Informs NRC of Change of Committed Due Date Contained in LER 97-015,dtd 970812.Station Changing Due Date of Commitment to 990528
ML20247E666
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 05/05/1998
From: Dimmette J
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
SVP-98-168, NUDOCS 9805180413
Download: ML20247E666 (2)


LER-2097-015, Informs NRC of Change of Committed Due Date Contained in LER 97-015,dtd 970812.Station Changing Due Date of Commitment to 990528
Event date:
Report date:
2542097015R00 - NRC Website

text

- - _ - _ _ _ _ _ _ _ _ - _ . _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ - _ _ _ _ - _ _ _ _ _ _ _ _ .

j' Commone.cahh Ednon (.ompan)

S

  • 9"d""'""""""""""

4* 22 to Jo(ah Asenue Nonh

(:ordm a. II. 612 6 2C 40 Tei .wn s.-22 i SVP-98-168 May 5,1998 U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Document Control Desk

Subject:

Quad Cities Station Units 1 and 2; Change of Commitment Date on LER 97-015 NRC Docket Numbers 50-254 and 50-265

Reference:

(a) L W. Pearce (Comed) SM-97-079 to USNRC, dated August 12,1997 The purpose of this letter is to inform you of the change of a committed due date contained in the Licensee Event Report 50-245/50-265/97-015, reference (a).

In this report, the station made the following commitment:

The breakers in EF AS 1 A-1,1 A-2, l AB-1,1 AB-2,1B-1,2B-1,2A-1, and 2AB-2 will be replaced with new 2-pole breakers to resolve the undervoltage release coil problem. (NTS item 245-180-97-01501, due May 1,1998)

The following breakers have been replaced: 2A-1,2B-1,2AB-2, and 1 AB-2. The following breakers will be scheduled in system windows for replacement: l A-1, I A-2, 1B-1, and 1 AB-1. These breakers were not replaced due to inetTective scheduling and tracking of parts issues. Three system windows will be required to complete the breaker and card replacements. The .ition is changing the due date of this commitment to May 28,1999.

\ f>

> 1

-3 9805180413 980505 PDR ADOCK 05000254 [iJ-b d '

S PM J u ,m om tomn.m,

[ .

i  ;..

USNRC SVP-98-168 2 May 5,1998 If there are any questions or comments concerning this letter, please refer them to Mr.

Charles Peterson, Regulatory Affairs Manager, at (309) 654-2241, ext. 3609.

Sinc ely,

, , n oel P.

/LowwM -

immette, Jr.

Site Vice President Quad Cities Station cc: A. B. Beach, Regional Administrator, Region III ,

R. M. Pulsifer, Project Manager, NRR l C. G. Miller, Senior Resident Inspector, Quad Cities

, W. D. Leech, MidAmerican Energy Company D. C. Tubbs, MidAmerican Energy Company .

F. A. Spangenberg, Regulatory Affairs Manager, Dresden INPO Records Center Office of Nuclear Facility Safety, IDNS DCD License (both electronic and hard copies)

M. E. Wagner, Licensing, Comed SVP Letter File i

L