Public Meeting Between USNRC Oversight Panel and FirstEnergy Nuclear Operating Company August 12, 2003

Davis-Besse Oversight Panel - Public Meeting August 2003 PURPOSES OF THIS MEETING

  • Discuss Licensees Progress on Implementing the Return to Service Plan
  • Inform the Public of the NRCs Oversight Panel Activities 2

Davis-Besse Oversight Panel - Public Meeting August 2003 AGENDA

  • Introduction and Opening Remarks
  • Summary of July 9th Public Meetings
  • Discussion of Significant NRC Activities Since July 9th Public Meeting
  • Licensee Presentation on the Status of Their Return to Service Plan
  • Adjourn NRC meeting with FENOC

<break>

  • Public Comments and Questions of NRC
  • Adjourn Meeting 3

Davis-Besse Oversight Panel - Public Meeting August 2003

SUMMARY

OF JULY 9, 2003 PUBLIC MEETING

  • Topics Discussed

- Containment Activities / Preparation for Heat-Up

- High Pressure Injection Pump Modification Update

- Operations Performance

- Engineering Performance

- Maintenance Performance

- Safety Margin Improvements

- Restart Schedule Milestones

  • Transcripts of the July 9, 2003 meetings are available on our web site.

http://www.nrc.gov/

4

Davis-Besse Oversight Panel - Public Meeting August 2003 SIGNIFICANT NRC ACTIVITIES SINCE JULY 9 PUBLIC MEETING

  • Issued Preliminary Significance Determination for Yellow Finding Regarding Containment Sump Clogging Issue
  • Issued Management and Human Performance Root Cause Assessment Report 02-18
  • Closed Restart Checklist Item 2b - Containment Vessel Restoration Following Reactor Pressure Vessel Head Replacement
  • Closed Restart Checklist Item 3h - Radiation Protection Program 5

Davis-Besse Oversight Panel - Public Meeting August 2003 SIGNIFICANT NRC ACTIVITIES SINCE JULY 9 PUBLIC MEETING

  • Update of Confirmatory Action Letter 3-02-001C
  • Issued NRC Integrated Inspection Report 03-15 (Preliminary Yellow Finding) 6

Davis-Besse Oversight Panel - Public Meeting August 2003 CONTINUING NRC ACTIVITIES

  • System Health Reviews / Design Issues Inspection
  • Safety Culture / Safety Conscious Work Environment Inspection
  • Corrective Action Team Inspection
  • Resident Inspection 7

Davis-Besse Oversight Panel - Public Meeting August 2003 UPCOMING NRC ACTIVITIES

  • Preparation for Under-Vessel Head Inspection
  • Public Meetings to Discuss Licensee Assessment of Safety Culture 8

Davis-Besse Oversight Panel - Public Meeting August 2003 UPCOMING NRC ACTIVITIES

  • Preparation for Restart Assessment Team Inspection
  • Preparation for Review of Inaccurate / Incomplete Required Records and Submittals Inspection
  • Follow up on Potentially Risk-Significant Licensee Event Reports
  • Confirmatory Action Letter Update
  • Commission Meeting on Davis-Besse Investigatory and Enforcement Issues 9

Davis-Besse Oversight Panel - Public Meeting August 2003 PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION PORT CLINTON, OHIO August 12th, 2003, 7:00 pm EDT Purpose of Meeting:

Inform the Public of the NRCs Oversight Panel Activities 10

Davis-Besse Oversight Panel - Public Meeting August 2003 GOALS

  • Brief Public With Results of Afternoon Meeting with FENOC
  • Receive Comments and Questions From Public To ensure we hear all comments, please limit comments or questions to 5 minutes each. We will follow the format from previous meetings where we start with local members of the public.