August 24, 2023

SUBJECT:

UPDATED INSPECTION PLAN FOR DAVIS-BESSE NUCLEAR POWER STATION (REPORT 05000346/2023005)

Dear Terry Brown:

The enclosed inspection plan lists the inspections scheduled through June 30, 2025, for Davis-Besse Nuclear Power Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 630-892-9731 with any questions you have regarding this letter.

Sincerely, Signed by Stoedter, Karla on 08/24/23 Karla K. Stoedter, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000346 License No. NPF-3 Enclosure:

Inspection Plan cc: Distribution via LISTSERV