Licensee Slides for Davis-Besse Annual Assessment Meeting
ML102150118
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/29/2010
From:
FirstEnergy Nuclear Operating Co
To:
NRC/RGN-III/DRMA
Shared Package
ML100550359 List:
References
Download: ML102150118 (6)


Text

NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station July 29, 2010

Participants Barry Allen - Site Vice President Brian Boles - Director, Site Operations Clark Price - Director, Performance Improvement John Dominy - Director, Maintenance Vito Kaminskas - Director, Engineering NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station 7-29-10 2

2009 Accomplishments Safe, Reliable, and Cost-Effective Operations

- Unit Capability Factor = 95.07%

- Force Loss Rate = 0.03%

Successful ERO Evaluated Exercise Key Regulatory Activities

- Problem Identification and Resolution Inspection (April)

- Emergency Preparedness Evaluated Exercise (May)

- Initial Licensed Operator NRC Examinations (July)

- Emergency Actions Levels Conversion (September)

- Component Design Bases Inspection (October - November)

NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station 7-29-10 3

June 25, 2009 - Switchyard Event Inadequate Emergency Classification Root cause investigation performed as a result of the NRC finding

- Inadequate Change Management - procedure change that revised the Explosion Definition was not communicated effectively

- Less than adequate communications - Security personnel who witnessed the switchyard explosion did not effectively communicate the information to the Control Room Corrective Actions

- Training for Security on EALs, interface with Operations, and the importance of precise communications

- Revised Emergency Response continuing training to include off-normal procedures

- Revised Emergency Classification procedure to provide direct tie to off-normal procedures NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station 7-29-10 4

2010 Key Regulatory Interest Activities Inspections

- Engineering Inservice Inspection (March)

- Special Inspection Team (March-Present)

- Radiation Protection Outage Baseline (Access Control, ALARA) Inspection (March)

- Triennial Fire Protection Inspection (April-May)

- Emergency Preparedness Baseline Inspection (April)

- Radiation Protection Access Control, ALARA Planning, NRC PIs (August)

- Security Access Control, Control of Safeguards Information, Performance Indicators Inspection (August)

- Radiological Monitoring & Radioactive Material Control (November)

NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station 7-29-10 5

2010 Key Focus Areas Station Priorities

- Safe, Reliable, and Cost-Effective Operations

- 16th Refueling Outage

- Operations Training Accreditation Renewal

- Defect-Free Fuel Performance

- Human Performance and Industrial Safety Performance Improvements

- Plant Life Extension

- Recognize and Celebrate Success NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station 7-29-10 6