Forwards Insp Rept 50-277/99-07 & 50-278/99-07 on 990920.No Violations Noted
ML20217M663
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 10/19/1999
From: Cowgill C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Rainey G
PECO CONTROLS CORP.
Shared Package
ML20217M668 List:
References
50-277-99-07, 50-278-99-07, NUDOCS 9910280002
Download: ML20217M663 (3)


See also: IR 05000277/1999007

Text

r . _ ..

.

y.

!

October 19,1999

( -.

Mr. G. Rainey, President

PECO Nuclear -

Nuclear Group Headquarters

Correspondence Control Desk

P.O. Box 195

Wayne, Pennsylvania L19087-0195

SUBJECT: NRC INSPECTION REPORT 50-277/99-07, 50-278/99-07

Dear Mr. Rainey:

On September 20,1999, the NRC completed an inspection at the Peach Bottom Atomic Power

Station The enclosed report presents the results of that inspection. We concluded that your

staff continued to operate both units safely. 1

We noted that main control room personnel continued to perform well during plant maneuvers

and transients, including the response to the 3A reactor feedwater pump trip and the challenges

encountered during Tropical Storm Floyd. ,

!

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter and its i

enclosures will be placed in the NRC Public Document Room (PDR).

We appreciate your cooperation. i

Sincerely,,.

Original Signed By:  ;

Curtis J. Cowgill, Chief

Projects Branch 4

Division of Reactor Projects

Docket Nos.: 50 277.50-278,

,

License Nos.: DPR-44, DPR-56

Enclosure: NRC Inspection Report No. Fs-277/99-07,50-278/99-07

s

,

99102800G2 991019

PDR

8 ADOCK 05000277

PDR- ,pl

1 I

I

L 4

,-

. .

.

3..

G.'Rainey 2

c' c w/encls:

J. Hagan, Senior Vice President, Nuclear Operations

'J. Doering, Vice President, Peach Bottom Atomic Power Station

M. Wamer, Plant Manager, Peach Bottom Atomic Power Station

J.A. Hutton, Director, Licensing, PECO Nuclear

. G. D. Edwards, Chairman, Nuclear Review Board

R. Boyce, Director, Nuclear Quality Assurance

A. F. Kirby, Ill, External Operations - Delmarva Power & Light Co.

A. A. Winter, . Manager, Experience Assessment

J. W. Durham, Sr., Senior Vice President and General Counsel

H. C. Kresge, Manager, External Operations, Connectiv

N. J. Sproul, Manager, Financial Control & Co-owner Affairs, Connectiv

R. McLean, Power Plant Siting, Nuclear Evaluations

D. Levin, Acting Gecretary of Harford County Council

R. Ochs, Maryland Safe Energy Coalition - ,

J. H. Walter, Chief Engineer, Public Service Commission of Maryland -

Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance

Mr. & Mrs. Kip Adams

Commonwealth of Pennsylvania

State of Maryland

TMI- Alert (TMIA)

_ _ _ _ _

. ..

. .

G. Rainey 3

' Distribution w/encls:

Region i Docket Room (with concurrences) -

Nuclear Safety Information Center (NSIC)

NRC Resident inspector

PUBLIC

H. Miller, RA/J. Wiggins, DRA (1)

C.' Cowgill, DRP

D. Florek, DRP

D. Cullison, DRP '

C. O'Daniell, DRP

Distribution w/encis: (Via E-Mail)

M. Tschiltz, RI EDO Coordinator

E. Adensam, PDI-2, NRR

J. Clifford, NRR

M. Thadani, NRR

B. Buckley, NRR

R. Correia, NRR

Inspection Program Branch, NRR (IPAS)

DOCDESK

J

, l

DOCUMENT NAME: G:\ BRANCH 4\PB\PB990707.wpd

To receive a copy of this document, Indicate in the box: "C" = Copy without

attachment / enclosure "E" = Copy with attachment / enclosure "N" = No copy

OFFICE Rl/DRP l Rl/DRPfk

i NAME DFlorek CCowgill

DATE 10/19/99 10//i/99

-

l

\