IR 05000346/2022004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000346/2022004 and 07200014/2022001
ML23038A204
Person / Time
Site: Davis Besse  
Issue date: 02/09/2023
From: Billy Dickson
NRC/RGN-III/DORS/RPB2
To: Tony Brown
Energy Harbor Nuclear Corp
References
EA-22-137 IR 2022001, IR 2022004
Download: ML23038A204 (1)


Text

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000346/2022004 AND 07200014/2022001

Dear Terry Brown:

On December 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Davis-Besse Nuclear Power Station. On January 24, 2023, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Billy C. Dickson, Jr., Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket Nos. 05000346 and 07200014 License No. NPF-3

Enclosure:

As stated

Inspection Report

Docket Number:

05000346 and 07200014

License Number:

NPF-3

Report Number:

05000346/2022004 and 07200014/2022001

Enterprise Identifier:

I-2022-004-0043 and I-2022-001-0113

Licensee:

Energy Harbor Nuclear Corp.

Facility:

Davis-Besse Nuclear Power Station

Location:

Oak Harbor, OH

Inspection Dates:

October 01, 2022 to December 31, 2022

Inspectors:

B. Bergeon, Senior Operations Engineer

R. Cassara, Resident Inspector

J. Cassidy, Senior Health Physicist

R. Edwards, Branch Chief

G. Hansen, Senior Emergency Preparedness Inspector

T. Henning, Operations Engineer

J. Kutlesa, Emergency Preparedness Inspector

D. Mills, Senior Resident Inspector

J. Nance, Senior Operations Engineer

J. Robbins, Senior Resident Inspector

Approved By:

Billy C. Dickson, Jr., Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Davis-Besse Nuclear Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On December 5, 2022, the unit was shut down to replace the reactor coolant pump 1-2 seal. The unit was returned to rated thermal power on December 19, 2022. At 1412 ET on December 23, 2022, operators commenced a technical specification required reactor shutdown due to a lowering level in the intake forebay caused by severe weather. The shutdown was halted at 87.5 percent power and the unit was returned to full rated power later on December 23 after NRC granted verbal approval of a notice of enforcement discretion to allow continued operation with reduced intake forebay level. The unit remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems:

ultimate heat sink, service water, and component cooling water.

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated that flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Emergency diesel generator 2 following emergency diesel generator 1 surveillance run during the week ending October 15, 2022
(2) Fire protection system after repair during the week ending November 19, 2022
(3) Emergency diesel generator 1 following emergency diesel generator 2 surveillance run during the week ending November 26, 2022
(4) Decay heat during reduced reactor coolant system inventory during the week ending December 10, 2022
(5) Emergency feedwater system following outage during the week ending December 24, 2022

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the service water system during the week ending October 22, 2022.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Protected area yard while main and auxiliary transformer deluge systems were out of service for repairs, fire areas MA, MB, MC, ME, MF, MH, and OS during the week ending November 12, 2022
(2) Emergency core cooling system train 1 room 105, fire area AB during the week ending December 17, 2022
(3) Containment closeout walkdown, fire areas D, AB, and A during the week ending December 17, 2022

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during a live fire drill during the week ending October 8, 2022.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Manholes MH 3045 and MH 3001 following sump pump replacement during the week ending December 3, 2022

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Ultimate heat sink during the week ending December 24, 2022

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification biennial written examinations and the annual operating tests administered from October 17, 2022 through December 2, 2022.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on December 2, 2022.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

The inspectors identified one potential violation associated with this review. This issue is documented in NRC Inspection Report 2022091.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

Problem Identification and Resolution The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated requalification annual simulator evaluation drills on October 19, 2022.
(2) The inspectors observed and evaluated annual simulator evaluation drills on October 26, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) AFW train 1 agastat relay replacement during the week ending November 12, 2022

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) RCP seal replacement during the week ending December 17, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Risk management during emergent fire protection system maintenance during the week ending November 26, 2022
(2) AFW sticking agastat during the week ending November 12, 2022
(3) Yellow risk for reduced inventory to remove handholes in preparation for reactor coolant pump seal replacement during the week ending December 10, 2022
(4) Yellow risk for reduced inventory below flange level for reactor coolant pump seal replacement during the week ending December 10, 2022
(5) Yellow risk to fill and vent the RCS after reactor coolant pump seal replacement during the week ending December 17, 2022
(6) Source range nuclear instrumentation replacement and calibration during the week ending December 24, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) TC computer point during the week ending October 22, 2022
(2) Annunciator panel 4 after power failure during the week ending December 3, 2022
(3) Decay heat valves DH11, DH12, DH48, DH48A during the week ending December 17, 2022
(4) Electrical penetration 2 using excessive nitrogen to maintain pressure during the week ending December 17, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Control room door 509 frame reinforcement during the week ending December 24, 2022

Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03) (1 Sample)

(1) The inspectors verified the site SAMG were updated in accordance with the PWR generic severe accident technical guidelines and validated in accordance with NEI 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, Revision 1.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1) Service water pump 3 after scheduled maintenance during the week ending October 29, 2022
(2) Auxiliary feedwater train 1 quarterly test following agastat relay replacement during the week ending November 12, 2022
(3) Emergency diesel generator 1 monthly test after replacement of pressure control and regulating pilot valves during the week ending November 12, 2022
(4) Component cooling water pump 1 after scheduled maintenance during the week ending December 3, 2022
(5) Source range nuclear instrument 1 following replacement during the week ending December 17, 2022
(6) Personnel hatch local leak rate test during the week ending December 17, 2022

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated maintenance outage activities related to reactor coolant pump 1-2 seal replacement from December 5 to December 19.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Inservice Testing (IP Section 03.01) (2 Samples)

(1) High pressure injection quarterly test during the week ending October 29, 2022
(2) Auxiliary feedwater pump 2 during the week ending November 12, 2022

RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) Reactor coolant system leak rate testing during the week ending November 26, 2022

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes:

10 CFR 50.54(q)3 Screen/Evaluation: DB-2020-015-00, 09/08/2020 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Emergency response organization training and tabletop exercise on November 8,

RADIATION SAFETY

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Sampling and Analysis (IP Section 03.02) (2 Samples)

Inspectors evaluated the following effluent samples, sampling processes and compensatory samples:

(1) Station vent - weekly grab sample
(2) Radiative waste storage building - compensatory action

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) April 1, 2021 through September 30, 2022

MS06: Emergency AC Power Systems (IP Section 02.05) (1 Sample)

(1) July 1, 2021 through September 30, 2022

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) July 1, 2021 through September 30, 2022

MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)

(1) July 1, 2021 through September 30, 2022

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) October 1, 2021 through September 30, 2022

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) October 1, 2021 through September 30, 2022

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) ICS11A (Atmospheric vent valve 2) carbon bushing wrong size - 2022-02351
(2) Reactor coolant system unidentified leakage trend

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends related to ground settling and sink holes that might be indicative of a more significant safety issue.

71153 - Follow-Up of Events and Notices of Enforcement Discretion Notice of Enforcement Discretion (NOED) (IP Section 03.04)

(1) The inspectors evaluated licensee actions related to severe weather conditions on December 23-25, including a seiche on Lake Erie, that decreased the plant intake canal level to below the technical specification required 562 feet above sea level. At 1412 ET on December 23, the licensee petitioned the NRC for enforcement discretion. At 1640 ET NRC granted verbal approval for a notice of enforcement discretion [EPID: I-2022-004-0043] to allow continued plant operation during the period of reduced intake canal level. The events are discussed in greater detail in the licensees written request (ADAMS Accession number ML22362A109) and the NRC response (ADAMS Accession number ML22363A561). The NOED can be accessed at http://www.nrc.gov/reading-rm/doc-collections/enforcement/notices/noedreactor.html.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855 - Operation of an ISFSI Operation of an ISFSI

(1) The inspectors evaluated the licensees activities related to the long-term operation and monitoring of its Independent Spent Fuel Storage Installation (ISFSI). The inspectors reviewed relevant documentation remotely during the weeks of October 10 and October 17, 2022, and were onsite on October 18, 2022. During the onsite walkdown, the inspector toured the ISFSI and evaluated the material and radiological conditions of the ISFSI pad and loaded TN NUHOMS 24P, 32PTH, and EOS 37PTH systems. The inspectors verified that radiological conditions on the ISFSI pad were as expected during the walkdown.

Since the last inspection, the inspectors evaluated corrective action documents and changes performed in accordance with 10 CFR 72.48, "Changes, Tests, and Experiments." The inspectors also reviewed the surveillance procedure and interviewed operations staff regarding daily checks of the loaded horizontal storage modules.

INSPECTION RESULTS

Observation: ICS11A (Atmospheric Vent Valve 2) Carbon Bushing Wrong Size 71152A The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

In March 2022, during the performance of atmospheric vent valve #2 scheduled maintenance, the licensee found a stem-packing carbon bushing broken. Licensee personnel determined the installed bushing to be incorrect and that the supplied replacement part was also wrong.

The licensee determined that the incorrect part was supplied for the previous maintenance and the scheduled maintenance due to errors in the licensees supply software. The licensee corrected the supply software's mistakes and installed the correct carbon bushing. The inspectors reviewed the circumstances leading to this incident, the licensee's corrective actions, and extent of condition. The inspectors also reviewed surveillance test procedures, drawings, and work orders for both atmospheric vent valves. No findings were identified.

Observation: Reactor Coolant System Unidentified Leakage Trending Higher 71152A The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

The licensee detected an increasing trend in reactor coolant system unidentified leakage following reactor coolant pump 1-2 seal replacement during the refueling outage in April 2022. Residents verified that the licensee followed their process to investigate the elevated unidentified leakage. The licensee did not identify the source of the leakage, but it was suspected to be an unmeasured flow past the seal leak-off measuring device. Due to this indication and other indications pointing to a damaged or degrading seal third stage, the licensee replaced the seal during a maintenance outage in December 2022. Following this seal replacement, the unidentified leakage returned to the expected range. The resident inspectors verified that licensee actions were in accordance with their procedures and observed inspections of infrequently accessed locations, including containment. Resident inspectors continue to monitor unidentified leakage independent of the licensee monitoring program. No findings were identified.

Observation: Ground Settling/Sinkholes 71152S The inspectors reviewed the licensees corrective action program for potential adverse trends related to ground settling and sinkholes that might indicate of a more significant safety issue.

During the review period for this inspection sample, the inspectors noted several issues related to ground settling. The licensee previously identified similar problems over the previous several years. The inspectors determined that the licensee identified these issues and that the licensee implemented corrective actions. Specific examples associated with this trend included but were not limited to:

  • Sinkhole near Security Warehouse (2021-01278)
  • Sinkhole under sidewalk (2021-08529)
  • Sinkhole training center contractor lot (2022-06310)
  • Cooling Tower Bypass Pipe Support Settlement/Sinkhole (2022-02401)
  • Potential Sink Hole Identified in Personnel Walkway between PSF and South PAC (2022-09856)
  • Potential sinkhole near Water Treatment Plant (2022-04366)
  • Potential Sinkhole Near AC Transformer (2022-07790)
  • North Underground Fire Protection Loop Pipe Rupture (2022-07575)
  • Small Sinkhole Identified South of Wellness Center (2022-04199)
  • Sinkhole Identified in security isolation zone (2022-04728)
  • Potential Sinkhole North of Circulating Water Pump House (2022-05651)
  • Sink Holes In The Protected Area (2021-05696)

Individually, none of these examples suggested an ongoing problem, but the inspectors determined that they may indicate a potential weakness when viewed in the aggregate.

Specifically, for these and other issues, the station may be missing the opportunity to identify and resolve deficiencies before a failure manifests and adversely impacts the plant. The inspectors provided these observations to the licensee and the inspectors will continue monitoring the licensees actions to identify and correct similar issues.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On November 4, 2022, the inspectors presented the ISFSI Interim Exit inspection results to T. Brown, Site Vice President, and other members of the licensee staff.

On December 2, 2022, the inspectors presented the emergency action level and emergency plan changes inspection results to G. Wolf and other members of the licensee staff.

On December 8, 2022, the inspectors presented the radiation protection inspection results to C Jackson, General Plant Manager, and other members of the licensee staff.

On January 5, 2023, the inspectors presented the Licensed Operator Requalification Program Annual Testing Summary Results inspection results to C. Jackson, General Plant Manager, and other members of the licensee staff.

On January 18, 2023, the inspectors presented the Biennial Licensed Operator Requalification Program Exit inspection results to T. Brown, Site Vice President, and other members of the licensee staff.

On January 24, 2023, the inspectors presented the integrated inspection results to T. Brown, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20-07214

Aging Management Inspections

09/16/2020

20-07215

DSC 24P-R01 Was Not Rotated 180-Degrees

09/16/2020

20-07216

Foreign Material Identified on the Rail During AMP

Inspections

09/10/2020

20-08358

Exceeding Groundwater Chemistry Limits

11/18/2020

Corrective Action

Documents

21-05199

NCV From Davis-Besse 2019 EOS Campaign

08/06/2021

Corrective Action

Documents

Resulting from

Inspection

22-08332

Missing FME Plugs on DB-HSM1 to DB-HSM4

11/02/2022

CFR 72.212 Evaluation Report

CFR 72.212 Evaluation Report for the NUHOMS EOS

System

HSM Basemat Survey Results

09/01/2021

2.48 Screen No.

20-00443

HSM-80 Door Plate Helicoil Inserts

2.48 Screen No.

20-01045

ISFSI Aging Management Program

Miscellaneous

2.48 Screen No.

20-01271

Shielding Request for HSM Aging Management Inspections

Procedures

DB-NE-03400

Horizontal Storage Monitoring

DB-M-20200624-3

Dry Fuel Storage Pad

06/24/2020

DB-M-20210610-1

Dry Fuel Storage Pad

06/10/2021

Radiation

Surveys

DB-M-20220615-2

Dry Fuel Storage Pad

06/15/2022

60855

Self-Assessments QFO-2021-0001

ISFSI Audit

04/02/2021

DB-ME-09521

Preventive Maintenance and Circuit Testing of Freeze

Protection and Heat Tracing

DB-OP-06331

Freeze Protection and Electrical Heat Trace

DB-OP-06913

Seasonal Plant Preparation Checklist

71111.01

Procedures

RA-EP-02830

Flooding

71111.04

Corrective Action

Documents

22-06915

EDG Air Compressor 1 Air Leak

09/10/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DB-FP-04031

Quarterly Fire Valve Alignment Verification

DB-OP-06012

Decay Heat and Low-Pressure Injection System Operating

Procedure

DB-OP-06234

Emergency Feedwater System

DB-OP-06261

Service Water System Operating Procedure

DB-OP-06316

Diesel Generator Operating Procedure

Procedures

DB-OP-06316

Diesel Generator Operating Procedure

PFP-AB-105

ECCS Pump Room 1-1, Rooms 105, Fire Area AB-01

PFP-AB-105

ECCS Pump Room 1-1, Rooms 105, Fire Area AB-01

PFP-CB-214

Core Flooding Tank Area, Room 214, Fire Area D

PFP-CB-215

Let Down Coolers Area, Room 215, Fire Area D

PFP-CB-216

Steam Generator West D Ring Area, Room 216, Fire Area

D

PFP-CB-218

Steam Generator East D Ring Area, Room 218, Fire Area D

PFP-CB-317

Containment Air Cooler Area, Room 317 and Room 317A,

Fire Area D

PFP-CB-EL603

Fuel Transfer Pool and North and West 603' Elevation,

Rooms 219, 407, and 410A, Fire Area D

PFP-CV-EL565

North Area 565' Elevation, Rooms 213, 217, and Normal

Sump Area, Fire Area D

PFP-YD-PROT

Protected Area Yard, General, Manholes, Junction Box,

Transformers, and Auxiliary Feedwater Exhaust Enclosure,

Fire Areas MA, MB, MC, ME, MF, MH, and OS

71111.05

Fire Plans

PFP-YD-STRAT

Protected Area Yard Strategy, Explosion and/or Large

Accelerant Fed Fire Involving Large Areas of the Plant

22-08207

Standing Water in Electrical Manhole MH 3001

10/28/2022

Corrective Action

Documents

22-09251

Aux Boiler Deaerator Level Control Valve CD1666B Failed

Open

2/05/2022

Procedures

RA-EP-02880

Internal Flooding

200605395

Replace Sump Pump - MH3045

11/04/2022

71111.06

Work Orders

200898057

Replace Motor CNDS PIT West Sump 1-1 Pump B

2/05/2022

C-69

Construction Water Intake

71111.07A

Drawings

TECW-201-BI

Intake Canal Water Intake and Discharge

2/20/1972

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

System

Description

Service Water System for Energy Harbor Nuclear Davis-

Besse Nuclear Power Station, Unit 1

DB-ME-09521

Preventive Maintenance and Circuit Testing of Freeze

Protection and Heat Tracing

DB-OP-06331

Freeze Protection and Electrical Heat Trace

Procedures

DB-OP-06913

Seasonal Plant Preparation Checklist

71111.11A

Miscellaneous

22 Annual

Licensed Operator

Requal Test

Results

Davis-Besse 2022 Annual LORT Exam Summary Results

2/02/2022

Corrective Action

Documents

Resulting from

Inspection

22-09503

22 NRC 71111.11 Inspection: Continuous Training

Participation

2/15/2022

Engineering

Evaluations

NOBP-TR-1112

Davis-Besse Crew 2 Evaluation Annual Exam Form

11/30/2022

Operating Crew 2 Watch Standing Hours 2021-2022

22 Biennial Exam 1

DB-0779-1

Crew / Individual Performance Improvement Plan(s)

2/09/2020

None

Attendance Sheets Licensed Operator Continuing Training

Cycle

20

None

Attendance Sheets Licensed Operator Continuing Training

Cycle

21

None

Attendance Sheets Licensed Operator Continuing Training

Cycle

22

ORQ-EPE-S101

Crew 2 Requalification Scenario

ORQ-EPE-S105

Crew 2 Requalification Scenario

ORQ-EPE-S137

Crew 2 Requalification Scenario

ORQ-EPE-S139

Crew 2 Requalification Scenario

ORQ-EPE-S153

22 Annual Exam SBT

07/12/2022

OTL1POS106

Approach to Criticality

2/22/2020

OTL1POS107

Raise Power Above Low Level Limits

2/22/2020

OTLAOPDBS104

Rapid Shutdown

2/26/2021

71111.11B

Miscellaneous

Post-Event

Overcooling Plant Trip

07/08/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Testing

Simulator Based

Testing

Cycle 23 Steady State Comparison 100% Reactor Power

Simulator

Scenario Based

Testing

Cycle 23 Steady State Comparison 40% Reactor Power

Simulator

Scenario Based

Testing

Cycle 23 Steady State Comparison 75% Reactor Power

Simulator

Scenario Based

Testing Form

22 ILT Scenario 4

11/3/2021

Simulator Training

Certification Test

N2a

SHUTDOWN - FPSS to 500 Degrees

Simulator Training

Certification Test

N6

Sixty Minute Drift Test

Simulator Training

Certification Test

RTT

Computer Real Time Test

Simulator Training

Certification Test

Tab 03

Simultaneous Closure of All Main Steam Isolation Valves

Simulator Training

Certification Test

Tab 05

Trip of One Reactor Coolant Pump

Simulator Training

Certification Test

Tab 08

Double Ended Hot Leg Shear with a Coincident Loss of All

Off-Site Power

Simulator Training

Certification Test

Tab 10

The PORV Fails Fully Open and HPI Does Not Actuate

Procedures

DBBP-TRAN-0021

Simulator Configuration Control

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DBBP-TRAN-01

NRC Initial Operator License Exam Security

DBBP-TRAN-0552

Continuing Training Simulator Evaluations

NOBP-TR-1112

Conduct of Simulator Training and Evaluation

NOBR-TR-1271

Operator License Administration

NOP-TR-1010

Licensed Operator Requalification Exam Development and

Administration

NOP-TR-1280

Simulator Configuration Management

Self-Assessments Assessment ATA-

22-0659

NRC 71111.11 Inspections Preparations

21-00083

Training Simulator Phone System Stopped Working

01/06/2021

22-04375

Simulator Malfunction Could Not be Removed During an

Evaluated Scenario

05/24/2022

71111.11Q

Corrective Action

Documents

22-04403

EP Drill: Simulator Computer Point Did Not Display

Correctly

05/25/2022

ALARA Plans

2-2010

Troubleshoot/Repair/Replace Nuclear Instrumentation 1

Detector

Corrective Action

Documents

22-09351

RCP1-2 Shaft Alignment As-Found Data Out of Tolerance

2/08/2022

264

Schematic Diagram Source Range Channel Sub Assembly

'A'

Drawings

C-149

Containment Internal Structures Reactor Seal Ring Details

Sheet 2

Engineering

Evaluations

601383951

Evaluate RCP 1-2 Shaft Alignment Data

2/09/2022

End of Day Shift Package

2/10/2022

601384078

Request to Store Old NI Detector in Containment on 603'

Elevation

78A-ISN101

String Work Package

CA9900131

Degradation and Life Expectancy Tests for BF3 Detectors

Miscellaneous

ODMI 22-06

Operation with Reactor Coolant Pump 1-2 Indications of

Degraded Seal Performance

DB-MI-03452

Channel Calibration of 78A-ISN101 Source Range Neutron

Flux and Rate to RPS Channel 2

71111.12

Procedures

DB-MI-09023

RCP 1-1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DB-MM-03006

Examination of Safety Related Hydraulic Snubbers

DB-MM-09012

RCP Seal Removal and Replacement

DB-MM-09108

Removal and Installation of Snubbers

DB-MM-09117

Reactor Coolant Pump Maintenance

DB-MM-09266

Torquing

200833803

AFW Train 1 Level Control, Interlock and Flow Transmitter

Test

10/09/2022

200835994

AFW Train 1 Level Control, Interlock and Flow Transmitter

Test

11/05/2022

200835995

AFPT 1 Inlet Isolation

11/06/2022

200881008

RCP 1-2 Seal Replacement

2/05/2022

200895775

Low Suction Pressure Switch 1 AFP

11/22/2022

Work Orders

200898520

Contingent Detector Replacement, Troubleshooting

2/12/2022

ALARA Plans

2-2010

Troubleshoot/Repair/Replace Nuclear Instrumentation 1

Detector

Corrective Action

Documents

22-09383

RCP 1-2 Schedule Logic Omission

2/09/2022

264

Schematic Diagram Source Range Channel Sub Assembly

'A'

Drawings

C-149

Containment Internal Structures Reactor Seal Ring Details

Sheet 2

End of Day Shift Package

2/10/2022

Contingency Plan for RCS Drain Below Flange Level and

Operation Below 80 Inches Above the RCS Hot Leg

Centerline

11/14/2022

Shutdown Defense In-Depth Review Sheet, Forced Outage

11/14/2022

601384078

Request to Store Old NI Detector in Containment on 603'

Elevation

78A-ISN101

String Work Package

Miscellaneous

CA9900131

Degradation and Life Expectancy Tests for BF3 Detectors

DB-MI-03452

Channel Calibration of 78A-ISN101 Source Range Neutron

Flux and Rate to RPS Channel 2

71111.13

Procedures

DB-OP-06904

Shutdown Operations

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DBBP-OPS-0003

On-Line Risk Management Process

01/27/2021

NG-DB-00001

On-Line Risk Management

NOP-OP-1007

Risk Management

200833803

AFW Train 1 Level Control, Interlock and Flow Transmitter

Test

10/09/2022

200835994

AFW Train 1 Level Control, Interlock and Flow Transmitter

Test

11/05/2022

Work Orders

200835995

AFPT 1 Inlet Isolation

11/06/2022

22-02170

Electrical Penetration 101 Exceeds Maximum Allowable

Total Leakage Rate

03/14/2022

22-02902

Electrical Penetration Room 1 Nitrogen Flow High

04/01/2022

22-02950

FI6443, Nitrogen Flow to Electrical Penetration Room 2,

Reading Greater Than 550 CC/M

04/03/2022

22-07811

Shift in RCS Delta Tcold

10/16/2022

22-07891

SASS Tcold Instrument String Could Not be Returned to

Auto

10/18/2022

22-08004

Improper Crimp on RTD Lead

10/21/2022

22-08234

Reactor Coolant Loop 1 Cold Leg Narrow Range T780 Step

Change

10/30/2022

22-09292

1M23 - BACC: Leak on Pipe Cap of DH48A

2/07/2022

22-09324

1M23 - BACC: Boric Acid Deposits Identified on DH12

2/08/2022

Corrective Action

Documents

22-09351

RCP1-2 Shaft Alignment As-Found Data Out of Tolerance

2/08/2022

Engineering

Evaluations

601383951

Evaluate RCP 1-2 Shaft Alignment Data

2/09/2022

ISTB4

Pump and Valve Basis Document

Miscellaneous

ODMI 22-06

Operation with Reactor Coolant Pump 1-2 Indications of

Degraded Seal Performance

DB-MM-03006

Examination of Safety Related Hydraulic Snubbers

DB-MM-09012

RCP Seal Removal and Replacement

DB-MM-09108

Removal and Installation of Snubbers

DB-MM-09117

Reactor Coolant Pump Maintenance

DB-MM-09266

Torquing

71111.15

Procedures

DB-OP-06411

Station Annunciator Operating Procedure

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NOPB-WM-4004

Critical Maintenance Identification and Execution

200881008

Align Right 11424 RCP 1-2 Seal Rebuild with PM 2415 RCP

1-2 Seal

2/05/2022

200895721

Request Forced Outage

11/18/2022

Work Orders

200897623

Annunciator and Miscellaneous Power Supply

11/30/2022

Calculations

VBW07/B001-043

Evaluation of Auxiliary Building Masonry Wall 5337 at

Elevation 623'0"

10/10/2017

Corrective Action

Documents

2019-01345

New SAMG Input Will Not be Corrected in Initial Revision

2/13/2019

14-0629

Reinforcement of Block Wall 5337

Engineering

Changes

14-0629-001

Reinforcement of Door 509 Frame and Associated Analysis

of Block Wall 5337

Miscellaneous

Maintenance Rule

2016-08324/2016-13970

2/09/2016

DB SAMG-BASES

SAMG Bases

DPG

Diagnostic Process Guideline

NG-EN-00550

Severe Accident Management

PWROG-15015-P

PWR Owners Group Severe Accident Management

Guidelines

SAG-1

Technical Support Center Severe Accident Guideline - Initial

Response

SAG-10

Technical Support Center Severe Accident Guideline

Control SFP Level

SAG-2

Technical Support Center Severe Accident Guideline - TSC

Recommending Strategies

SAG-3

Technical Support Center Severe Accident Guideline -

Injection into Steam Generators

SAG-4

Technical Support Center Severe Accident Guideline -

Depressurize RCS

SAG-5

Technical Support Center Severe Accident Guideline - Inject

into RCS

SAG-6

Technical Support Center Severe Accident Guideline - Inject

into Containment

71111.18

Procedures

SAG-7

Technical Support Center Severe Accident Guideline -

Reduce Containment Hydrogen

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SAG-8

Technical Support Center Severe Accident Guideline -

Control Containment Pressure

SAG-9

Technical Support Center Severe Accident Guideline -

Mitigate Fission Product Release

TSG-1

Technical Support Guideline - Instrumentation

TSG-2

Technical Support Guideline - SAMG Ultimate

Decisionmaker

TSG-3

Technical Support Guideline - Site Capabilities Technical

Support Information

TSG-4

Technical Support Guideline - Benefit Consequence

TSG-5

Technical Support Guideline - Computational Aids

ALARA Plans

2-2010

Troubleshoot/Repair/Replace Nuclear Instrumentation 1

Detector

Corrective Action

Documents

22-09351

RCP1-2 Shaft Alignment As-Found Data Out of Tolerance

2/08/2022

264

Schematic Diagram Source Range Channel Sub Assembly

'A'

Drawings

C-149

Containment Internal Structures Reactor Seal Ring Details

Sheet 2

End of Day Shift Package

2/10/2022

601384078

Request to Store Old NI Detector in Containment on 603'

Elevation

78A-ISN101

String Work Package

CA9900131

Degradation and Life Expectancy Tests for BF3 Detectors

Miscellaneous

ODMI 22-06

Operation with Reactor Coolant Pump 1-2 Indications of

Degraded Seal Performance

DB-MI-03452

Channel Calibration of 78A-ISN101 Source Range Neutron

Flux and Rate to RPS Channel 2

DB-MI-05145

Source Range Detector High Voltage and Discriminator

Setting Procedure

DB-MM-03006

Examination of Safety Related Hydraulic Snubbers

DB-MM-09012

RCP Seal Removal and Replacement

DB-MM-09108

Removal and Installation of Snubbers

71111.19

Procedures

DB-MM-09117

Reactor Coolant Pump Maintenance

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DB-MM-09266

Torquing

DB-PF-03030

Service Water Pump 3 Testing

NOPB-WM-4004

Critical Maintenance Identification and Execution

200748084

PM 6636 Replace PCV2988 and PCV2988A

10/13/2022

200767904

PM 6142 MP43-1, Motor Testing, CCW 101 P

10/10/2022

200804006

PM 2907 Calculation EDG 1 Air Receiver

09/19/2022

200833294

AFP 1 Quarterly Test

10/04/2022

200835995

AFPT 1 Inlet Isolation

11/06/2022

200836400

AFP 2 Quarterly Test

11/15/2022

200840426

CCW Pump 1 Quarterly Test

11/29/2022

Work Orders

200881008

Align Right 11424 RCP 1-2 Seal Rebuild with PM 2415 RCP

1-2 Seal

2/05/2022

71111.20

Miscellaneous

Restart readiness Package

DB-SP-03357

RCS Water Inventory Balance

DB-SP-03357

RCS Water Inventory Balance

Procedures

DB-SP-03357

RCS Water Inventory Balance

71111.22

Work Orders

200836400

AFP 2 Quarterly Test

11/15/2022

DBNPS

Emergency Plan

Davis-Besse Nuclear Power Station Emergency Plan

Miscellaneous

DBNPS

Emergency Plan

Davis-Besse Nuclear Power Station Emergency Plan

71114.04

Procedures

CFR 50.54(q)3

Screen/Evaluation:

DB-2020-015-00

DBNPS Emergency Plan Revision 35

09/08/2020

NOP-LP-5501

Accident Assessment

NOP-LP-5502

Event Classification

NOP-LP-5503

Emergency Notifications

NOP-LP-5504

Protective Measures

NOP-LP-5505

Facility Activation, Operation and De-Activation

71114.06

Procedures

NOP-LP-5506

Termination and Recovery

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Resulting from

Inspection

22-09428

NRC Observation of Alpha Survey on RCP 1-2 Seal

2/13/2022

Miscellaneous

Standing Order

22-001

Alpha Contamination Risk Level Assignments

01/04/2022

Procedures

NOP-OP-4903

Determination of Alpha Monitoring Levels

Radiation

Surveys

DB-I-20220328-10

RCP 1-2 Seal Replacement

03/28/2022

71124.01

Radiation Work

Permits (RWPs)

2-2005

Reactor Coolant Pump 1-2 Seal

11/23/2022

CR-2022-09426

NRC identified Tritium Sampling Basis Methodology Was

Not Determined

2/13/2022

Corrective Action

Documents

Resulting from

Inspection

CR-2022-09427

NRC Observation Low Level Radwaste Storage Facility

Effluent Release Point

2/13/2022

White Paper - DBNPS Tritium Sampler Flow Rate Inquiry

Date Not

Provided

71124.06

Miscellaneous

Davis-Besse Low-Level Radiation Waste Storage Facility

Position

Date Not

Provided

Corrective Action

Documents

22-02351

1R22 Repack of AVV DB-ICS11A Identified Incorrect

Carbon Bushing Size

03/17/2022

Drawings

645141-1

Drag Valve

D

ASME 2008a

Section XI,

Division 1

Article IWA-4000 Repair/Replacement Activities

04/14/2010

Miscellaneous

Vendor Certificate

Certificate of conformance, Control Components Inc.

06/30/1994

Procedures

DB-PF-03440

Atmospheric Vent Valves, ICS11A and ICS11B, Operability

Test

200817842

Repack ICS11A during IR11

03/14/2022

71152A

Work Orders

200822911

Main Steam Line 1 Atmospheric Vent Valve

03/29/2022

21-01278

Sinkhole Near Security Warehouse

2/25/2021

21-02075

Sinkhole in Zone 9 Degrading Stone Near Perifield

03/21/2021

21-02350

Sink Hole in Owner Controlled Area

03/29/2021

71152S

Corrective Action

Documents

21-04199

Small Sinkhole Identified South of Wellness Center

05/24/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

21-04366

Potential Sinkhole Near Water Treatment Plant

06/01/2021

21-04728

Sinkhole Identified in Security Isolation Zone

06/16/2021

21-05651

Potential Sinkhole North of Circ Pump House

07/25/2021

21-05696

Sinkholes in the Protected Area

07/27/2021

21-08529

Sinkhole Under Sidewalk

11/08/2021

22-01260

Degraded Storm Drain and Sinkhole Identified in ROCA

2/18/2022

22-02401

Cooling Tower Bypass Pipe Support Settlement/Sinkhole

03/19/2022

22-02401

Cooling Tower Bypass Pipe Support Settlement/Sinkhole

03/19/2022

22-03985

Duct Bank Not on Site Drawings Discovered During

Sinkhole Excavation

05/10/2022

22-06310

Sinkhole Training Center Contractor Lot

08/16/2022

22-06310

Sinkhole Training Center Contractor Lot

08/16/2022

22-06365

Assessment Identified Temporary Configuration Change

Process Non-Compliance Issues

08/17/2022

22-06519

ECCS Sump Pump Discharge Piping Temporary Leak

Repairs to Remain in Place for additional Cycle

08/24/2022

22-06639

Temporary Leak Repairs that Remained in Place Past 1R22

08/29/2022

22-07031

Possible Sinkhole/Trip Hazard Along Safe Walkway

Southwest of the Primary Access Facility

09/15/2022

22-07575

North Underground Fire Protection Loop Pipe Rupture

1010/2022

22-07790

Potential Sinkhole Near AC Transformer

10/15/2022

22-07790

Potential Sinkhole Near AC Transformer

10/15/2022

22-09856

Potential Sinkhole Identified in Personnel Walkway Between

PSF and South PAC

2/29/2022

22-09879

Potential Water Leak Near Fire Protection Valve 43

2/31/2022

Corrective Action

Documents

Resulting from

Inspection

22-07735

NRC Questions/Concerns Concerning CR 2022-03195

Investigation

10/13/2022

118817

Seal Leak Meter Assembly

Drawings

1F-8737

Pump Sectional, Reactor Coolant Pump

H

M-530-00452-02

Vendor Manual, RCP Seal Leak Meter

05/03/2005

Miscellaneous

ODMI

2013-14401, Recommendations for Operating with

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Recommendation

Summary Sheet

Degraded RCP 1-1 Third Stage Seal Performance

Procedures

NG-EN-00327

RCS Integrated Leakage Program

2