IR 05000346/2022003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000346/2022003
ML22314A166
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/10/2022
From: Billy Dickson
NRC/RGN-III/DORS/RPB2
To: Tony Brown
Energy Harbor Nuclear Corp
References
IR 2022003
Download: ML22314A166 (21)


Text

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000346/2022003

Dear Terry Brown:

On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Davis-Besse Nuclear Power Station. On October 25, 2022, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Davis-Besse Nuclear Power Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Davis-Besse Nuclear Power Station.

November 10, 2022 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Billy C. Dickson, Jr., Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000346 License No. NPF-3

Enclosure:

As stated

Inspection Report

Docket Number:

05000346

License Number:

NPF-3

Report Number:

05000346/2022003

Enterprise Identifier:

I-2022-003-0043

Licensee:

Energy Harbor Nuclear Corp.

Facility:

Davis-Besse Nuclear Power Station

Location:

Oak Harbor, OH

Inspection Dates:

July 01, 2022 to September 30, 2022

Inspectors:

R. Cassara, Resident Inspector

J. Cassidy, Senior Health Physicist

D. Mills, Senior Resident Inspector

J. Reed, Health Physicist

Approved By:

Billy C. Dickson, Jr., Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Davis-Besse Nuclear Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Develop Appropriate Local Leak Rate Testing for Fuel Transfer Tubes Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000346/2022003-01 Open/Closed

[H.6] - Design Margins 71152S The inspectors identified a Green finding and associated non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XI, Test Control.

Specifically, the licensee did not establish testing requirements and acceptance limits to provide reasonable assurance of containment integrity by detecting fuel transfer tube flange seal degradation as required by 10 CFR Part 50, Appendix B, Criterion XI. Failure to detect degradation of the fuel transfer tube flange seals could result in a loss of containment integrity. The licensee entered this issue into their corrective action program as condition reports 2022-03195.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000346/2021-002-00 LER 2021-002-00 for Davis-Besse Nuclear Power Station, Unit 1, Failure of Auxiliary Feedwater Rooms Interconnecting Door to Latch due to Worn Interlock 71153 Closed LER 05000346/2021-003-00 LER 2021-003-00 for Davis-Besse Nuclear Power Station, Unit 1, Reactor Trip due to Failed Uninterruptible Power Supply and Steam Feedwater Rupture Control System Actuations 71153 Closed

PLANT STATUS

The unit operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending weather of forecasted severe thunderstorms and high winds during the week ending July 23, 2022

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Component cooling water (CCW) train 2 following pump maintenance during the week ending August 13, 2022
(2) Spent fuel pool cooling system during the week ending August 27, 2022
(3) Auxiliary feedwater train 1 while auxiliary feedwater train 2 out of service for scheduled maintenance during the week ending August 27, 2022
(4) Motor driven feed pump while emergency feedwater out of service for scheduled maintenance during the week ending September 24, 2022

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Security data management system locations for the CAS/SAS (Central Alarm Station/Secondary Alarm Station) and security computer rooms during the week ending July 9, 2022
(2) Number 4 mechanical penetration room, rooms 115CC, 314 and 314CC, and fire area A, during water curtain outage the week ending August 13, 2022
(3) Emergency feedwater facility during the week ending September 10, 2022
(4) Auxiliary feed pump 1 and 2 rooms, room 237 and 238, fire area E and F during the week ending August 27, 2022
(5) Cable spreading room, room 422A, fire area DD during the week ending September 3, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) High water in manholes 3009 and 3010, and inspection of manholes 3040, 3045, 3046, and 3005

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated requalification simulator during drill on August 30, 2022

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Control rod drive absolute position indicating power supply replacement after failure
(2) Integrated control system feedwater module replacement and calibration

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Integrated control system feedwater module calibration causing delta cold leg temperature difference during the week ending August 27, 2022
(2) Risk management during scheduled emergency feedwater outage during the week ending September 24, 2022
(3) Containment entry at power to inspect for reactor coolant system leakage during the week ending September 17, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (1 Sample)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Anticipatory reactor trip system channel 4 due to unexpected trip of control rod drive breaker C after opening the cabinet door during the week ending August 6, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) CCW pump 2 rotor and seal package replacement during the week ending August 6, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1) Makeup pump 2 maintenance and PMT during the week ending July 30, 2022
(2) CCW pump 2 after rotor and seal package replacement during the week ending August 6, 2022
(3) Motor driven feed pump after scheduled maintenance during the week ending August 6, 2022
(4) Safety features actuation signal channel integrated testing following scheduled component replacement during the week ending August 20, 2022
(5) Auxiliary feedwater pump 2 quarterly test after scheduled maintenance during the week ending August 27, 2022
(6) High pressure injection pump 1 after flow transmitter calibration during the week ending September 17, 2022
(7) Emergency feedwater pump quarterly after planned maintenance during the week ending September 24, 2022
(8) Near full-power testing of turbine stop and control valves following installation of p-port orifices during the week ending September 24, 2022

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (1 Sample)

(1) Low pressure injection pump 1 quarterly during the week ending July 23, 2022

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Personnel hatch local leak rate testing during the week ending September 17, 2022

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Integrated drill on August 30,

RADIATION SAFETY

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (4 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1) Station vent system
(2) Borated water storage tank
(3) North basin
(4) Training center pond to Toussaint River

Sampling and Analysis (IP Section 03.02) (2 Samples)

Inspectors evaluated the following effluent samples, sampling processes and compensatory samples:

(1) Borated water storage tank - weekly gamma emitter
(2) Training center pond to Toussaint River - compensatory action

Dose Calculations (IP Section 03.03) (2 Samples)

The inspectors evaluated the following dose calculations:

(1) Containment purge pre-release permit - 22-B0003G
(2) Liquid discharge pre-release permit - 21-B0008L

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) January 1, 2021 through June 30, 2022 IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
(1) January 1, 2021 through June 30, 2022

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) January 1, 2021 through June 30, 2022 BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)
(1) July 1, 2021 through June 30, 2022

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) October 1, 2021 through September 30, 2022

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) July 1, 2021 through June 30, 2022 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) July 1, 2021 through June 30, 2022

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Condition report 2022-00382, "Door 300 Damaged During Fuel Delivery." In January 2022, during new fuel delivery, a truck impacted the fuel handling building train bay door (door 300) and damaged the door frame. The inspectors reviewed the circumstances leading to this incident and licensee corrective actions, including repairs. The inspectors also reviewed licensee analyses related to fuel handling building and fuel handling weather enclosure air leakage. No deficiencies were identified.

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

Transfer tube flange leaks following acceptable local leak rate tests

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends related to transfer tube flange leaks that might be indicative of a more significant safety issue. The plant has two fuel transfer tubes connecting the spent fuel pool with the refueling canal in containment. The transfer tubes are isolated from containment using gate valves and bolted blind flanges. The bolted blind flanges are sealed to the pipe flanges using two concentric rubber O-rings. In 2018, the licensee implemented an engineering change that reduced the number of flange bolts from 28 to 14. This reduction of bolts was supported by an engineering evaluation. Since this change, the licensee has experienced multiple issues related to the positive sealing of the east and west transfer tubes.

In 2020, following shutdown for refueling outage, a walkdown of the containment revealed a significant amount of wet and dry boric acid in the refueling canal. This boric acid was traced to a leak of approximately 60 drops per minute from the west transfer tube flange. Condition report 2020-01652

In 2022, during a walkdown of containment prior to startup a leak of more than 1 gallon per minute was found coming from the east transfer tube flange. The flange bolts were found to be only slightly more than hand-tight.

Inspectors identified a Green non-cited violation and a minor violation of NRC regulations related to these issues.

71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated Davis-Besse licensee event reports (LERs) 05000346/202100300, "Reactor Trip due to Failed Uninterruptible Power Supply and Steam Feedwater Rupture Control System Actuations," and 05000346/2021002 "Failure of Auxiliary Feedwater Rooms Interconnecting Door to Latch due to Worn Interlock."

(1) LER 05000346/2021002, "Failure of Auxiliary Feedwater Rooms Interconnecting Door to Latch due to Worn Interlock," (ADAMS Accession No. ML21235A413). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements. This LER is closed.
(2) LER 05000346/2021003, "Reactor Trip due to Failed Uninterruptible Power Supply and Steam Feedwater Rupture Control System Actuations," (ADAMS Accession No. ML21250A131). The inspection conclusions associated with this LER are documented in Inspection Report 05000346/2021050. This LER is closed.

INSPECTION RESULTS

Failure to Develop Appropriate Local Leak Rate Testing for Fuel Transfer Tubes Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000346/2022003-01 Open/Closed

[H.6] - Design Margins 71152S The inspectors identified a Green finding and associated non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XI, Test Control.

Specifically, the licensee did not establish testing requirements and acceptance limits to provide reasonable assurance of containment integrity by detecting fuel transfer tube flange seal degradation as required by 10 CFR Part 50, Appendix B, Criterion XI. Failure to detect degradation of the fuel transfer tube flange seals could result in a loss of containment integrity. The licensee entered this issue into their corrective action program as condition reports 2022-03195.

Description:

In 2018, the licensee performed a local leak rate test on the east and west fuel transfer tube blind flanges. Both fuel transfer tubes satisfactorily passed these local leak rate tests. In 2020, the licensee determined that the west transfer tube flange was leaking and had leaked for a significant amount of time. In 2022, during containment walkdowns before reactor startup, the licensee found the east transfer tube flange leaking at the flange. The east and west flanges had previously passed local leak rate testing (LLRT). The licensee determined the bolts holding the flanges in place to be only hand-tight, and upon disassembly, the licensee found the LLRT test port filled with grease. With grease blocking the test point port, the results of the LLRTs conducted gave invalid results.

Based on a review of licensee procedures for assembling the transfer tube seals and for performing local leak rate testing, the inspectors determined that the LLRT procedure is unsuitable for detecting transfer tube sealing with excess grease on the O-rings as is current licensee practice.

Corrective Actions: The licensee revised the transfer tube flange assembly procedure, reperformed the local leak rate test, and performed an extent of condition considering the west transfer tube.

Corrective Action References: CR 2020-01652, CR 2022-03169, CR 2022-03195, CR 2022-07735

Performance Assessment:

Performance Deficiency: In 2020, at the beginning of a refueling outage, it was discovered that the west transfer tube flange leaked. In 2022, prior to startup, it was discovered that the west transfer tube leaked. In both cases the leaks developed following successful local leak rate tests. The licensee's failure to adequately test the flange seals to provide reasonable assurance that they were reasonably leak tight is a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the structures, systems, and component (SSC) and Barrier Performance attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the failure of the LLRT as currently performed with seals coated in grease may result in a failure to detect an improperly sealed transfer tube flange.

Significance: The inspectors assessed the significance of the finding using Inspection Manual Chapter (IMC) 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Inspectors referenced IMC 0609 Appendix A, Exhibit 3 - "Barrier Integrity Screening" Question C.1 which refers the user to IMC 0609, Appendix H, because the flange leaks represented an actual open pathway in the physical integrity of reactor containment.

Inspectors referenced IMC 0609 Appendix H, Table 7.2 "Phase 2 Risk Significance - Type B Findings at Power" for large dry containments, which resulted in the finding screening to Green because there was no actual leakage from containment to environment and the volume of leakage under postulated accident conditions would have been much less than 100 percent of containment volume per day.

Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment. Specifically, the flange leaks discovered in 2020 and 2022 coupled with the discovery of the local leak rate test port packed with grease should have resulted in a more robust organizational response and recognition of a potentially deficient local leak rate test.

Enforcement:

Violation: 10 CFR 50 Appendix B Criterion XI "Test Control," requires, in part, "A test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents." Contrary to the above, the licensee failed to develop a testing program for the fuel transfer tube flange seals to ensure they remained capable of performing their functions satisfactorily in service.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Minor Violation 71152S Minor Violation: In 2018, the licensee implemented a design change to reduce the number of transfer tube blind flange bolts from 28 to 14 per tube. The licensee performed an engineering analysis but failed to consider all factors. Specifically, the licensee failed to analyze the adequacy of the reduced bolting for the maximum allowed planar warpage/misalignment of the tube flange and blind flange. The design drawing states, "check seal surface of the tube flange for flatness

(a) At 45-degree intervals (8 places);
(b) To be within 0.015" which was specified for the original design using 28 flange bolts. The licensee failed to validate that this specification is adequate to ensure proper sealing with the use of 14 flange bolts. Since the licensee made this change, the licensee has, on multiple occasions, detected fuel transfer tube leakage following reassembly.

Screening: The inspectors determined the performance deficiency was minor. The licensee's failure to perform a thorough engineering review constituted a minor performance deficiency.

Enforcement:

Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that, "measures shall be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures and instructions." Contrary to the above requirement, the licensee failed to evaluate and/or document that the design specification for the seal flange was adequate to ensure proper sealing with reduced bolting.

This failure to comply with 10 CFR 50 Appendix B, Criteria III constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 25, 2022, the inspectors presented the integrated inspection results to Mr. T. Brown, Site Vice President, and other members of the licensee staff.

On August 26, 2022, the inspectors presented the radiation protection inspection results to Mr. T. Brown, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

21-04816

Handwheel Nut and Handwheel Fell Off of Valve FW126

06/21/2021

Corrective Action

Documents

22-06530

BACC on SF16268

08/24/2022

DB-OP-06021

Spent Fuel Pool Operating Procedure

DB-OP-06233

Auxiliary Feedwater System

DB-OP-06262

Component Cooling Water System Procedure

71111.04

Procedures

DB-SS-03090

Motor Driven Feed Pump Monthly Valve Verification

Corrective Action

Documents

22-05878

Fire Piping Flange Leak in Cable Spread Room Near West

Wall

07/29/2022

PFP-AB-237

Auxiliary Feed Pump 1 Room 237

PFP-AB-238

Auxiliary Feed Pump 2 Room 238, Fire Area F

PFP-AB-314

No 4 Mechanical Penetration Rooms 115CC, 314, and

314CC, Fire Area A

PFP-AB-422A

Cable Spreading Room 422A, Fire Area DD

71111.05

Fire Plans

PFP-AB-422A

Cable Spreading Room, Room 422A, Fire Area DD

22-05891

High Water in Manhole MH3009

07/29/2022

22-05892

High Water in Manhole MH3010

07/29/2022

Corrective Action

Documents

22-06114

Paved Area East of the Plant is Underwater

08/09/2022

Emergency Preparedness Integrated Drill

08/30/2022

Miscellaneous

Visual Exam of

Equipment and

Components

(VT-3)

DB-SUB49-01 Emergency Sump, Borated Water Storage

Tank

09/13/2022

71111.06

Work Orders

200832523

Check Manhole Water Levels in MH3040, MH3044,

MH3045, and MH3048

09/28/2020

2019-05879

CCW Heat Exchanger 3 Outage at Risk

07/11/2019

20-03251

E22-2, CCW 2 Heat Exchanger, Endbell Leak

04/15/2020

Corrective Action

Documents

22-04541

CCW HX 3 Eddy Current Test Results

06/01/2022

71111.07A

Corrective Action

Documents

Resulting from

Inspection

20-07564

NRC Identified: Error in EER 600724048, CCW HX Tube

Evaluation

09/29/2020

71111.11Q

Miscellaneous

Emergency Preparedness Integrated Drill

08/30/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2019-10760

Q233, CRD 5 VDC Power Supply 'B' Fault, Indicates NTNM

09/11/2016

20-02452

The CRD API Power Supply 'B' in C4801X Did Not Turn on

When the DCRDCS Was Energized

03/20/2020

22-00893

MFP 1 Did Not Transfer from ICS to MDT-20 Control

2/06/2022

22-01894

System Monitoring Identified Anomalies with Rod 2-1

Absolute Position Indication

03/09/2022

22-02312

Set Screw Missing From HIC-ICS20

03/17/2022

22-03271-1

Maintenance Rule Review ICS/NNI System

04/29/2022

22-03275

Plant Computer Lost OPC Connection to ICS-ULD

04/14/2022

22-03441

Main Feed Pump 1 ICS Controller HICICS36B Will Not

Transfer from Manual to Auto

04/19/2022

22-04263

Received Unexpected Annunciator Alarm 14-2-F ICS ULD

Trouble

05/20/2022

22-05606

CRD Absolute Position Indicator 5-Vold Power Supply 'B'

Failed High

07/18/2022

22-06464

Secondary HBP Unexpectedly Non-Functional During

Testing

08/22/2022

22-06474

T983 Feedwater Temperature Incorrectly Feeding Through

to FDMIS

08/23/2022

22-06499

String Check Found Out of Tolerance

08/23/2022

22-06500

Temperature Sensitivity for FYSP02A1 (X) Calibration

08/23/2022

Corrective Action

Documents

22-06734

Unit Load Demand Transferred to Manual on Feedwater

Flow Deviation

09/01/2022

Miscellaneous

NOBP-LP-2601-

Pre-Job Brief

Procedures

DB-OP-06401

Transferring Rod Control Panel

71111.12

Work Orders

200889122

DB-SUB055-01 SUB055-01 CRD System Power Supply B

Fault

07/18/2022

22-06909

Unexpected Change in Delta T Cold During Adjustments

09/10/2022

22-06935

Boric Acid Identified During Containment Walkdown

09/12/2022

22-07181

Diesel Oil Leak coming from EFW Day Tank

09/22/2022

22-07345

Containment Entry, Higher Dose Rates than Expected in Not

Normally Accessed Area

09/29/2022

71111.13

Corrective Action

Documents

22-07349

Untimely Documentation of a Condition Report

09/29/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DBBP-OPS-0003

On-Line Risk Management Process

DBBP-OPS-0011

Protected Equipment Posting

NG-DB-00001

On-Line Risk Management

Procedures

NOP-OP-1007

Risk Management

200724732

PM 12055 EFW Diesel, Gear and Pump Drain/Fill T-89

09/19/2019

Work Orders

200820648

PM 12055 EFW Diesel, Gear and Pump

09/12/2022

Corrective Action

Documents

22-05932

ARTS Channel 4 Trip During Testing

08/01/2022

200829575

Train 2 Staggered Test, Breaker C

08/02/2022

71111.15

Work Orders

200842248

Channel Functional Test of SFRCS Actuation Channel 2

Logic for Mode 1

08/01/2022

20-01257

CCW Pump 1 Lessons Learned

2/18/2020

22-05826

Potential Leakage Identified from Degraded Hose

07/27/2022

Corrective Action

Documents

22-07345

Containment Entry, Higher Dose Rates Than Expected in

Not Normally Accessed Area

09/29/2022

2-1032-001

Temporary Modification to Replace a Braided Hose with SS

Tubing on RE4598BA

Engineering

Changes

2-1032-002

Temporary Modification to Replace a Braided Hose with SS

Tubing on RE4598BA, Restoration

Procedures

NOP-CC-2003

Engineering Changes 200763445

Add Constant Level Oilers to CCW Pump 2 Inboard and

Outboard Bearing

08/23/2018

200765344

Replace CCW Pump 2 Inboard and Outboard Slinger Rings

with 8.5" ID Slinger Rings

07/26/2022

71111.18

Work Orders

200889938

CCW Pump 2 Baseline Test

08/05/2022

21-01355

Main Turbine Stop Valve 4 Closed While Testing Main

Turbine Stop Valve 2

2/28/2021

21-04152

Turbine Stop Valve 2 Testing Issues

05/22/2021

22-03993

Elevated Vibration Readings on MDFP

05/11/2022

22-06031

Motor Driven Feedwater Pump P241 High Vibration Level

08/05/2022

22-06049

Engineering Review DB-PF-03573 CCW Pump 2 Baseline

Data

08/05/2022

71111.19

Corrective Action

Documents

22-06060

CCW Pump 2 Outboard Oil Discoloration

08/06/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

22-06066

CCW Pump 2 Abnormal Noise

08/06/2022

22-06070

High Pressure Injection Pumps Recirculation Line Drain

Valve HP157A Handwheel is Loose

08/07/2022

22-06950

BACC: Water Drop Formed on Bottom of HPI Pump 1

Casing Flange

09/12/2022

Miscellaneous

SD-038

System Description for High Pressure Injection System for

Energy Harbor Nuclear Davis Besse Nuclear Power Station

Unit 1

Procedures

DB-SS-04201

Emergency Feedwater Pump Quarterly Test

200627177

PM 5190 BF1201 Test MCC Breakers

08/25/2022

200724732

PM 12055 EFW Diesel, Gear and Pump Drain/Fill T-89

09/19/2019

200804014

Makeup Pump 1-2 PM 0171

07/27/2022

200820648

PM 12055 EFW Diesel, Gear and Pump

09/12/2022

200821069

Repair Oil Leak on the Pump Inboard Bearing Cap

07/05/2022

200822815

PM 2522 Lubricate MDFP Motor MP241

08/04/2022

200825460

CRD Exercise Test

09/12/2022

200829614

Motor Driven Feed Pump Quarterly Test

08/03/2022

200831602

PM 1702K3-2 Lube/Check TTV

08/22/2022

200831943

P3218-001 05.001 BW26 Forward Flow BW26 Forward Flow

FA Norm

09/12/2022

200847339

Installation of P-Port Orifices on All Fast-Acting Solenoid

Valves for All Main Stop, Control, Intercept, and Intermediate

Stop Valves

04/20/2021

200859897

Install P-Port Orifice in the FASVs for Turbine Generator

Control Valves and Reheat Stop Valves

08/06/2021

Work Orders

200889938

CCW Pump 2 Baseline Test

08/05/2022

DB-OP-03291

Containment Personnel and Emergency Airlocks Seal

Leakage Test

DB-OP-06012

Decay Heat and Low Pressure Injection System Operation

Procedure

DB-PF-03291

Containment Personnel and Emergency airlocks Seal

Leakage Test

71111.22

Procedures

DB-SP-03446

Decay Heat Train 1 Pump and Valve Test (Mode 1-3)

71114.06

Corrective Action

22-06710

EP Drill: Trend Identified in Lack of Overall Knowledge of

08/31/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Security Events or Threats Procedures

Documents

22-06726

EP Drill: August 30, 2022, Integrated Drill Objectives Not Met

09/01/2022

Corrective Action

Documents

22-06404

Storm Sewer RE 4686 Indication Flashing

08/19/2022

Corrective Action

Documents

Resulting from

Inspection

22-0658

Lack of Clarity in DB-CN-12005 Could Result in Required

Compensatory Sampling Interval Being Exceeded

08/24/2022

Offsite Dose Calculation Manual

Offsite Dose Calculation Manual

21-B0008L

Liquid Batch Release Package

03/08/2021

2-B0003G

Containment Purge Release Package

03/03/2022

L-21-107

Combined Annual Radiological Environmental Operating

Report and Radiological Effluent Release Report for the

Davis-Besse Nuclear Power Station - 2020

05/15/2021

Miscellaneous

L-22-092

Annual Radiological Environmental Operating Report,

including the Radiological Effluent Release Report for the

Davis-Besse Nuclear Power Station - 2021

05/16/2022

DB-CH-04005

Weekly Condenser Air Activity Sampling and Analysis

DB-CN-03008

Station Vent Release, Weekly Radiological Monitoring,

Sampling, and Analysis of RE4598AA

DB-CN-03013

Liquid Releases, Quarterly Monitoring Analysis

DB-CN-04039

North Settling Basin Weekly Sampling and Analysis

DB-CN-04040

North Settling Basin Quarterly Analysis

DB-CN-12005

Storm Sewer Monitor (RE4686) Inoperable / In Alarm

DB-OP-03011

Radioactive Liquid Batch Release

71124.06

Procedures

DB-OP-03012

Radioactive Gaseous Batch Release

21 DOSE_ST.xlsx

Various

22 DOSE_ST.xlsx

Various

Cycle 22 DEI.xlsx

Various

Miscellaneous

Cycle 23 DEI.xlsx

Various

71151

Procedures

NOBP-LP-4012

Industry Reporting and Information System (IRIS)

71152A

Corrective Action

22-00382

Door 300 Damaged During Fuel Delivery

01/18/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Calculations

2-9279098-000

Davis-Besse Fuel Transfer Tube Cover Plate Bolt Reduction

[Proprietary]

01/24/2018

2008-32482

Fuel Transfer Tube Blank Flanges Improperly Sealed

01/02/2008

2008-33846

DB-PA-08-01: DB-MM-09186 Procedural

Quality/Compliance Issues

01/19/2008

2008-34027

DB-PA-08-01: Transfer Tube Blank Flanges Were Installed

with 2 O-Rings

01/02/2008

2008-34209

Rework Fuel Transfer Tube Blank Flanges

01/23/2008

2009-67480

2009 CDBI: Inadequate Equivalency Justification Provided in

ERR 60-0003-070

11/09/2009

20-01652

1R21 BACC: Boric Acid Crystals and Oil Underneath West

Fuel Transfer Tube Flange

03/01/2020

20-01655

ESM: Oil Under Fuel Transfer Tube in Refueling Canal

03/01/2020

20-01664

1R21 BACC: Fuel Transfer Tube 1-2 Flange

03/02/2020

22-03169

1R22 BACC: Active Leak in Refueling Canal/ Deep End

04/11/2022

Corrective Action

Documents

22-03195

As Found Condition of the East Transfer Tube Flange

04/12/2022

Drawings

M-519-00050

Drawing/Diagram

8, 15, 17, 18

Engineering

Changes

ECP 2018-0022

Fuel Transfer Tube Bolting Reduction

Engineering

Evaluations

EER 60-0003-070

Gasket Equivalent Replacement Flexitalic gasket, O-ring,

EPDM gasket

11/05/1999

Miscellaneous

Document

Change Request

M-519-00050

5, 6

DB-MM-09186

Fuel Transfer Tube Removal and Installation

Procedures

DB-PF-03008

Containment Local Leak Rate Tests

21, 22, 23,

24, 25

200686523

Fuel Transfer Tube 1-1 Local Rate Testing

03/19/2018

200686524

Fuel Transfer Tube 1-2 Local Leak Rate Testing

03/19/2018

200688164

Fuel Transfer Tube 1-1

03/20/2018

200755857

200755857 - Fuel Transfer Tube 1-1 Local Leak Rate

Testing

03/18/2020

71152S

Work Orders

200755858

Fuel Transfer Tube 1-2 Local Leak Rate Testing

03/18/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

200768446

Fuel Transfer Tube 1-1

03/19/2020

200822015

Fuel Transfer Tube 1-1

03/29/2022

200822140

Fuel Transfer Tube 1-2 Local Leak Rate Testing

03/29/2022

200822141

Fuel Transfer Tube 1-1 Local Leak Rate Testing

03/29/2022

200880334

Fuel Transfer Tube 1-1

04/20/2022

200880454

Fuel Transfer Tube 1-2 Local Leak Rate Testing

04/12/2022

MWO 1747

Fuel Transfer Tube Blind Flanges

06/22/1977