRC and FPL to Discuss Cable and Electrical Aging Management Programs Associated with the Turkey Point Subsequent License Renewal Application Project stage: Other ML18081A2932018-01-0505 January 2018 Summary of Closed Pre-Application Teleconference Held on September 12, 2017, Between NRC and FPL to Discuss Scoping and Screening Methodology Associated with the Turkey Point Unit Nos. 3 and 4 Subsequent License Renewal Application Project stage: Meeting ML18081A2632018-01-0505 January 2018 Summary of Closed Pre-Application Teleconference Between NRC and FPL to Discuss Concrete Degradation Associated with the Turkey Point Subsequent License Renewal Application Project stage: Meeting ML18081A2392018-01-0505 January 2018 Summary of Closed Pre-Application Telecon Held on November 6, 2017, Between the NRC and FPL to Discuss MRP-227, Reactor Vessel Internals, and Environmentally Assisted Fatigue Associated with the Turkey Point Subsequent License Renewal Appli Project stage: Other L-2018-004, Enclosure 4 - Non-Proprietary Reference Documents and Redacted Versions of Proprietary Reference Documents (Public Version)2018-01-30030 January 2018 Enclosure 4 - Non-Proprietary Reference Documents and Redacted Versions of Proprietary Reference Documents (Public Version) Project stage: Request ML18037A8122018-01-30030 January 2018, 31 January 2018 Submittal of Subsequent License Renewal Application Project stage: Request ML18037A8292018-01-30030 January 2018 Enclosure 2 - Applications for Withholding Proprietary Information from Public Disclosure Pursuant to 10 CFR 2.390 Project stage: Other ML18037A8282018-01-30030 January 2018 Enclosure 1 - Turkey Point Subsequent License Renewal Application Enclosure Summary Project stage: Other ML18037A8242018-01-30030 January 2018 Submittal of Subsequent License Renewal Application Project stage: Other ML18113A1322018-01-31031 January 2018, 10 April 2018, 30 April 2018 Transmittal of Subsequent License Renewal Application Revision 1 Project stage: Request L-2018-039, License Renewal Application - Supplement 12018-02-0909 February 2018 License Renewal Application - Supplement 1 Project stage: Supplement ML18053A1372018-02-16016 February 2018 Subsequent License Renewal Application - Supplement 2 Project stage: Supplement L-2018-053, Replacement Pages to Enclosure 3, SLRA Section 42018-02-16016 February 2018 Replacement Pages to Enclosure 3, SLRA Section 4 Project stage: Request ML18053A1232018-02-16016 February 2018 Subsequent License Renewal Application - Supplement 2 Project stage: Request ML18038A6912018-04-0303 April 2018 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML18113A1422018-04-10010 April 2018 Enclosure 2 to L-2018-082, Applications for Withholding Proprietary Information from Public Disclosure Per 10 CFR 2.390 (Public Version) Project stage: Other ML18074A2522018-04-12012 April 2018 Status of Subsequent License Renewal Application Project stage: Other ML17338A1342018-04-13013 April 2018 Receipt and Availability of the Subsequent License Renewal Application for the Turkey Point Nuclear Generating Units 3 and 4 Project stage: Other ML17338A1392018-04-13013 April 2018 FRN for Receipt and Availability of the Subsequent License Renewal Application for the Turkey Point Nuclear Generating Units 3 and 4 Project stage: Other ML18087A4332018-04-20020 April 2018 Change in Determination for Withholding Information from Public Disclosure Project stage: Other ML18087A4742018-04-20020 April 2018 Change in Determination for Withholding Information from Public Disclosure Project stage: Request ML17360A0542018-04-25025 April 2018 Subsequent License Renewal Application Online Reference Portal Project stage: Other ML18003A0482018-04-26026 April 2018 Federal Register Notice (FRN) for Opportunity to Request a Hearing and to Petition for Leave to Intervene in the Review of FPLs Turkey Point Subsequent License Renewal Application Project stage: Approval ML18003A0472018-04-26026 April 2018 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from FPL for Subsequent Renewal of the Turkey Point Units 3 and 4 Project stage: Other ML18086A7052018-04-26026 April 2018 Plan for the Operating Experience Review Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML18149A5702018-05-29029 May 2018 Draft RAI B.2.3.16 1, Fire Protection System Enhancements, for Turkey Point SLRA, for Public Teleconference on June 13, 2018 Project stage: Draft RAI ML18150A2552018-05-30030 May 2018 Slides for Turkey Point Public Scoping Meeting on May 31 2018 - Spanish Project stage: Meeting ML18150A2402018-05-30030 May 2018 Slides for Turkey Point Public Scoping Meeting on May 31 2018 - English Project stage: Meeting ML18160A0122018-06-12012 June 2018 Plan for the In-Office Regulatory Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML18173A0872018-07-0505 July 2018 Plan for the Irradiated Concrete Technical Issue Regulatory Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML18183A4452018-07-23023 July 2018 Report for the Operating Experience Review Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML18214A1712018-08-0101 August 2018 Subsequent License Renewal Application Project stage: Other ML18218A2002018-08-0606 August 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 1 (EPID No. L-2018-RNW-0002) - Enclosure Project stage: RAI ML18218A1992018-08-0606 August 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 1 (EPID No. L-2018-RNW-0002) - E-mail Project stage: RAI ML18218A1982018-08-0606 August 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 1 Project stage: Request ML18232A5142018-08-20020 August 2018 Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 2 Project stage: RAI 2018-02-09
[Table View] |
Text
OFFICIAL USE ONLY - PROPRIETARY INFORMATION January 5, 2018 LICENSEE:
Florida Power & Light Company FACILITY:
Turkey Point Nuclear Generating Units 3 and 4
SUBJECT:
SUMMARY
OF CLOSED PRE-APPLICATION TELECONFERENCE HELD ON SEPTEMBER 12, 2017, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION STAFF AND FLORIDA POWER & LIGHT COMPANY REPRESENTATIVES TO DISCUSS SCOPING AND SCREENING METHODOLOGY ASSOCIATED WITH THE TURKEY POINT NUCLEAR GENERATING UNITS 3 AND 4, SUBSEQUENT LICENSE RENEWAL APPLICATION On September 12, 2017, the U.S. Nuclear Regulatory Commission (NRC) staff met with representatives of Florida Power & Light Company (FPL) in a closed teleconference to discuss the subsequent license renewal application for the Turkey Point Nuclear Generating Units 3 and 4, specifically FPLs scoping and screening methodology. The proprietary meeting agenda can be found at the NRCs Agencywide Documents and Access Management System Accession No. ML17230A299, a list of attendees is provided in Enclosure 1, a summary of the meeting is provided in Enclosure 2, and a list of risk significant systems is provide in.
Sincerely,
/RA/
Lois M. James, Senior Project Manager License Renewal Project Branch Division of Materials and License Renewal Office of Nuclear Reactor Regulation Docket Nos.: 50-250 and 50-251
Enclosures:
1.
Attendance List 2.
Meeting Summary 3.
Risk Significant Systems cc w/encls: See next page OFFICIAL USE ONLY - PROPRIETARY INFORMATION FPL submitted the Subsequent License Renewal Application on January 30, 2018 (ADAMS Package Accession No. ML18037A812) therefore, it is no longer necessary to withhold as proprietary.
ML18002A006
- Concurrence via email OFFICE PM:MRPB:DMLR LA:MRPB:DMLR MVIB:DMLR BC:MRPB:DMLR NAME LJames*
YEdmonds SLent for BRogers EOesterle*
DATE 01/02/2018 01/04/2018 01/04/2018 01/04/2018 OFFICE PM:MRPB:DMLR NAME LJames DATE 01/05/2018
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION CLOSED TELECON BETWEEN THE NRC STAFF AND FLORIDA POWER & LIGHT COMPANY TURKEY POINT NUCLEAR GENERATING UNITS 3 AND 4 SUBSEQUENT LICENSE RENEWAL APPLICATION - SCOPING AND SCREENING METHODOLOGY MEETING ATTENDANCE LIST SEPTEMBER 12, 2017 PARTICIPANTS AFFILIATIONS Lois James U.S. Nuclear Regulatory Commission (NRC)
Bill Rogers NRC David Drucker NRC Paula Cooper NRC Adam Wilson NRC Allen Hiser NRC William Holston NRC William Maher Florida Power & Light Company (FPL)
Paul Jacobs FPL Terry McCool FPL Rick Orthen FPL Steve Franzone FPL James V. Wicks Enercon Stephen Hale Enercon Jack Hoffman Enercon
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION CLOSED TELECON BETWEEN THE NRC STAFF AND FLORIDA POWER & LIGHT COMPANY TURKEY POINT NUCLEAR GENERATING UNITS 3 AND 4 SUBSEQUENT LICENSE RENEWAL APPLICATION - SCOPING AND SCREENING METHODOLOGY TELECONFERENCE
SUMMARY
SEPTEMBER 12, 2017 On May 17, 2017, Florida Power & Light Company (FPL or the applicant) submitted a Notice of Intent (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML17142A036 (non-public, proprietary) and ML17139D442 (public, non-proprietary)) to submit a subsequent license renewal application (SLRA) for Turkey Point Nuclear Generating Units 3 and 4 (Turkey Point). This Notice of Intent was submitted as proprietary information.
On May 25, 2017, the U.S. Nuclear Regulatory Commission (NRC) staff issued its approval of FPLs request for withholding information from public disclosure (ADAMS Accession Nos. ML17096A477 (non-public, proprietary) and ML17139D441 (public, non-proprietary)).
On September 12, 2017, the NRC staff participated in a pre-application, closed teleconference with FPL to discuss the content of the Turkey Point SLRA, specifically FPLs scoping and screening methodology. The proprietary meeting notice was issued on August 23, 2017 (ADAMS Accession No. ML17230A299).
The applicant began the discussion by explaining that the same individuals who were involved in the scoping and screening of the development of the initial license renewal application were also involved in the scoping and screening of the development of the SLRA. In reviewing what changed between the initial license renewal and the subsequent license renewal (SLR), the applicant noted no changes in Title 10 of the Code of Federal Regulations Section 54.4 (a)(1)
(10 CFR 54.4(a)(1)) or 10 CFR 54.4(a)(3):
10 CFF 54.4 Scope.
(a) Plant systems, structures, and components within the scope of this part are--
(1) Safety-related systems, structures, and components which are those relied upon to remain functional during and following design-basis events (as defined in 10 CFR 50.49 (b)(1)) to ensure the following functions--
(i) The integrity of the reactor coolant pressure boundary; (ii) The capability to shut down the reactor and maintain it in a safe shutdown condition; or (iii) The capability to prevent or mitigate the consequences of accidents which could result in potential offsite exposures comparable to those referred to in § 50.34(a)(1), § 50.67(b)(2), or § 100.11 of this chapter, as applicable.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION (3) All systems, structures, and components relied on in safety analyses or plant evaluations to perform a function that demonstrates compliance with the Commission's regulations for fire protection (10 CFR 50.48), environmental qualification (10 CFR 50.49), pressurized thermal shock (10 CFR 50.61),
anticipated transients without scram (10 CFR 50.62), and station blackout (10 CFR 50.63).
The applicant identified one major change, implementation of National Fire Protection Association (NFPA)-805, "Performance-Based Standard for Fire Protection for Light-Water Reactor Electric Generating Plants," that could impact the scope of SLR. As a result of this change, the applicant evaluated its scoping regarding 10 CFR 54.4(a)(2):
10 CFF 54.4 Scope.
(a) Plant systems, structures, and components within the scope of this part are--
(2) All nonsafety-related systems, structures, and components whose failure could prevent satisfactory accomplishment of any of the functions identified in paragraphs (a)(1)(i), (ii), or (iii) of this section.
The applicant stated they used the following four documents to develop the scope of SLR:
NUREG-2191, Generic Aging Lessons Learned for Subsequent License Renewal (GALL-SLR) Report, NUREG-2192, Standard Review Plan for Review of Subsequent License Renewal Applications for Nuclear Power Plants, Nuclear Energy Institute (NEI) 17-01, Industry Guideline for Implementing the Requirements of 10 CFR Part 54 for Subsequent License Renewal [SLR], and NEI 95-10, "Industry Guidelines for Implementing the Requirements of 10 CFR Part 54 -
The License Renewal Rule."
The applicant considered special interactions and whether these are within scope:
Buildings containing safety and non-safety systems High energy line break consideration considerations Structural integrity attachment Leakage and spray systems/areas for mid to low energy line break (external areas not included)
For containment, non-safety equipment near moderate or low energy line break are not within scope The NRC staff reminded FPL that the application needs to provide a basis for what is within and not within scope. In addition, the applicant should be aware of what the NRC staff asked in requests for additional information (RAIs) during license renewal reviews and address any RAIs potentially applicable to Turkey Point.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION The NRC staff reminded the applicant that there is a new pipe coating aging management program (AMP) and that implementation of NFPA-805 could impact fire protection equipment within the scope of SLR. The applicant stated that no equipment was removed from within scope of SLR as a result of NPFA-805 and that they will commit to new AMPs.
As a follow up to this meeting, the applicant provided a list of the top risk significant systems (see Enclosure 3) to permit the NRC staff to use risk insights in performing its review.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION List of Risk Significant Systems provided by the applicant:
Intake Cooling Water (ICW)
Component Cooling Water (CCW)
Auxiliary Feedwater Safety Injection Main Feedwater Emergency Diesel Generators (EDGs)
Instrument Air Startup Transformer 4160 Volt (V) Switchgear Chemical and Control Volume System (CVCS)
Emergency Load Sequencers Service Water 125 V DC & 120 V AC 240 KV Switchyard 480 V Load Centers DC Equipment Room Heating, Ventilation, and Air Conditioning (HVAC)
Standby Steam Generator Feedwater Pumps (SSGFW)
Reactor Coolant Engineered Safeguards Accumulators