Public Meeting Between USNRC Oversight Panel and FirstEnergy Nuclear Operating Company September 10, 2003
2 Davis-Besse Oversight Panel - Public Meeting September 2003 PURPOSES OF THIS MEETING
- Discuss Licensees Progress on Implementing the Return to Service Plan
- Inform the Public of the NRCs Oversight Panel Activities
3 Davis-Besse Oversight Panel - Public Meeting September 2003 AGENDA
- Introduction and Opening Remarks
- Summary of August 12th Public Meetings
- Discussion of Significant NRC Activities Since August 12th Public Meeting
- Licensee Presentation on the Status of Their Return to Service Plan
- Adjourn NRC meeting with FENOC
<break>
- Public Comments and Questions of NRC
- Adjourn Meeting
4 Davis-Besse Oversight Panel - Public Meeting September 2003
SUMMARY
OF AUGUST 12, 2003 PUBLIC MEETING Topics Discussed
- High Pressure Injection Pumps
- Electrical Distribution System
- Plant Readiness for Mode 4
- Operations Start-Up Plan
- Restart Milestones/Actions
- Safety Culture Assessments Results and Readiness for Mode 4/3
- Quality Assurance Oversight
- Transcripts of the August 12, 2003 meetings are available on our web site.
5 Davis-Besse Oversight Panel - Public Meeting September 2003 SIGNIFICANT NRC ACTIVITIES SINCE AUGUST 12 PUBLIC MEETING
- Closed Restart Checklist Item 2c1 - Emergency Core Cooling System and Containment Spray System Sump
- Closed Restart Checklist Item 6g - License Amendment Request for High and Low Pressure Injection Systems
- Confirmatory Action Letter Update
6 Davis-Besse Oversight Panel - Public Meeting September 2003 CONTINUING NRC ACTIVITIES
- System Health Reviews / Design Issues Inspection
- Corrective Action Team Inspection
- Safety Culture / Safety Conscious Work Environment Inspection
- Resident Inspection
7 Davis-Besse Oversight Panel - Public Meeting September 2003 UPCOMING NRC ACTIVITIES Under-Vessel Head Inspection Public Meeting to Discuss Licensee Assessment and Ongoing Improvement Initiatives to Address Safety Culture Review of Inaccurate / Incomplete Required Records and Submittals Inspection Follow up on Potentially Risk-Significant Issues (Containment Emergency Sump and High Pressure Injection Pumps)
Restart Assessment Team Inspection
8 Davis-Besse Oversight Panel - Public Meeting September 2003 PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION PORT CLINTON, OHIO September 10th, 2003, 7:00 pm EDT Purpose of Meeting:
Inform the Public of the NRCs Oversight Panel Activities
9 Davis-Besse Oversight Panel - Public Meeting September 2003
- Brief Public With Results of Afternoon Meeting with FENOC
- Receive Comments and Questions From Public To ensure we hear all comments, please limit comments or questions to 5 minutes each. We will follow the format from previous meetings where we start with local members of the public.
GOALS