Forwards LER 97-023-00,which Documents Event That Occurred at Quad Cities Nuclear Power Station,Unit 1.Commitments Made by Ltr,Listed
ML20202E718
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 11/25/1997
From: Cook D
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20202E721 List:
References
SM-97-111, NUDOCS 9712080128
Download: ML20202E718 (2)


LER-2097-023, Forwards LER 97-023-00,which Documents Event That Occurred at Quad Cities Nuclear Power Station,Unit 1.Commitments Made by Ltr,Listed
Event date:
Report date:
2542097023R00 - NRC Website

text

.

$ tilllMbl(l% c.lilU k (31% .111 '111l1,10 %

, Quad titics t.t nt ratur.: Mainen 22 to 2n<,in u enne vnn i . .ra,n a o m 2 u ..)

Irl MrM v2: el SM-97-Ill i l

i Noveniber 25, 1997 United States Nu;.iear Regulatory Commission Washington, DC 20555 Attention: Document Control Desk

Reference:

Quad Cities Nt. clear Power Station Docket Number 50-254, DPR-29, Unit One Enclosed is Licensee Event Report (LER)97-023, Revision 00, for Quad

Cities Nuclear Power Station.

This report is submitted in accordance with the requirements of the Code of Federal Regulations, Title 10. ' art 50.73(a)(2)(i)(B). The licensee shall report any coeration r andition prohibited by the Plant's Technical Specifications.

j The following commitments are being made by this lette.:

1. Revise QCGP l-4 and 1-5 by 121597 to require that QCIS 0700-11 be performed within 7 days prior to start-up.
2. Revise QCIS 0700-09 by 121597 to delete the words indicating that the procedure functionally tests the Average Power Range Monitors downscale control rod block.

Due Date: 121597.

3. Revise QCAP 1100-04, by 123197 to require that each

'rocedure revision be reviewed for possible effect or inclusion as a predefine in Electronic Work Control System.

4. Revise QCAP 1100-04 by 123197 to ensure a detailed cross-discipline review for Technical Specification (TS) compliance is included for all changes to procedures impler.ienting TS 4.0 to 4.12 requirements, f f

y [_ [y ) ,;

9712000128 971125 PDR ADOCK 05000254 i kk, 4

, )

STMGRiLERi97111 T l Hit t >til ( t tHl})Jin

4 USNRC SM'-97-111- 2 November 25, 1997 If there are any questions or comments concerning this letter, please refer them to Charles Peterson,-Regulatory Affairs Manager at 309-654-2241, ext. 3609..

Respectfully, COMMONWEALTH EDISON COMPANY QUAD CITIFS NUCLEAR POWER STATION

a. o . C/e

- D. B. Cook Station Manager DBC/CP/pkm Enclosure cc: A. B. Beach, Regional Administrator, . egion III-R. M. Pulsifer, Project Manager, NRR C. G. Miller, Senior Resident Inspector, Quad Cities W. D. Leach,-MidAmerican Energy Company-D. C. Tubbs,-MidAmerican Energv Company M. E. Wagner, Licensing, Comed F. A. Spangenberg, Regulatory Affairs Manager, Dresden INP0 Records Center i

ed STMGR\LER\97111