Letter Sequence Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance, Acceptance
- Supplement, Supplement
Results
Other: ML17153A285, ML17156A093, ML17157B367, ML17180A077, ML17187A035, ML17240A332, ML17262A200, ML17269A051, ML17279A874, ML17298B174, ML17348B167, ML18002A369, ML18003A047, ML18037A836, ML18155A331, ML18155A333, ML18158A335, ML18162A063, ML18162A065, ML18162A066, ML18162A074, ML18173A169, ML18178A152, ML18179A155, ML18183A445, ML18186A088, ML18193B074, ML18197A294, ML18204A079, ML18204A088, ML18204A119, ML18204A129, ML18204A133, ML18204A140, ML18204A146, ML18204A185, ML18213A435, ML18214A146, ML18219A101, ML18219A165, ML18233A182, ML18247A502, ML18247A509, ML18353A835, ML19221B583, ML19295E426, ML19295E427, ML19295F527, ML19309F859
|
MONTHYEARML17153A2852017-05-25025 May 2017 License Renewal Application Project stage: Other ML17156A0932017-06-20020 June 2017 Receipt and Availability of the License Renewal Application for River Bend Station, Unit 1 Project stage: Other ML17186A1592017-07-10010 July 2017 License Renewal Application - Supplemental Information Needed for Acceptance of Requested Licensing Action, Regarding the Application from Entergy Operations, Inc. for Renewal of the Operating License for River Bend Station, Unit 1 Project stage: Acceptance Review ML17180A0772017-07-27027 July 2017 Correction Letter for the Receipt and Availability of the License Renewal Application for the River Bend Station, Unit 1 Project stage: Other ML17157B3672017-07-31031 July 2017 License Renewal Application Online Reference Portal Project stage: Other ML17187A0462017-08-0202 August 2017 License Renewal Pre- Application Coordination Meeting 1 River Bend Nuclear Generating Station Unit 1 - Summary of Meeting Held on April 25, 2017 Project stage: Meeting ML17187A0272017-08-0202 August 2017 License Renewal Application, NRC Presentation Summary of Meeting Held on May 25, 2017 Project stage: Meeting ML17187A0352017-08-0707 August 2017 Determination of Acceptability and Sufficiency for Docketing and Proposed Review Schedule Regarding the Application from Entergy Operations, Inc. for Renewal of the Operating License for River Bend Station, Unit 1 (CAC No. MF9747 and MF9778 Project stage: Other ML17187A0372017-08-0909 August 2017 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and Entergy Operations, Inc. Representatives to Discuss the River Bend Station, Unit 1 License Renewal Application Project stage: Meeting ML17180A1362017-08-0909 August 2017 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and Entergy Operations, Inc. Representatives to Discuss the River Bend Station, Unit 1 License Renewal Application Project stage: Meeting ML17173A1332017-08-0909 August 2017 FRN River Bend Acceptability for Docketing and Opportunity to Request a Hearing and to Petition for Leave to Intervene Project stage: Request ML17240A3322017-09-0707 September 2017 License Renewal Application Review Status Letter Project stage: Other ML17262A2002017-09-25025 September 2017 Plan for the Operating Experience Review Regarding the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML17269A0512017-10-10010 October 2017 Plan for the Aging Management Program Regulatory Audit Regarding the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML17279A8742017-10-11011 October 2017 Plan for the Scoping and Screening Methodology Regulatory Audit Regarding the License Renewal Application Review Project stage: Other ML17298B1742017-10-31031 October 2017 Audit Plan for the Onsite Aging Management Program Regulatory Audit for the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML18004A0662017-12-20020 December 2017 Entergy - Anchor Darling Double Disc Gate Valve Information and Status Project stage: Request ML17348B1672018-01-0404 January 2018 Status Letter - December Project stage: Other ML18002A3692018-01-0808 January 2018 Extension Letter Request Response Project stage: Other L-2018-004, Enclosure 2 - Applications for Withholding Proprietary Information from Public Disclosure Pursuant to 10 CFR 2.3902018-01-30030 January 2018 Enclosure 2 - Applications for Withholding Proprietary Information from Public Disclosure Pursuant to 10 CFR 2.390 Project stage: Request ML18037A8362018-01-31031 January 2018 Appendix E - Turkey Point Nuclear Plant Units 3 and 4 Environmental Report Subsequent Operating License Renewal Stage Project stage: Other Press Release-18-009, NRC Makes Available First Subsequent License Renewal Application from Turkey Point Nuclear Power Plant2018-03-22022 March 2018 Press Release-18-009: NRC Makes Available First Subsequent License Renewal Application from Turkey Point Nuclear Power Plant Project stage: Request L-2018-086, Subsequent License Renewal Application Appendix E Environmental Report Supplemental Information2018-04-10010 April 2018 Subsequent License Renewal Application Appendix E Environmental Report Supplemental Information Project stage: Supplement ML18003A0472018-04-26026 April 2018 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from FPL for Subsequent Renewal of the Turkey Point Units 3 and 4 Project stage: Other ML18155A3292018-05-27027 May 2018 Comment (1) of Matthew Cook on Florida Power & Light Company; Turkey Point Nuclear Plant Units 3 and 4 Project stage: Request ML18155A3312018-05-28028 May 2018 Comment (2) of Hannah Gardiner Supporting License Renewal for Turkey Point Nuclear Plant Units 3 and 4 Project stage: Other ML18155A3322018-05-30030 May 2018 Comment (3) of Gabriel Ignetti on Turkey Point Nuclear Plant Units 3 and 4 Project stage: Request ML18155A3332018-05-30030 May 2018 Comment (4) of John Karahalios Supporting License Renewal of Florida Power & Light Company; Turkey Point Nuclear Plant Units 3 and 4 Project stage: Other ML18162A0632018-05-31031 May 2018 Comment (6) of Anthony Denardo Supporting Turkey Point Nuclear Plant, Units 3 and 4 License Renewal Project stage: Other ML18155A3342018-05-31031 May 2018 Comment (5) of Elaine Trotter on Turkey Point Nuclear Plant, Units 3 and 4 Project stage: Request ML18187A2212018-05-31031 May 2018 Documents Provided by Laura Sue Wilansky to the U.S. Nuclear Regulatory Commission During the Turkey Point Nuclear Generating Units 3 and 4 Public Environmental Scoping Meeting on May 31, 2018 Project stage: Request ML18187A2242018-05-31031 May 2018 Documents Provided by Steve Schoedinger to U.S. Nuclear Regulatory Commission During the Turkey Point Unit 3 & 4 Public Environmental Scoping Meeting on May 31, 2018 Project stage: Request ML18162A0652018-06-0202 June 2018 Comment (7) of James Hopf Supporting Turkey Point Nuclear Plant, Units 3 and 4 License Renewal Project stage: Other ML18162A0662018-06-0303 June 2018 Comment (8) of D. Sotelo Opposing Turkey Point Nuclear Plant, Units 3 and 4 License Renewal Project stage: Other ML18162A0672018-06-0303 June 2018 Comment (9) of Jonathan Bauer Objecting to Extension of the License of Florida Power & Light Company, Turkey Point Nuclear Plant Units 3 and 4 Project stage: Request ML18162A0682018-06-0404 June 2018 Comment (10) of Diane Johnson on Turkey Point Nuclear Plant Units 3 and 4 Project stage: Request ML18162A0692018-06-0505 June 2018 Comment (11) of Sarah Fangman of Us Dept of Commerce, National Oceanic & Atmospheric Admin on Florida Power & Light Company; Turkey Point Nuclear Plant Units 3 and 4 Project stage: Request ML18162A0702018-06-0606 June 2018 Comment (12) of Ian Zink on Florida Power & Light Company; Turkey Point Nuclear Plant Units 3 and 4 Project stage: Request ML18162A0742018-06-0707 June 2018 Comment (13) of Robert Pike on Florida Power & Light Company; Turkey Point Nuclear Plant Units 3 and 4 License Renewal Project stage: Other ML18179A1582018-06-0707 June 2018 Comment (28) of Kirk C. Zuelch on Behalf of Florida Keys Aqueduct Authority on Florida Power and Light Application for Renewal Project stage: Request ML18163A1132018-06-0909 June 2018 Comment (14) of Patricia Milone on Turkey Point Nuclear Plant Units 3 and 4 Project stage: Request ML18169A1522018-06-12012 June 2018 NRR E-mail Capture - (External_Sender) SNO Requests Consultation Meeting with Nrc/Fpl at Turkey Point Nuclear Power Plant Project stage: Request ML18158A3352018-06-13013 June 2018 License Renewal Environmental Site Audit Regarding the Turkey Point Nuclear Generating Units 3 and 4 Subsequent License Renewal Application Project stage: Other ML18179A3632018-06-14014 June 2018 Comment (35) E-mail Regarding T.P. 3&4 SLR EIS Scoping Project stage: Request ML18179A2322018-06-14014 June 2018 Comment (25) E-mail Regarding T.P. 3&4 SLR EIS Scoping Project stage: Request ML18179A3542018-06-14014 June 2018 Comment (34) E-mail Regarding T.P. 3&4 SLR EIS Scoping Project stage: Request ML18179A3412018-06-14014 June 2018 Comment (33) E-mail Regarding T.P. 3&4 SLR EIS Scoping Project stage: Request ML18179A3332018-06-14014 June 2018 Comment (32) E-mail Regarding T.P. 3&4 SLR EIS Scoping Project stage: Request ML18179A2452018-06-14014 June 2018 Comment (31) E-mail Regarding T.P. 3&4 SLR EIS Scoping Project stage: Request ML18179A2352018-06-14014 June 2018 Comment (27) E-mail Regarding T.P. 3&4 SLR EIS Scoping Project stage: Request 2018-01-08
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 25, 2017 Mr. William F. Maguire Site Vice President River Bend Station, Unit 1 Entergy Operations, Inc.
5485 U.S. Highway 61 N St. Francisville, LA 70775
SUBJECT:
PLAN FOR THE OPERATING EXPERIENCE REVIEW AUDIT REGARDING THE RIVER BEND STATION UNIT 1, LICENSE RENEWAL APPLICATION REVIEW (CAC NO. MF9747)
Dear Mr. Maguire:
By letter dated May 25, 2017, Entergy Operations, Inc. (Entergy) submitted an application for renewal of operating license NPF-47 for the River Bend Station, Unit 1. The staff of the U.S.
Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants.
The staff plans to conduct its Operating Experience Review at the Nuclear Energy Institute office in Rockville, Maryland from October 2, 2017, through October 13, 2017, in accordance with the enclosed operating experience review audit plan. If you have any questions, please contact me by telephone at 301-415-4084 or by e-mail at Emmanuel.Sayoc@nrc.gov.
Sincerely,
/RA/
Emmanuel Sayoc, Project Manager Projects Management and Guidance Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-458
Enclosures:
- 1. Audit Plan
- 2. Audit Needs List cc w/encl: Listserv
ML17262A200 OFFICE PM:RPGB:DLR LA:RPGB:DLR PM:RCCB:DLR NAME ESayoc YEdmonds BRogers DATE 9/25/2017 9/21/2017 9/25/2017 OFFICE BC: RPGB:DLR BC: RCCB:DLR PM:RPGB:DLR NAME SStuchell SBloom ESayoc DATE 9/25/2017 9/25/2017 9/25/2017 Audit Plan Plan For The Operating Experience Review Audit Regarding The River Bend Station Unit 1, License Renewal Application October 2-13, 2017 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Plan For The Operating Experience Review Audit Regarding The River Bend Station Unit 1, License Renewal Application
- 1.
Background
The NRC staff performs an independent review of plant specific operating experience to identify examples of age related degradation, as documented in the applicants corrective action program database. These activities are performed as part of the staffs review of the River Bend Station (RBS) license renewal application.
- 2.
Regulatory Audit Bases License renewal requirements are specified in Title 10 of the Code of Federal Regulations (10 CFR), Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants.
Guidance is provided in NUREG-1800, Rev. 2, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR), dated December 2010, and NUREG-1801, Rev. 2, Generic Aging Lessons Learned (GALL) Report, dated December 2010.
- 3.
Regulatory Audit Scope The scope of this license renewal regulatory audit of RBS is the staffs independent review of plant specific operating experience. The review is performed to identify pertinent examples of age related degradation, as documented in the applicants corrective action program database. The results of the audit will be used to support the staffs further review of aging management programs (AMP), time limited aging analyses (TLAAs) and aging management review line items to provide a basis for the staffs conclusions on the ability of the applicants proposed AMP and TLAAs to manage the effects of aging in the period of extended operation.
The staff will use risk insights to focus the breadth and depth of its review of plant specific operating experience. However, the staffs review is not limited to risk significant systems and components because 10 CFR Part 54 is a deterministic rule. The staff must conclude that there is reasonable assurance that activities will continue to be conducted in accordance with the current licensing basis and the effects of aging will be managed during the period of extended operation for all structures and components within the scope of 10 CFR Part 54.
- 4.
Information and Other Material Necessary for the Regulatory Audit As described in the Audit Needs List
- 5.
Team Assignments Area of Review Assigned Auditors Documentation of plant specific operating experience as described in the River Bend Station corrective action program database.
Disciplines include mechanical, materials, structural, electrical and systems.
Allik, Brian Chereskin, Alexander Fu, Bart Gavula, James Holston, William Lehman, Bryce Medoff, James Mink, Aaron Nold, David Prinaris, Andrew Sadollah, Mohammad Sun, Summer Wong, Albert Yoo, Mark Buford, Angela Cuadrado de Jesus, Samuel Gardner, William Hoang, Dan Huynh, Alan Lopez, Juan Min, Seung Nguyen, Duc Otto, Ngola Rogers, Billy Sayoc, Emmanuel Thomas, George Yoder, Matthew Steve Jones
- 6.
Logistics The audit will be conducted on location at the Nuclear Energy Institute office, located in Rockville, Maryland, from of October 2 through October 13, 2017. Entrance and exit briefings will be held at the beginning and end of this audit, respectively.
- 7.
Special Requests The staff requests River Bend to provide electronic access to Entergy information, as discussed in the Audit Needs List. The NRC staff requests a suitable facility for the audit team to caucus during the audit and to hold meetings between staff and Entergy personnel.
- 8.
Deliverables An audit report should be issued to River Bend within 90 days from the end of the audit.
Operating Experience Review for the River Bend Station Unit 1, License Renewal Application Audit Needs List
- 1.
Operating Experience Keyword Review Results The staff requests electronic access, using Entergy equipment, to the results of the operating keyword list query of Entergys corrective action database. The results are expected to be in an excel workbook, organized by keywords.
- 2.
Corrective Action Program Database The staff requests electronic access, using Entergys equipment, to the Entergys corrective action database to perform independent searches of the database.
- 3.
License Renewal Portal The staff requests electronic access, using Entergys equipment, to the license renewal portal.