ML12221A264
| ML12221A264 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 08/09/2012 |
| From: | Division of Nuclear Materials Safety III |
| To: | |
| Atif Shaikh | |
| References | |
| Download: ML12221A264 (29) | |
Text
NRC Public Meeting NRC Public Meeting Davis Besse Shield Building Cracks August 9, 2012
Welcome Ch l
C t
2 Charles Casto Regional Administrator NRC Region III
Meeting Information Steve Reynolds 3
y Director Division of Reactor Safety NRC Region III
Meeting Agenda
- Meeting Purpose & Background
- Licensee Presentation 4
- NRC Shield Building Inspection & Conclusions
- License Renewal Inspections
- Summary
- Break
- Public Questions and Comments
Meeting Purpose
- Inform public about safety of Davis Besse shield building through:
Presentation by licensee on results of root cause evaluation and corrective actions Presentation by NRC on NRCs inspection of licensees root cause activities and actions going forward 5
Safety Issue
- On October 10, 2011, licensee promptly notified NRC upon identifying cracking in the Davis Besse shield building.
6
- NRC determined there was no immediate safety concern. The plant was shut down at the time.
- NRC conducted a rigorous inspection resulting in licensee performing additional testing and more extensive, sophisticated calculations.
- Shield building is safe despite the cracking NRC Safety Conclusion Regarding Operability 7
- Licensee could safely restart the plant
- Public meeting held 1/5/12 on NRCs safety conclusion 7
Confirmatory Action Letter Issued to Licensee
- Letter dated December 2, 2011 8
- Implement a short-term monitoring program
- Complete a root cause evaluation
- Develop and implement corrective actions
- Develop and implement a long-term monitoring program
Additional NRC Actions to Ensure Continued Safety of the Shield Building
- Conducted a follow-up inspection of root cause evaluation and proposed corrective actions
- Continued relentless monitoring of licensee correction actions
- Scrutinous oversight of licensee actions going forward 9
Introductions - NRC
- Charles Casto, Regional Administrator, Region III
- Steve Reynolds, Director, Division of Reactor Safety 10
- Ann Marie Stone, Chief, Engineering Branch 2
- Melvin Holmberg, Senior Reactor Inspector
- James Neurauter, Senior Reactor Inspector
- Daniel Kimble, Senior Resident Inspector
Introductions - NRC
- Jared Heck, Meeting Facilitator
- David Hills, Chief, Engineering Branch 1 J
C Chi f R t
P j
t B
h 6 11
- Jamnes Cameron, Chief, Reactor Projects Branch 6
- Brian Harris, Project Manager, DLR, Office of Nuclear Reactor Regulation
- Bryce Lehman, Structural Engineer, DLR, Office of Nuclear Reactor Regulation
- Michael Mahoney, Project Manager, DORL, Office of Nuclear Reactor Regulation
First Energy Nuclear Operating Company 12 Operating Company (FENOC) Introductions and Presentation
NRC Root Cause Inspection Mel in Holmberg 13 Melvin Holmberg Senior Reactor Inspector Division of Reactor Safety NRC Region III
NRC Safety Focused Inspection
- Early NRC Engagement with the Root Cause Investigation - December of 2011.
- Provided NRC with real time results 14
- Facilitated independent NRC observations and interaction with licensee and vendor staff
- Facilitated coordination of independent NRC inspections onsite 14
NRC Safety Focused Inspection
- NRC Actions - Assess Validity of the Causes of the Shield Building Cracking.
- Team of 4 NRC Inspectors 15 Team of 4 NRC Inspectors
- Independently observed cracks in:
- 1. SB access opening
- 2. Core bores
- 3. Removed core samples
- Observed offsite vendor test facilities-core bore samples 15
NRC Safety Focused Inspection
- Reviewed licensee and vendor Root Cause Reports
- Evaluated licensee cause determination process
- Evaluated inputs/assumptions/modeling for SB calculations
- Evaluated licensee and vendor experience and education 16
- Sufficient basis established for the causes of the shield building laminar cracking:
NRC Conclusion - Causes of Shield Building Cracking 17
- Blizzard of 1978
- Lack of exterior moisture barrier
- Structural design elements of shield building 17
Basis for NRC Conclusion
- Systematic Root Cause Process Followed with Qualified Subject Matter Experts
- Experts in concrete degradation and root cause 18 Experts in concrete degradation and root cause analysis considered and eliminated a wide range of possible causes
- Comprehensive analysis in accordance with well known and accepted root cause processes 18
Basis for NRC Conclusion
- Causes Supported by:
- Objective Evidence:
j Weather records, core bore sample and impulse response test results
- Analytical Analysis Five analytical model results
- Operating Experience Similar structures identified with laminar cracking which supports the identified causes 19
- The NRC determined that the licensees proposed corrective actions, if adequately implemented, should keep the shield building safe to operate NRC Conclusions - Corrective Actions 20 keep the shield building safe to operate.
20
Basis of NRC Conclusion -
Correction Actions
- Exterior moisture barrier to prevent additional moisture related laminar cracking.
21
- Procedures to examine the exterior moisture barrier and monitoring of extent of existing cracking
- NRC follow-up inspections to closely monitor licensee implementation of corrective actions 21
NRC Identified Weakness in Root Cause Report
- Certain details associated with supporting the licensees analysis and conclusions 22 licensee s analysis and conclusions
- The licensee entered these weaknesses into the Corrective Action Program
- Two examples for which the corrective actions proposed by licensee were too narrow
- The licensee entered these observations into the Corrective Action Program.
22
License Renewal Inspections 23 Ann Marie Stone Engineering Branch Chief Division of Reactor Safety NRC Region III
License Renewal Perspectives
- Operating Experience has a KEY role in the License Renewal process
- Incorporation of Shield Building cracking in the 24 p
g g
License Renewal process
- License Renewal application process
- Perform detailed technical reviews and audits
- Perform independent inspections
License Renewal Perspectives
- Davis Besse License Renewal Inspections
- In-plant walk downs, and review of current credited programs, planned future programs/actions, and operating experience.
25 p
g p
g p
- Determine if licensees programs, when implemented, will be consistent with requirements.
- Inspection Results Documented in Inspection Reports 05000346/2011010 and 05000346/2011012
License Renewal Perspectives
- Current and future actions
- Application: Licensees proposed aging management program titled Shield Building 26 Monitoring Program being reviewed
- (If a renewed license is granted) Post Renewal:
Additional NRC inspections to verify the licensee completed the commitments and license conditions
Regulatory Overview
- Shield Building is safe
- NRC continues to provide close oversight going forward
- NRC will keep the public informed 27
Summary Ch l
C t
28 Charles Casto Regional Administrator NRC Region III
Meeting Contacts
- Followup Questions - Contact the NRC Region III Office of Public Affairs Vikt i
Mitl
/ P Ch d
thil Viktoria Mitlyng / Prema Chandrathil Tel: (630) 829-9500 OPA3@nrc.gov 29