|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000302/19990051999-09-13013 September 1999 Insp Rept 50-302/99-05 on 990704-0814.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000302/19990041999-07-27027 July 1999 Insp Rept 50-302/99-04 on 990523-0703.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19990031999-06-0404 June 1999 Insp Rept 50-302/99-03 on 990411-0522.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Maint, Operations,Engineering & Plant Support IR 05000302/19990021999-05-0606 May 1999 Insp Rept 50-302/99-02 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000302/19990011999-03-29029 March 1999 Insp Rept 50-302/99-01 on 990117-0227.No Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000302/19980101999-01-0404 January 1999 Insp Rept 50-302/98-10 on 981025-1205.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Insp Also Included Results of Physical Security Specialist IR 05000302/19980131998-12-16016 December 1998 Insp Rept 50-302/98-13 on 981116-20.No Violations Noted. Major Areas Inspected:Area of Plant Support by Regional Safeguards Specialist.Physical Security Program Was Evaluated IR 05000302/19980121998-12-0101 December 1998 Insp Rept 50-302/98-12 on 981013-16.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Biennial EP Exercise for Crystal River Unit 3 IR 05000302/19980091998-11-13013 November 1998 Insp Rept 50-302/98-09 on 980913-1024.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980081998-10-0606 October 1998 Insp Rept 50-302/98-08 on 980802-0912.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maint & Plant Support IR 05000302/19980071998-08-31031 August 1998 Insp Rept 50-302/98-07 on 980621-0801.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980061998-07-20020 July 1998 Insp Rept 50-302/98-06 on 980510-0620.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000302/19980041998-06-0808 June 1998 Insp Rept 50-302/98-04 on 980322-0509.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20216H8941998-04-0808 April 1998 Insp Rept 50-302/98-03 on 980208-0321.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980021998-03-13013 March 1998 Insp Rept 50-302/98-02 on 980126-30.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering.Emergency Operating Procedures Were Also Reviewed ML20216E9611998-03-0404 March 1998 Insp Rept 50-302/98-01 on 980104-0207.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20203F5631998-02-23023 February 1998 Insp Repts 50-302/97-12 on 971020-24,1208-12 & 980105-09. Violations Noted.Major Areas Inspected:Adequacy of EOPs Development Process IR 05000302/19970191998-01-29029 January 1998 Insp Rept 50-302/97-19 on 971130-980103.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20199G6861998-01-16016 January 1998 Insp Rept 50-302/97-20 on 971201-16.Violations Noted.Major Areas Inspected:Operations,Radiological Protection,Maint & Surveillance Programs IR 05000302/19972011998-01-0909 January 1998 Insp Rept 50-302/97-201 on 970929-1003.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of CAs Previously Committed by Licensee & Related Discussion W/Personnel IR 05000302/19970181998-01-0606 January 1998 Insp Rept 50-302/97-18 on 971117-21 & 1201-12.No Violations Noted.Major Areas Inspected:Plant Support ML20198P2251997-12-29029 December 1997 Insp Rept 50-302/97-21 on 971203.Violations Noted.Major Areas Inspected:Noncompliances in Design control,10CFR50.59, Procedural Adequacy,Reportability & Corrective Actions.No Notice of Violation Being Issued in This Case ML20198N6271997-12-29029 December 1997 Insp Rept 50-302/97-19 on 971026-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20203A2061997-12-0404 December 1997 Insp Rept 50-302/97-14 on 971006-24.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000302/19970161997-11-24024 November 1997 Insp Rept 50-302/97-16 on 970921-1025.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000302/19970131997-10-16016 October 1997 Insp Rept 50-302/97-13 on 970817-0920.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19970151997-10-14014 October 1997 Partially Withheld Insp Rept 50-302/97-15 on 970922-26 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Plant Support by Regional Safeguards Inspector ML20211E5791997-09-12012 September 1997 Insp Rept 50-302/97-11 on 970713-0816.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20210R9361997-08-27027 August 1997 Partially Withheld Insp Rept 50-302/97-10 on 970804-06. Violations Noted.Major Areas Inspected:Physical Security ML20210M5731997-08-11011 August 1997 Insp Rept 50-302/97-08 on 970608-0712.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20149H0981997-07-14014 July 1997 Insp Rept 50-302/97-09 on 970602-20.Apparent Violations Being Considered for Escalated Ea.Major Areas Inspected: Engineering of Functional Areas IR 05000302/19970071997-07-0707 July 1997 Insp Rept 50-302/97-07 on 970504-0607.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re self-assessment Rept on Health Physics & Radiation Control Areas Access Control Program ML20140D2721997-06-0202 June 1997 Integrated Insp Rept 50-302/97-05 on 970330-0503.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint, Plant Support & Review of restart-related Open Items ML20138J4091997-04-21021 April 1997 Insp Rept 50-302/97-02 on 970223-0329.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20140E7481997-04-18018 April 1997 Partially Withheld Insp Rept 50-302/97-03 on 970317-21 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Physical Security Program for Power Reactors & Control of Safeguards Info ML20138J8191997-04-17017 April 1997 Special Insp Rept 50-302/97-06 on 970127-0321.Apparent Violation Being Considered for Escalated Ea.Major Areas Inspected:Engineering Functional Area to Followup on URI 97-01-06;HPI Sys Design,Licensing Basis & TS Concerns ML20137V7271997-04-11011 April 1997 Insp Rept 50-302/97-04 on 970127-0321.No Violations Noted. Major Areas Inspected:Operations & Engineering ML20137T0461997-03-24024 March 1997 Insp Rept 50-302/97-01 on 970112-0222.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20134P4001997-02-0505 February 1997 Insp Rept 50-302/96-20 on 961201-970111.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20138J5691997-01-31031 January 1997 Insp Rept 50-302/96-18 on 961202-06 & 16-19.Violations Noted.Major Areas Inspected:Area of Plant Support by Three Regional Safeguards Specialists IR 05000302/19960171996-12-23023 December 1996 Insp Rept 50-302/96-17 on 961103-30.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maintenance,& Plant Support IR 05000302/19960141996-12-0202 December 1996 Insp Rept 50-302/96-14 on 961015-18.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Biennial Emergency Preparedness Exercise IR 05000302/19960151996-11-27027 November 1996 Insp Rept 50-302/96-15 on 961006-1102.Violations Noted.Major Areas Inspected:Operations Re Emergency Feedwater Sys,Maint, Engineering & Plant Support ML20134J7111996-11-0404 November 1996 Insp Rept 50-302/96-12 on 960826-1011.Violations Noted.Major Areas Inspected:Licensee Operations & Engineering & follow- Up on URI 50-302/96-201-08,acceptability of EDG Surveillance Test Values ML20129H7311996-10-30030 October 1996 Insp Rept 50-302/96-11 on 960908-1005.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maintenance, & Plant Support IR 05000302/19960161996-10-30030 October 1996 Insp Rept 50-302/96-16 on 961029-31.No Violations Noted. Major Area Inspected:Malevolent Use of Vehicles at Nuclear Power Plants.Details Withheld ML20134F0381996-10-28028 October 1996 Insp Rept 50-302/96-13 on 960919-1009.No Violations Noted. Major Areas Inspected:Licensees Response to Potential Tampering Event ML20129A2861996-10-0404 October 1996 Insp Rept 50-302/96-09 on 960811-0907.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maintenance & Plant Support ML20134C3131996-09-12012 September 1996 Insp Rept 50-302/96-08 on 960714-0810.Violations Noted.Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000302/19930161993-12-23023 December 1993 Insp Rept 50-302/93-16 on 931115-19 & 1206-1210.Violations Noted.Major Areas Inspected:Emergency Operating Procedure Team,Representative Records,Interviews W/Personnel & Observation of Activities in Progress 1999-09-13
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000302/19990051999-09-13013 September 1999 Insp Rept 50-302/99-05 on 990704-0814.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000302/19990041999-07-27027 July 1999 Insp Rept 50-302/99-04 on 990523-0703.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19990031999-06-0404 June 1999 Insp Rept 50-302/99-03 on 990411-0522.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Maint, Operations,Engineering & Plant Support IR 05000302/19990021999-05-0606 May 1999 Insp Rept 50-302/99-02 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000302/19990011999-03-29029 March 1999 Insp Rept 50-302/99-01 on 990117-0227.No Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000302/19980101999-01-0404 January 1999 Insp Rept 50-302/98-10 on 981025-1205.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Insp Also Included Results of Physical Security Specialist IR 05000302/19980131998-12-16016 December 1998 Insp Rept 50-302/98-13 on 981116-20.No Violations Noted. Major Areas Inspected:Area of Plant Support by Regional Safeguards Specialist.Physical Security Program Was Evaluated IR 05000302/19980121998-12-0101 December 1998 Insp Rept 50-302/98-12 on 981013-16.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Biennial EP Exercise for Crystal River Unit 3 IR 05000302/19980091998-11-13013 November 1998 Insp Rept 50-302/98-09 on 980913-1024.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980081998-10-0606 October 1998 Insp Rept 50-302/98-08 on 980802-0912.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maint & Plant Support IR 05000302/19980071998-08-31031 August 1998 Insp Rept 50-302/98-07 on 980621-0801.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980061998-07-20020 July 1998 Insp Rept 50-302/98-06 on 980510-0620.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000302/19980041998-06-0808 June 1998 Insp Rept 50-302/98-04 on 980322-0509.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20216H8941998-04-0808 April 1998 Insp Rept 50-302/98-03 on 980208-0321.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980021998-03-13013 March 1998 Insp Rept 50-302/98-02 on 980126-30.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering.Emergency Operating Procedures Were Also Reviewed ML20216E9611998-03-0404 March 1998 Insp Rept 50-302/98-01 on 980104-0207.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20203F5631998-02-23023 February 1998 Insp Repts 50-302/97-12 on 971020-24,1208-12 & 980105-09. Violations Noted.Major Areas Inspected:Adequacy of EOPs Development Process IR 05000302/19970191998-01-29029 January 1998 Insp Rept 50-302/97-19 on 971130-980103.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20199G6861998-01-16016 January 1998 Insp Rept 50-302/97-20 on 971201-16.Violations Noted.Major Areas Inspected:Operations,Radiological Protection,Maint & Surveillance Programs IR 05000302/19972011998-01-0909 January 1998 Insp Rept 50-302/97-201 on 970929-1003.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of CAs Previously Committed by Licensee & Related Discussion W/Personnel IR 05000302/19970181998-01-0606 January 1998 Insp Rept 50-302/97-18 on 971117-21 & 1201-12.No Violations Noted.Major Areas Inspected:Plant Support ML20198P2251997-12-29029 December 1997 Insp Rept 50-302/97-21 on 971203.Violations Noted.Major Areas Inspected:Noncompliances in Design control,10CFR50.59, Procedural Adequacy,Reportability & Corrective Actions.No Notice of Violation Being Issued in This Case ML20198N6271997-12-29029 December 1997 Insp Rept 50-302/97-19 on 971026-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20203A2061997-12-0404 December 1997 Insp Rept 50-302/97-14 on 971006-24.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000302/19970161997-11-24024 November 1997 Insp Rept 50-302/97-16 on 970921-1025.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000302/19970131997-10-16016 October 1997 Insp Rept 50-302/97-13 on 970817-0920.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19970151997-10-14014 October 1997 Partially Withheld Insp Rept 50-302/97-15 on 970922-26 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Plant Support by Regional Safeguards Inspector ML20211E5791997-09-12012 September 1997 Insp Rept 50-302/97-11 on 970713-0816.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20210R9361997-08-27027 August 1997 Partially Withheld Insp Rept 50-302/97-10 on 970804-06. Violations Noted.Major Areas Inspected:Physical Security ML20210M5731997-08-11011 August 1997 Insp Rept 50-302/97-08 on 970608-0712.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20149H0981997-07-14014 July 1997 Insp Rept 50-302/97-09 on 970602-20.Apparent Violations Being Considered for Escalated Ea.Major Areas Inspected: Engineering of Functional Areas IR 05000302/19970071997-07-0707 July 1997 Insp Rept 50-302/97-07 on 970504-0607.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re self-assessment Rept on Health Physics & Radiation Control Areas Access Control Program ML20140D2721997-06-0202 June 1997 Integrated Insp Rept 50-302/97-05 on 970330-0503.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint, Plant Support & Review of restart-related Open Items ML20138J4091997-04-21021 April 1997 Insp Rept 50-302/97-02 on 970223-0329.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20140E7481997-04-18018 April 1997 Partially Withheld Insp Rept 50-302/97-03 on 970317-21 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Physical Security Program for Power Reactors & Control of Safeguards Info ML20138J8191997-04-17017 April 1997 Special Insp Rept 50-302/97-06 on 970127-0321.Apparent Violation Being Considered for Escalated Ea.Major Areas Inspected:Engineering Functional Area to Followup on URI 97-01-06;HPI Sys Design,Licensing Basis & TS Concerns ML20137V7271997-04-11011 April 1997 Insp Rept 50-302/97-04 on 970127-0321.No Violations Noted. Major Areas Inspected:Operations & Engineering ML20137T0461997-03-24024 March 1997 Insp Rept 50-302/97-01 on 970112-0222.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20134P4001997-02-0505 February 1997 Insp Rept 50-302/96-20 on 961201-970111.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20138J5691997-01-31031 January 1997 Insp Rept 50-302/96-18 on 961202-06 & 16-19.Violations Noted.Major Areas Inspected:Area of Plant Support by Three Regional Safeguards Specialists IR 05000302/19960171996-12-23023 December 1996 Insp Rept 50-302/96-17 on 961103-30.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maintenance,& Plant Support IR 05000302/19960141996-12-0202 December 1996 Insp Rept 50-302/96-14 on 961015-18.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Biennial Emergency Preparedness Exercise IR 05000302/19960151996-11-27027 November 1996 Insp Rept 50-302/96-15 on 961006-1102.Violations Noted.Major Areas Inspected:Operations Re Emergency Feedwater Sys,Maint, Engineering & Plant Support ML20134J7111996-11-0404 November 1996 Insp Rept 50-302/96-12 on 960826-1011.Violations Noted.Major Areas Inspected:Licensee Operations & Engineering & follow- Up on URI 50-302/96-201-08,acceptability of EDG Surveillance Test Values ML20129H7311996-10-30030 October 1996 Insp Rept 50-302/96-11 on 960908-1005.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maintenance, & Plant Support IR 05000302/19960161996-10-30030 October 1996 Insp Rept 50-302/96-16 on 961029-31.No Violations Noted. Major Area Inspected:Malevolent Use of Vehicles at Nuclear Power Plants.Details Withheld ML20134F0381996-10-28028 October 1996 Insp Rept 50-302/96-13 on 960919-1009.No Violations Noted. Major Areas Inspected:Licensees Response to Potential Tampering Event ML20129A2861996-10-0404 October 1996 Insp Rept 50-302/96-09 on 960811-0907.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maintenance & Plant Support ML20134C3131996-09-12012 September 1996 Insp Rept 50-302/96-08 on 960714-0810.Violations Noted.Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000302/19930161993-12-23023 December 1993 Insp Rept 50-302/93-16 on 931115-19 & 1206-1210.Violations Noted.Major Areas Inspected:Emergency Operating Procedure Team,Representative Records,Interviews W/Personnel & Observation of Activities in Progress 1999-09-13
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000302/19990051999-09-13013 September 1999 Insp Rept 50-302/99-05 on 990704-0814.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000302/19990041999-07-27027 July 1999 Insp Rept 50-302/99-04 on 990523-0703.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19990031999-06-0404 June 1999 Insp Rept 50-302/99-03 on 990411-0522.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Maint, Operations,Engineering & Plant Support IR 05000302/19990021999-05-0606 May 1999 Insp Rept 50-302/99-02 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000302/19990011999-03-29029 March 1999 Insp Rept 50-302/99-01 on 990117-0227.No Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000302/19980101999-01-0404 January 1999 Insp Rept 50-302/98-10 on 981025-1205.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Insp Also Included Results of Physical Security Specialist IR 05000302/19980131998-12-16016 December 1998 Insp Rept 50-302/98-13 on 981116-20.No Violations Noted. Major Areas Inspected:Area of Plant Support by Regional Safeguards Specialist.Physical Security Program Was Evaluated IR 05000302/19980121998-12-0101 December 1998 Insp Rept 50-302/98-12 on 981013-16.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Biennial EP Exercise for Crystal River Unit 3 IR 05000302/19980091998-11-13013 November 1998 Insp Rept 50-302/98-09 on 980913-1024.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980081998-10-0606 October 1998 Insp Rept 50-302/98-08 on 980802-0912.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maint & Plant Support IR 05000302/19980071998-08-31031 August 1998 Insp Rept 50-302/98-07 on 980621-0801.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980061998-07-20020 July 1998 Insp Rept 50-302/98-06 on 980510-0620.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000302/19980041998-06-0808 June 1998 Insp Rept 50-302/98-04 on 980322-0509.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20216H8941998-04-0808 April 1998 Insp Rept 50-302/98-03 on 980208-0321.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980021998-03-13013 March 1998 Insp Rept 50-302/98-02 on 980126-30.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering.Emergency Operating Procedures Were Also Reviewed ML20216E9611998-03-0404 March 1998 Insp Rept 50-302/98-01 on 980104-0207.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20203F5631998-02-23023 February 1998 Insp Repts 50-302/97-12 on 971020-24,1208-12 & 980105-09. Violations Noted.Major Areas Inspected:Adequacy of EOPs Development Process IR 05000302/19970191998-01-29029 January 1998 Insp Rept 50-302/97-19 on 971130-980103.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20199G6861998-01-16016 January 1998 Insp Rept 50-302/97-20 on 971201-16.Violations Noted.Major Areas Inspected:Operations,Radiological Protection,Maint & Surveillance Programs IR 05000302/19972011998-01-0909 January 1998 Insp Rept 50-302/97-201 on 970929-1003.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of CAs Previously Committed by Licensee & Related Discussion W/Personnel IR 05000302/19970181998-01-0606 January 1998 Insp Rept 50-302/97-18 on 971117-21 & 1201-12.No Violations Noted.Major Areas Inspected:Plant Support ML20198P2251997-12-29029 December 1997 Insp Rept 50-302/97-21 on 971203.Violations Noted.Major Areas Inspected:Noncompliances in Design control,10CFR50.59, Procedural Adequacy,Reportability & Corrective Actions.No Notice of Violation Being Issued in This Case ML20198N6271997-12-29029 December 1997 Insp Rept 50-302/97-19 on 971026-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20203A2061997-12-0404 December 1997 Insp Rept 50-302/97-14 on 971006-24.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000302/19970161997-11-24024 November 1997 Insp Rept 50-302/97-16 on 970921-1025.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000302/19970131997-10-16016 October 1997 Insp Rept 50-302/97-13 on 970817-0920.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19970151997-10-14014 October 1997 Partially Withheld Insp Rept 50-302/97-15 on 970922-26 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Plant Support by Regional Safeguards Inspector ML20211E5791997-09-12012 September 1997 Insp Rept 50-302/97-11 on 970713-0816.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20210R9361997-08-27027 August 1997 Partially Withheld Insp Rept 50-302/97-10 on 970804-06. Violations Noted.Major Areas Inspected:Physical Security ML20210M5731997-08-11011 August 1997 Insp Rept 50-302/97-08 on 970608-0712.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20149H0981997-07-14014 July 1997 Insp Rept 50-302/97-09 on 970602-20.Apparent Violations Being Considered for Escalated Ea.Major Areas Inspected: Engineering of Functional Areas IR 05000302/19970071997-07-0707 July 1997 Insp Rept 50-302/97-07 on 970504-0607.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re self-assessment Rept on Health Physics & Radiation Control Areas Access Control Program ML20140D2721997-06-0202 June 1997 Integrated Insp Rept 50-302/97-05 on 970330-0503.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint, Plant Support & Review of restart-related Open Items ML20138J4091997-04-21021 April 1997 Insp Rept 50-302/97-02 on 970223-0329.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20140E7481997-04-18018 April 1997 Partially Withheld Insp Rept 50-302/97-03 on 970317-21 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Physical Security Program for Power Reactors & Control of Safeguards Info ML20138J8191997-04-17017 April 1997 Special Insp Rept 50-302/97-06 on 970127-0321.Apparent Violation Being Considered for Escalated Ea.Major Areas Inspected:Engineering Functional Area to Followup on URI 97-01-06;HPI Sys Design,Licensing Basis & TS Concerns ML20137V7271997-04-11011 April 1997 Insp Rept 50-302/97-04 on 970127-0321.No Violations Noted. Major Areas Inspected:Operations & Engineering ML20137T0461997-03-24024 March 1997 Insp Rept 50-302/97-01 on 970112-0222.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20134P4001997-02-0505 February 1997 Insp Rept 50-302/96-20 on 961201-970111.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20138J5691997-01-31031 January 1997 Insp Rept 50-302/96-18 on 961202-06 & 16-19.Violations Noted.Major Areas Inspected:Area of Plant Support by Three Regional Safeguards Specialists IR 05000302/19960171996-12-23023 December 1996 Insp Rept 50-302/96-17 on 961103-30.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maintenance,& Plant Support IR 05000302/19960141996-12-0202 December 1996 Insp Rept 50-302/96-14 on 961015-18.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Biennial Emergency Preparedness Exercise IR 05000302/19960151996-11-27027 November 1996 Insp Rept 50-302/96-15 on 961006-1102.Violations Noted.Major Areas Inspected:Operations Re Emergency Feedwater Sys,Maint, Engineering & Plant Support ML20134J7111996-11-0404 November 1996 Insp Rept 50-302/96-12 on 960826-1011.Violations Noted.Major Areas Inspected:Licensee Operations & Engineering & follow- Up on URI 50-302/96-201-08,acceptability of EDG Surveillance Test Values ML20129H7311996-10-30030 October 1996 Insp Rept 50-302/96-11 on 960908-1005.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maintenance, & Plant Support IR 05000302/19960161996-10-30030 October 1996 Insp Rept 50-302/96-16 on 961029-31.No Violations Noted. Major Area Inspected:Malevolent Use of Vehicles at Nuclear Power Plants.Details Withheld ML20134F0381996-10-28028 October 1996 Insp Rept 50-302/96-13 on 960919-1009.No Violations Noted. Major Areas Inspected:Licensees Response to Potential Tampering Event ML20129A2861996-10-0404 October 1996 Insp Rept 50-302/96-09 on 960811-0907.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maintenance & Plant Support ML20134C3131996-09-12012 September 1996 Insp Rept 50-302/96-08 on 960714-0810.Violations Noted.Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000302/19930161993-12-23023 December 1993 Insp Rept 50-302/93-16 on 931115-19 & 1206-1210.Violations Noted.Major Areas Inspected:Emergency Operating Procedure Team,Representative Records,Interviews W/Personnel & Observation of Activities in Progress 1999-09-13
[Table view] Category:UTILITY
MONTHYEARIR 05000302/19900301990-11-17017 November 1990 Insp Rept 50-302/90-30 on 900924-28.No Violations or Deviations Noted.Major Areas Inspected:Licensee Annual Emergency Exercise IR 05000302/19900291990-10-31031 October 1990 Insp Rept 50-302/90-29 on 900908-1005.No Violations or Deviations Noted.Major Areas Inspected:Plant Operations, Security,Radiological Controls,Facility Mods & Licensee Action on Previous Insp Items ML20058B0891990-10-17017 October 1990 Insp Rept 50-302/90-32 on 900918-1005.Violations Noted. Major Areas Inspected:Events Resulting in Breach of Reactor Bldg Containment & Lack of Leak Integrity of Encapsulation Assembly Providing Secondary Boundary to Decay Heat Sys IR 05000302/19900311990-10-10010 October 1990 Insp Rept 50-302/90-31 on 900917-20.No Violation Noted.Major Areas Inspected:Verification That Corrective Actions for Previous Findings Adequate IR 05000302/19900251990-09-24024 September 1990 Partially Withheld Insp Rept 50-302/90-25 on 900812-17 (Ref 10CFR2.790(d) & 73.21).One Unresolved Item Identified.Major Areas Inspected:Security Plan & Implementing Procedures,Mgt Effectiveness,Security Programs,Organization & Audits IR 05000302/19900241990-08-31031 August 1990 Insp Rept 50-302/90-24 on 900707-0810.Violation Noted.Major Areas Inspected:Plant Operations,Security,Radioligical Controls,Lers & Nonconforming Operations Repts,Facility Mods & Licensee Action on Previous Insp Items IR 05000302/19900211990-07-27027 July 1990 Insp Rept 50-302/90-21 on 900602-0706.No Violations Noted. Major Areas Inspected:Plant Operations,Security,Radiological Controls,Ler,Facility Mods & Licensee Action on Previous Insp Items IR 05000302/19900171990-07-10010 July 1990 Insp Rept 50-302/90-17 on 900501-03.Noncited Violations Noted.Major Areas Inspected:Fitness for Duty Program as Required by 10CFR26,including Licensee Drug & Alcohol Abuse Policies,Training,Chemical Testing,Appeals & Repts & Audits IR 05000302/19900221990-07-0606 July 1990 Insp Repts 50-302/90-22 on 900612-16.Violations Noted But Not Cited.Major Areas Inspected:Review & Witnessing of Integrated Engineered Safeguards & Loss of Offsite Power Tests IR 05000302/19890241989-09-15015 September 1989 Insp Rept 50-302/89-24 on 890907-08.Violations Noted.Major Areas Inspected:Review of Events Resulting in Unplanned Shutdown of Facility IR 05000302/19890191989-08-31031 August 1989 Insp Rept 50-302/89-19 on 890708-0804.Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls, Security,Fire Protection,Surveillance Observation,Maint Observation,Safety Sys Walkdown & LERs IR 05000302/19890211989-08-25025 August 1989 Insp Rept 50-302/89-21 on 890808.No Violations or Deviations Noted.Major Areas Inspected:Observation & Analysis of Ultrasonic Exam Capabilities for Opposite Surface Initiating Flaws in Various Matls Involved Re Stated Welds IR 05000302/19890181989-08-16016 August 1989 Insp Rept 50-302/89-18 on 890710-14.Violations Noted.Major Areas Inspected:Inservice Testing & Followup on Previous Insp Findings ML20245K2961989-08-10010 August 1989 Insp Rept 50-302/89-17 on 890619-20.Violations Noted.Major Areas Inspected:Followup to Events Surrounding 890616 Loss of off-site Power transient-review of Plant & Operator Response to Transient,Root Cause & Corrective Actions ML20245J0581989-08-0404 August 1989 Insp Rept 50-302/89-200 on 890424-0505.Weaknesses Noted. Major Areas Inspected:Implementation of Licensee Vendor Interface Program & Program for Procurement of Items for Use in safety-related Applications IR 05000302/19890121989-08-0101 August 1989 Insp Rept 50-302/89-12 on 890620-23.No Violations or Deviations Noted.Major Areas Inspected:Observation & Evaluation of Annual Emergency Exercise,Emergency Operations Facility & Emergency News Ctr.One Weakness Noted IR 05000302/19890161989-08-0101 August 1989 Partially Withheld Insp Rept 50-302/89-16 on 890625-30 (Ref 10CFR2.790 & 73.21).Violations Noted.Major Areas Inspected: Mgt Support,Security Program Plans & Audits,Detection & Assessment Aids & Packages & Vehicles ML20245K0421989-08-0101 August 1989 Insp Rept 50-302/89-15 on 890603-0707.Violations Noted.Major Areas Inspected:Plant Operations,Security,Radiological Controls,Lers & Nonconforming Operations Repts,Facility Mods,Onsite Events & Annual Emergency Drill ML20246E4491989-06-28028 June 1989 Insp Rept 50-302/89-11 on 890429-0602.Violations Noted.Major Areas Inspected:Plant Operations,Security,Radiological Controls,Lers & Nonconforming Operations Repts,Facility Mods,Review of IE Info Notices & Followup of Onsite Events ML20246K7561989-06-27027 June 1989 Insp Rept 50-302/89-14 on 890531-0602.Violations Noted.Major Areas inspected:890529 Event Involving Emergency Feedwater Piping & Containment Penetration Heated Above Design Limits & Unanalyzed Thermal Stresses Imposed on Steam Generator IR 05000302/19890131989-06-23023 June 1989 Insp Rept 50-302/89-13 on 890529-0602.No Violations or Deviations Noted.Major Areas Inspected:Radiation Protection Program,Radwaste Mgt,Transportation of Radioactive Matls & Followup on Previous Inspector Identified Items ML20244D2831989-06-0707 June 1989 Insp Rept 50-302/89-09 on 890424-28.Violations Noted.Major Areas Inspected:Environ Qualification of Electrical Equipment & Followup on Previous Insp Findings,Including Review of Util Implementation of 10CFR50.49 Program IR 05000302/19890101989-06-0707 June 1989 Insp Rept 50-302/89-10 on 890515-19.No Violations or Deviations Noted.Major Areas Inspected:Review of Corrective Actions from Previous Findings Re Training & Emergency Operating Procedures IR 05000302/19890081989-05-10010 May 1989 Insp Rept 50-302/89-08 on 890401-28.Violations Noted.Major Areas Inspected:Plant Operations,Security,Radiological Controls,Nonconforming Operations Repts,Facility Mods & Followup of Onsite Events IR 05000302/19890061989-04-25025 April 1989 Insp Rept 50-302/89-06 on 890225-0331.Violations Noted. Major Areas Inspected:Plant Operations,Security,Radiological Controls,Lers & Nonconforming Operations Repts,Facility Mod, Review of 10CFR21 Repts & Followup of Onsite Events IR 05000302/19890041989-04-0505 April 1989 Insp Rept 50-302/89-04 on 890227-0303.No Violations or Deviations Noted.Major Areas inspected:post-accident Sampling Sys,Confirmatory Measurements,Radiological Effluents & Reactor Coolant Chemistry IR 05000302/19890051989-03-24024 March 1989 Insp Rept 50-302/89-05 on 890306-10.No Violations or Deviations Noted.Major Areas Inspected:Emergency Preparedness,Radiological Emergency Response Plan & Implementing Procedures & Emergency Facilities IR 05000302/19890031989-03-24024 March 1989 Insp Rept 50-302/89-03 on 890128-0224.No Violations or Deviations Noted.Major Areas Inspected:Plant Operations, Security,Radiological Controls,Lers & Nonconforming Operations Rept,Facility Mods & Licensee Actions on Insp IR 05000302/19890021989-02-27027 February 1989 Insp Rept 50-302/89-02 on 890130-31.No Violations Noted. Major Areas Inspected:Reactor Coolant Pump Vibration Monitoring Sys Data Acquisition,Interpretation & Written Instructions for Protective Measures in Event of Failure ML20235P0571989-02-16016 February 1989 Insp Rept 50-302/89-01 on 890101-27.Three Violations Noted. Major Areas Inspected:Plant Operations,Security,Radiological Controls,Ler & Nonconforming Operations Repts,Followup on Onsite Events & Licensee Action on Previous Insp Items IR 05000302/19880321988-11-30030 November 1988 Insp Rept 50-302/88-32 on 881031-1102.No Violations or Deviations Identified.Major Areas Inspected:Followup on Allegations IR 05000302/19880291988-11-21021 November 1988 Insp Rept 50-302/88-29 on 880916-1021.Violations Noted.Major Areas Inspected:Plant Operations,Security Radiological Controls,Lers & Nonconforming Operations Repts,Facility Mods & Review of Plant Review Committee IR 05000302/19880281988-11-0202 November 1988 Partially Withheld Insp Rept 50-302/88-28 (Ref 10CFR2.790 & 73.21).No Violations Noted.Major Areas Inspected:Security Plan & Implementing Procedures,Mgt Effectiveness,Security Program,Security Program Audit & Testing & Maint IR 05000302/19880271988-10-0707 October 1988 Insp Rept 50-302/88-27 on 880829-0902.Violations Noted. Major Areas Inspected:Previously Identified Environ Qualification Deficiencies Documented on Justification for Continue Operation.Licensee Commitment Identified ML20204J8041988-10-0404 October 1988 Insp Rept 50-302/88-26 on 880813-0916.Violations Noted. Major Areas Inspected:Plant Operations,Security,Radiological Controls,Lers & Nonconforming Operations Repts,Facility Mods & Licensee Action on Previous Insp Items IR 05000302/19880251988-09-20020 September 1988 Insp Rept 50-302/88-25 on 880822-26.No Violations or Deviations Noted.Major Areas Inspected:Mods & Design Control ML20155A9181988-09-13013 September 1988 Insp Rept 50-302/88-24 on 880716-0812.Violations Noted.Major Areas Inspected:Plant Operation,Security,Radiological Controls,Lers & Nonconforming Operation Repts IR 05000302/19880201988-09-0707 September 1988 Insp Rept 50-302/88-20 on 880620-24.No Violations or Deviations Noted.Major Areas Inspected:Complex Surveillance Testing & IE Bulletin Followup IR 05000302/19880221988-08-12012 August 1988 Insp Rept 50-302/88-22 on 880725-29.No Violations or Deviations Noted.Major Areas Inspected:Emergency Preparedness,Including Emergency Plan & Implementing Procedures & Organization & Mgt Control ML20151X0061988-08-0505 August 1988 Insp Rept 50-302/88-18 on 880609-0715.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Security,Lers,Nonconforming Operations Repts, Review of Bulletins & Actions on Insp Items IR 05000302/19880211988-08-0505 August 1988 Insp Rept 50-302/88-21 on 880711-15.No Violations or Deviations Noted.Major Areas Inspected:Plant Chemistry, Corrosion Control & Pipe Thinning IR 05000302/19880191988-07-28028 July 1988 Insp Rept 50-302/88-19 on 880627-0701.No Violations or Deviations Noted.Major Areas Inspected:Licensee Conformance to Reg Guide 1.97 ML20151K2941988-07-20020 July 1988 Insp Rept 50-302/88-15 on 880607-09.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Key Emergency & Organizational Functions & Locations During Partial Participation Exercise ML20151D9521988-07-0707 July 1988 Insp Rept 50-302/88-16 on 880512-0608.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Lers,Security & Nonconforming Operations Repts IR 05000302/19880171988-06-10010 June 1988 Insp Rept 50-302/88-17 on 880523-27.No Violations Noted. Major Areas Inspected:Security Plan & Implementing Procedures,Security Organization,Records & Repts,Security Sys Power Supply,Lighting,Assessment Aids & Alarm Stations ML20196B1251988-06-0606 June 1988 Insp Rept 50-302/88-14 on 880416-0611.Violation & Deviation Noted.Major Areas Inspected:Plant Operations,Security, Radiological Controls,Lers & Nonconforming Operations Repts & Review of NRC Bulletins & Circulars IR 05000302/19880091988-06-0606 June 1988 Insp Rept 50-302/88-09 on 880328-0408.Numerous Deficiencies Noted.Major Areas Inspected:Review of Adequacy of Emergency Operating Procedures IR 05000302/19880121988-05-19019 May 1988 Insp Rept 50-302/88-12 on 880411-15.No Violations or Deviations Noted.Major Areas Inspected:Review of Previously Identified Inspector Followup Items & Enforcement Matters, External Exposure Control & Control of Radioactive Matl IR 05000302/19880131988-05-12012 May 1988 Insp Rept 50-302/88-13 on 880418-22.No Violations Noted. Major Areas Inspected:Seismic Monitoring Program,Fire Protection/Prevention Program,Followup on Previously Identified Insp Items & LERs IR 05000302/19880111988-05-0202 May 1988 Insp Rept 50-302/88-11 on 880312-0415.Violations Noted. Major Areas Inspected:Plant Operations,Security,Radiological Controls,Ler & Noncomforming Operations Repts,Refueling Activities & Licensee Actions on Previous Items 1990-09-24
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000302/19990051999-09-13013 September 1999 Insp Rept 50-302/99-05 on 990704-0814.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000302/19990041999-07-27027 July 1999 Insp Rept 50-302/99-04 on 990523-0703.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19990031999-06-0404 June 1999 Insp Rept 50-302/99-03 on 990411-0522.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Maint, Operations,Engineering & Plant Support IR 05000302/19990021999-05-0606 May 1999 Insp Rept 50-302/99-02 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000302/19990011999-03-29029 March 1999 Insp Rept 50-302/99-01 on 990117-0227.No Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000302/19980101999-01-0404 January 1999 Insp Rept 50-302/98-10 on 981025-1205.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Insp Also Included Results of Physical Security Specialist ML20199D6161999-01-0404 January 1999 Notice of Violation from Insp on 981025-1205.Violation Noted:Its Requirements for Valve Position Verifications Not Met as Evidenced by Listed Examples IR 05000302/19980131998-12-16016 December 1998 Insp Rept 50-302/98-13 on 981116-20.No Violations Noted. Major Areas Inspected:Area of Plant Support by Regional Safeguards Specialist.Physical Security Program Was Evaluated IR 05000302/19980121998-12-0101 December 1998 Insp Rept 50-302/98-12 on 981013-16.No Violations Noted. Major Areas Inspected:Observation & Evaluation of Biennial EP Exercise for Crystal River Unit 3 IR 05000302/19980091998-11-13013 November 1998 Insp Rept 50-302/98-09 on 980913-1024.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19980081998-10-0606 October 1998 Insp Rept 50-302/98-08 on 980802-0912.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maint & Plant Support IR 05000302/19980071998-08-31031 August 1998 Insp Rept 50-302/98-07 on 980621-0801.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19983011998-07-31031 July 1998 NRC Operator Licensing Exam Rept 50-302/98-301,including Completed & Graded Tests,For Tests Administered on 980629-0702 IR 05000302/19980061998-07-20020 July 1998 Insp Rept 50-302/98-06 on 980510-0620.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000302/19980041998-06-0808 June 1998 Insp Rept 50-302/98-04 on 980322-0509.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20249A2941998-06-0808 June 1998 Notice of Violation from Insp on 980322-0509.Violation Noted:As of 980423,licensee Had Not Complied W/Requirements of Procedure CP-111,in That,Only Two of Discrepancies Identified in Ioc NL97-0262,had Been Documented IR 05000302/19980991998-06-0404 June 1998 SALP Rept 50-302/98-99 for 961006-980509 ML20216H8941998-04-0808 April 1998 Insp Rept 50-302/98-03 on 980208-0321.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20216H8871998-04-0808 April 1998 Notice of Violation from Insp on 980208-0321.Violation Noted:On 980220,Axial Power Imbalance Alarm Was Inoperable for Approx 3.5 Hours & Axial Power Imbalance Was Not Verified to Be within Acceptable Operating Limits ML20248L6171998-03-16016 March 1998 Notice of Violations from Insp on 980126-30.Violations Noted:Test Program for ECCS Operating in Piggyback Mode Did Not Demonstrate That Sys Would Perform Satisfactorily in Service IR 05000302/19980021998-03-13013 March 1998 Insp Rept 50-302/98-02 on 980126-30.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering.Emergency Operating Procedures Were Also Reviewed ML20216E9611998-03-0404 March 1998 Insp Rept 50-302/98-01 on 980104-0207.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20216E9291998-03-0404 March 1998 Notice of Violation from Insp on 980104-0207.Violations Noted:On 980203 Licensee Failed to Accomplish Required Posting of Bulletin Boards ML20203F5561998-02-23023 February 1998 Notice of Violation from Insp on 971021-24,1208-12 & 980105-09.Violations Noted:Implementation of Validation Program Did Not Adequately Demonstrate Usability of Emergency Procedures ML20203F5631998-02-23023 February 1998 Insp Repts 50-302/97-12 on 971020-24,1208-12 & 980105-09. Violations Noted.Major Areas Inspected:Adequacy of EOPs Development Process PNO-II-98-005, on 980201,plant Commenced Reactor Startup & Entered Mode 2 Conditions (Keff 0.99).On 980202,criticality Was Achieved,Followed by Mode 1 Conditions.Unit Scheduled to Be at 100% Power Late 9802051998-02-0202 February 1998 PNO-II-98-005:on 980201,plant Commenced Reactor Startup & Entered Mode 2 Conditions (Keff 0.99).On 980202,criticality Was Achieved,Followed by Mode 1 Conditions.Unit Scheduled to Be at 100% Power Late 980205 PNO-II-98-004, on 980130,Region II Administrator Informed FPC That NRC Was Satisfied W/Completion of FPC Actions Specified in Cal, & Concurred That Plant,Unit 3 Could Operate IAW License1998-01-30030 January 1998 PNO-II-98-004:on 980130,Region II Administrator Informed FPC That NRC Was Satisfied W/Completion of FPC Actions Specified in Cal, & Concurred That Plant,Unit 3 Could Operate IAW License IR 05000302/19970191998-01-29029 January 1998 Insp Rept 50-302/97-19 on 971130-980103.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-II-98-003, on 980120,licensee Placed Two Reactor Coolant Pumps in Operation to Add Heat to Rcs.Licensee Has Not Yet Requested Release from Cal.Licensee Issued Press Release1998-01-22022 January 1998 PNO-II-98-003:on 980120,licensee Placed Two Reactor Coolant Pumps in Operation to Add Heat to Rcs.Licensee Has Not Yet Requested Release from Cal.Licensee Issued Press Release ML20199G6761998-01-16016 January 1998 Notice of Violation from Insp on 971201-16.Violation Noted: as of 971211,licensee Health Physics Supervisors Failed to Identify & Correct Personnel Contamination Repts That Were Not Completed IAW Requirements of Procedure HPP-104 ML20199G6861998-01-16016 January 1998 Insp Rept 50-302/97-20 on 971201-16.Violations Noted.Major Areas Inspected:Operations,Radiological Protection,Maint & Surveillance Programs IR 05000302/19972011998-01-0909 January 1998 Insp Rept 50-302/97-201 on 970929-1003.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of CAs Previously Committed by Licensee & Related Discussion W/Personnel IR 05000302/19970181998-01-0606 January 1998 Insp Rept 50-302/97-18 on 971117-21 & 1201-12.No Violations Noted.Major Areas Inspected:Plant Support ML20198N6271997-12-29029 December 1997 Insp Rept 50-302/97-19 on 971026-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20198N6211997-12-29029 December 1997 Notice of Violation from Insp on 971026-1129.Violation Noted:On 971105,licensee Failed to Perform Adequate Se,Per 10CFR50.59 for Functional Test Procedure for B Emergency Diesel Generator Power Upgrade & Radiator Replacement Mods ML20198P2251997-12-29029 December 1997 Insp Rept 50-302/97-21 on 971203.Violations Noted.Major Areas Inspected:Noncompliances in Design control,10CFR50.59, Procedural Adequacy,Reportability & Corrective Actions.No Notice of Violation Being Issued in This Case ML20199A2091997-12-22022 December 1997 EN-97-116:on 971229,informs Commission That Staff Intends to Exercise Enforcement Discretion in Accordance W/Section VII.B.2 of Enforcement Policy & Not Issue NOV or Proposed Imposition of Civil Penalty to Util for Violations PNO-II-97-063, on 971218,Crystal River Unit 3 Achieved Significant Milestone by Declaring a EDG Operable & Thus Making Both EDGs Operable for Mode 5.Licensee Does Not Plan to Issue Press Release.State of Fl Notified1997-12-19019 December 1997 PNO-II-97-063:on 971218,Crystal River Unit 3 Achieved Significant Milestone by Declaring a EDG Operable & Thus Making Both EDGs Operable for Mode 5.Licensee Does Not Plan to Issue Press Release.State of Fl Notified IR 05000302/19973011997-12-17017 December 1997 NRC Operator Licensing Exam Rept 50-302/97-301 Including Completed & Graded Test for Test Administered on 971118. Exam Results:Sro Candidate Passed Written Exam ML20203A1911997-12-0404 December 1997 Notice of Violation from Insp on 971006-24.Violation Noted:Work Request Numbers 333797 & 333798,issued in Mar 1997 to Install Stem Protectors on Actuators Were Closed W/O Performing Work ML20203A2061997-12-0404 December 1997 Insp Rept 50-302/97-14 on 971006-24.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering ML20202D7301997-11-24024 November 1997 Notice of Violation from Insp on 970921-1025.Violation noted:10CFR50.59 SE Had Not Been Performed as Required within 90 Days on Wds Piping non-conforming Condition IR 05000302/19970161997-11-24024 November 1997 Insp Rept 50-302/97-16 on 970921-1025.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-II-97-059, on 971118,established Vacuum in Main Condenser & Steam Bubble in Pressurizer.Completed Work on Planned Upgrades for B Edg.Resident & regional-based Inspectors Are Closely Monitoring Subject Activities1997-11-18018 November 1997 PNO-II-97-059:on 971118,established Vacuum in Main Condenser & Steam Bubble in Pressurizer.Completed Work on Planned Upgrades for B Edg.Resident & regional-based Inspectors Are Closely Monitoring Subject Activities ML20212B9061997-10-16016 October 1997 Notice of Violation from Insp on 970817-0920.Violations Noted:Scaffolding Control Program Does Not Contain Measures to Assure That Deviations from Design Quality Std for safety-related Equipment Installed Have Adequate Control IR 05000302/19970131997-10-16016 October 1997 Insp Rept 50-302/97-13 on 970817-0920.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000302/19970151997-10-14014 October 1997 Partially Withheld Insp Rept 50-302/97-15 on 970922-26 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Plant Support by Regional Safeguards Inspector ML20211Q2581997-10-14014 October 1997 Notice of Violation from Insp on 970922-26.Violation Noted:On 970820,individual Was Terminated & Authorized Access Was Not Removed from Plant Security Computer Until 970905 ML20211E4891997-09-12012 September 1997 Notice of Violation from Insp on 970713-0816.Violations Noted:On 970728,licensee Personnel Performed quality-related Work to Restore once-through SGs During Reduced RCS Inventory Operation Without Written & Approved Procedure ML20211E5791997-09-12012 September 1997 Insp Rept 50-302/97-11 on 970713-0816.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support 1999-09-13
[Table view] |
Text
.
o UNITED STATES
,*
!"- n NUCLEAR REGULATORY COMMISSION
$ ec REGION ll
[ 101 MARIETTA ST., N.W., SUITE 3100 ob ATLANTA, GEORGIA 30303
.....
Report No. 50-302-81/23 Licensee: Florida Power Corporation 320134th Street, South St. Petersburg, FL 33733 Facility Name: Crystal River Unit 3 Nuclear Generating Plant Docket No. 50-302 License N OPR-72 Inspection at n ar Cr7stak ver, Florida Inspectors: b 1 Arm 1 e 'f/UA f/ / /2 [ 2-T. F. S,tjetk Ddte S'igned
& c ,enior h6& Resident (Inspector B. W. . 1)h, Resi nt Inspectori i/s/r'
Date Signed Approved by: [/D V. 'm W L /2- L Br,gIwnlee, Section Chief, Division of Date Sidned Resident and Reactor Project Inspection SUMf1ARY Inspection on October 24 - December 2,1981 l
Areas Inspected This routine inspection by the resident inspectors covered plant operations, security, radiological controls, Licensee Event Report (LER's) and Nonconfonning Operations Report (NCOR's), nonroutine events, refueling activities, environmental protection, and the licensee's action on previous inspection item Numerous facility tours were conducted and facility operations observed. Some of these tours and observations were conducted on back shifts. The inspection involved 249 hours0.00288 days <br />0.0692 hours <br />4.117063e-4 weeks <br />9.47445e-5 months <br /> onsite by two resident inspector Results Three violations were identified (Failure to follow procedures during plant operations, paragraph 5.a and 3.a; Failure to follow radiation protection procedures for contamination control, paragraph 5.b(4); Failure to calibrate reactor outlet temperature instrumentation, paragraph 5.b(8). One deviation was identified (Total reactor outlet temperature instrumentation error is in excess ofFSARanalyzederror, paragraph 5.b(8)).
'
j 8207010483 820618 i PDR ADOCK 05000302 l G PDR
!
.
.
DETAILS Persons Contacted Licensee Employees P. Baynard, llanager, fluclear Support Services
- Boldt, Technical Services Superintendent
- C. Brown, fluclear Compliance Supervisor D. Brock, Nuclear liaintenance Specialist J. Bufe, Compliance Auditor 11. Collins, Reactor Specialist
- J. Cooper, QA/QC Compliance flanager W. Cross, Licensing lianager
- T. Fay, Plant Engineer V. Hernandez, Compliance Auditor
- S. Johnson, liaintenance Staff Engineer
- B. Komara, Compliance Auditor T. Lutkehaus, Technical Assistant to the Nuclear Plant flanager
- li.11 ann, Compliance Auditor J. 11asada, Plant Engineer
- P. ficKee, Operations Superintendent G. Perkins, Health Physics Supervisor
- D. Poole,fluclear Plant flanager
- H. Reeder, Shift Technical Advisor
- G. Ruszala, Chemical / Radiation Protection Manager
- D. Smith, Security and Special Projects Superintendent
- K. Lancaster, Senior Quality Auditor J. Lander, liaintenance Superintendent G. Williams, QA/QC Supervisor
- K. Wilson, Licensing Specialist Other licensee employees contacted included office, operations, engineering, maintenance, chem / rad, and corporate personne U. S. Nuclear Regulatory Commission
- V. Brownlee, Chief, Reactor Projects Section 2
-
State of Florida C. Ness, Health Physicist, Department of Health and Rehabilitative Services
- Present at 11/11/81 Exit interview
- Present at 12/2/81 Exit interview
- Present at both Exit interviews Exit Interview The inspectors met with licensee representatives (denoted in paragraph 1) on numerous occasions during and at the conclusion of the inspection on
- _ . .
.
i
,
December 2,198 During this meeting the inspectors summarized the scope and findings of the inspection as they are detailed in this repor During this meeting the violations and inspector followup items were discusse As a result of the reactor coolant system overflows that are discussed in
, paragraph 8 of this report, the licensee presented additional long term
'
! corrective actions that are being taken to minimize recurrence of these events. These actions include:
-A procedural review is in progress to detemine if there are other procedures or conflicts between procedures that could result in system overflows or spill A procedural review is in progress to determine the feasibility of
- developing valve check lists that are operational mode dependen This review is expected to be completed by March,198 The licensee is initiating a new computer system that will enable
- operators to assess system status with respect to outstanding maintenance
'
activities and equipment cle4rarces. This system is in partial operation now and is expected to be fully operational by the end of January,198 The inspectors acknowledged the licensee's presentation and stated that these activities would be reviewed in subsequent inspections.
l Licensee Action on Previous Inspection Findings (Closed) Inspector Followup Item (302/81-02-16): The licensee's review of Engineered Safety Features Actuation System (ESFAS) relay failures has identified the Clark type Pfl relay as the cause of these failures. These failures were subsequently discussed in NRC Inspection Report 50-302/81-05, paragraph 8.b (3). The licensee is modifying these relays to prevent sticking and this activity is being tracked in accordance with Inspector Followup Item (302/81-05-12). The licensee has also identified failure problems with solid-state triac relays manufactured by Hamlin. Since Hamlin no longer manufactures these relays, the licensee has had to replace these relays with a relay manufactured by Crydon. The licensee's activities in replacing Hamlin relays with Crydon relays has identified additional problems and these problems are identified in paragraph 6.b of this repor Items affecting both solid-state relays and Clark Pil relays are being tracked in accordance with items (302/81-05-12) and (302/81-23-08). This
'
item is closed for record purpos (Closed) Unresolved Item (302/79-01-02): The licensee's leakrate procedure has been reviewed and independent calculations performed by the resident inspectors. In addition a reactor coolant system leakrate verification was conducted utilizing an independent calculation method (See NRC Inspection Report 50-302/81-15, paragraph 10) and the results of this verification compared favorably with the results of SP-31 , _ - - _ - __ . _ _ . .
.
(Closed) Inspector Followup Item (302/81-15-11): Quality Operating Manual procedure Q0P 7.0 has been revised as revision 10 on October 15, 1981 to include a new section 4.1.3 This new section rt'uires the signing and dating of a QCI at the time the material is picked up or delivered. Action on this item is complet (Closed) Violation (302/81-13-01): The licensee has completed training of all necessary personnel by the November 15, 1981 date committed to in the revised response dated October 13, 1981. The inspector has reviewed records and interviewed personnel to determine the extent of this training and considers the licensee's actions to be complete (0 pen) Violation (302/81-19-05): The licensee has revised surveillance procedure SP-110, Reactor Protective System Functional Testing, to functionally exercise the reactor building pressure switches on a monthly basis. The resident inspector reviewed the revised procedure and observed the new testing. The licensee's response does not address whether a review of other systems was conducted to verify that all required channel sensors are exercised. The licensee will conduct this review and issue a revised response. This issue remains open pending completion of this review and issuance of a revised respons (Closed) Violation (302/81-11-07): The licensee has fomed three person subcommittees to perfom the safety evaluations required by 10CFR 50.5 These subcommittees then report their findings to the full Nuclear General Review Committee (NGRC) for review. Three person subcommittees are also used to review plant operating reports, operating abnormalities or deviations, deficiencies in design or operation, and corporate audit resal ts. The inspector reviewed NGRC meeting minutes for meetings conducted during the period of July thorough November 11, 1981 and the summary reports of subcommittee reviews. The inspector also attended the NGRC meeting conducted on November 12, 1981 to observe committee activities. Based upon these reviews and observations, the licensee's corrective actions are considered to be complet (Closed) Inspector Followup Item (302/81-21-11): The remote RC temperature instrument RC-4A-T12 has been replaced. The inspectors have no further question of this ite (Closed) Inspection Followup Item (302/81-21-06): The inspectors verified OP-406 revision adequately places the fuel transfer canal level alam in service during filling operation The inspectors have no futher questions on this ite (Closed) Inspection Followup Item (302/81-21-07): The inspectors verified the installation of replacement gages of a smaller range on the snubber tester. The inspectors have no further questions on this ite (Closed) Inspector Followup Item (302/81-21-08): The inspectors verified SP-605 revision to classify the checking / cleaning requirements on the EDG
crankcase ejector and oil separator. The inspectors have no further question on this ite (Closed) Inspector Followup Item (302/81-15-06): The licensee has completed replacement of the aluminum bushings with stainless steel bushings in all of the inaccessible snubbers. The resident inspectors have followed these replacement activities by observing selected snubber rebuilding and testing and reviewing associated documentation. Due to additional functional test failures caused by unsatisfactory bleed rates, the licensee has committed to rebuild additional snubbers located in accessible areas. These committments are discussed in f4RC Inspection Report 50-302/81-29. The licensee's activities with respect to the inaccessible snubbers in considered to be comple te.
4. Unresolved Items There were no unresolved items identified during this report period.
5. Review of Plant Operations The plant continued in flode VI, refueling operations, and flode V, cold shutdown, for the majority of this inspection perio On December 2, 1981, the Plant entered flode IV, hot shutdown operations, in preparation for performing unit startup surveillance activitie Shift Logs and Facility Records The inspectors reviewed the records listed below and discussed various entries with operations personnel to verify compliance with TS and the Licensee's administrative procedures:
-Shift Supervisor's Log;
-Reactor Operator's Log;
-Equipment Out-of-Service Log;
-Shift Relief Checklist;
-Control Center Status Board;
-Short Term Instructions;
-Auxiliary Building Operators Log;
-Chemistry / Radiation Log;
-Daily Shutdown Surveillance Log;
-Refueling Supervisor's Log;
, l
. .
-Work Requests;
-!!odification Approval Records; and,
-Outage Coordinator's Lo In addition to these record reviews, the inspectors independently verified selected clearance order tagout As a result of these reviews, the following violation was found:
During a review of logs on October 29, the inspector noted an eqtry in the Outage Coordinator's log discussing steam flashing in the reactor coolant system hot legs that occurred during the plant cooldown on October 1,1981. The inspector cross-checked this log entry with the Nuclear Shift Supervisor's log and the Nuclear Operator's log and noted that no such entry had been made in either of these logs. This finding was discussed with operations personnel and the licensed operators on a duty when the event occured. These personnel stated that a log entry i
was not made because they did not consider hot leg steam flashing and the resultant steam bubble formation in the hot leg to be an unusual occurrence or trend. The inspector disagreed with the licensee's conclusions and stated that voiding in the reactor coolant system of a pressurized water reactor in any location other than the pressurizer is an unusual occurrenc Procedure AI-500, Conduct of Operations, requires adherence to the Implementation llanual (OSIri). The OSIfi, in Section III.E.2.A and B, requires log entries in the lluclear Shift Supervisor's Log and the Nuclear Operator's Log for any unusual occurrences or unusual trends or conditions observed. Failure to adhere to these requirements is contrary to the requirements of Technical Specification 6.8.1 and is a violatio Violation (302/81-23-01): Failure to adhere to administrative and operational procedures.
l The licensee took immediate corrective action to prevent recurrence of this event. These actions included:
-Discussions with the operators involved and with other operating shifts to insure that all personnel understand that RCS flashing is an unusual occurrence;
-Revised the OSIll to clarify the logging instructions; and,
-Revised procedure OP-209, Plant Cooldown, to provide additional steps to minimize steam flashing in the RC The inspectors reviewed these corrective actions and have detennined that no additional response to this item is require . .
b. Facility Tours and Observations Throughout the inspection period, facility tours were conducted to observe operations and maintenance activities in progress. Some operations and maintenance activity observations were conducted during backshifts. Also,during this inspection period, numerous licensee meetings were attended by the inspectors to observe planning and management activitie The facility tours and observations encompassed the following areas:
-Security Perimeter Fence;
-Turbine Building;
-Control Room;
'
-Emergency Diesel Generator Rooms;
-Auxiliary Building;
-Intermediate Building;
-Reactor Building;
-Battery Rooms; and,
-Electrical Switchgear Room During these tours, the following observations were made:
(1) lionitoring instrumentation - The following instrumentation was
, observed to verify that indicated parameters were in accordance i with the Technical Specifications for the current operational flode:
i -Equipment operating status;
-Area, atmospheric and liquid radiation monitors; l -Electrical system lineup;
, -Reactor operating parameters; and, I
'
-Auxiliary equipment operating parameters.
No discrepancies were identified in this area.
l (2) Shift Staffing - The inspectors verified by numerous checks that operating shift staffing was in accordance with Technical i Specification requirements. In addition, the inspectors observed
/
. .
shif t turnovers of major work groups, radiation protection personnel, refueling group personnel, and plant operations personnel, on different occasions to verify that information concerning plant status, operational problems, and other pertinent plant items were transmitted to oncoming shifts. No discrepancies were identified in this are (3) Plant housekeeping conditions - Storage of material and components and cleanliness conditions of various areas throughout the facility were observed to determine whether safety and/or fire hazards exist. No discrepancies were identified in this are (4) Radiation areas - Radiation control areas (RCA's) were observed to verify proper identification and implementation. These observ-ations included selected licensee-conducted surveys, review of step-off pad conditions, disposal of contaminated clothing, and area posting. Area posting was independently verified for occuracy through the use of the inspector's own monitoring instrument. The inspectors also reviewed selected radiation work permits and observed personnel use of protective clothing, respirators, and personnel monitoring devices to assure that the licensee's radition monitoring policies were being followe The following item was identified:
During a tour of the auxiliary building (AB) on December 1,1981, the inspector observed a person in a contaminated area wearing plastic shoe covers as the only means of radioactive contamination control. In addition, this worker was observed leaving the contaminated area partially carrying and partially dragging a bundle of rope without observing required contamination control measures (rope not bagged and/or gloves worn). The inspector questioned the worker as to the origin of the rope and lack of contamination controls. The worker
'
indicated that the rope was probably contaminated and that he didn't think to bag it since he was taking it to another contaminated are The inspector had the individual stand fast and then notified a ChemRad technician of the situatio The ChemRad technician assumed control of the situation and determined that the individual had contaminated his hands to level of approximately 1000 disintergrations per minute (DPil) . A further check into the incident indicated the individual had entered the contaminated area without consulting ChanRad personnel for the clothing requirements as required by the standing radiation work
,
permit (SRWP), and without the clothing that would have been specified for the area.
'
.
Chemistry and Radiation Protection Procedure, RP-101, section 4. requires: An individual entering a contaminated area to wear proper clothing i
and devices necessary for contamination control, l
.
.. - . - - . . _ _ __ _ _ . _ - __ _ _
._ . _ _ _ - - _
.
8 Chem / Rad personnel to be contacted to specify the clothing requirements for entering a contaminated area covered by (SRWP.)
In addition, Section 4.4 of RP-101 requires work to be conducted in a manner consistent with maintaining a minimum of contamination sprea Failure to adhere to the requirements of RP-101 is contrary to the requirements of Technical Specification 6.11 and is a violatio Violation (302/81-23-02): Failure to adhere to the requirements of RP-101 for contamination contro (5) Radioactive waste controls - Selected liquid and gaseous rddioactive releases were observed to verify that approved procedures were utilized, th;c appropriate release approvals were obtained, that required samples were taken, and that appropriate release control instrumentation was operable. Portions of radioactive waste shipment operations were observed to insure that the licensee's controls were implemented. flo problems were identified in this are (6) Security Controls - Security controls were observed to verify that security barriers are intact, guard forces are on duty and access to the protected area (PA) is controlled in accordance with the facility security pla Personnel within the PA were observed to insure proper display of badges and that personnel requiring escort were properly escorted. Personnel within vital areas were observed to insure proper authorization for the area. tio probelms were identified in this are (7) Operating Procedures - Operating Procedures (UP) use was observed to verify that:
-approved procedures were being used;
-qualified personnel were performing the operations; and,
-Technical Specification requirements were being followe The following procedures were observed:
-0P-202, Plant Heatup;
-0P-303, Draining and flitrogen Blanketing of the RC System;
-0P-404, Decay Heat Removal System;
-0P-608, OTSG Secondary Fill, Drain, and Layup; and-0P-209, Plant Cooldow fio problems were identified during these observation . .
(8) Surveillance Testing - Surveillance testing was observed to verify that:
-approved procedures were being used;
-qualified personnel were conducting the tests;
-testing was adequate to verify equipment operability;
-calibrated equipment, as required, was utilized; and,
-Technical Specification requirements were being followed.
I The following tests were observed:
-SP-455, Functional Test of Vital Bus Redundant Transformers (completed procedure review);
-SP-112, Calibration of the Reactor Protection System, (reactor coolant pump power monitor (RCCPil) data review and procedure review);
-SP-532, Reactor Building (RB) and Auxiliary Building (AB) Fuel Handling Bridge Electrical Interlock Checks (RB main bridge only);
-SP-220, Source Range Functional Test During Refueling Operations (data review);
-PT-132, Leak Testing 0TSG "A" with Helium or Nitrogen (completed procedure review);
-SP-415 Teansfer From Preferred Off-Site Power Source to Alternate Off-Site Power Source and Return to Preferred Off-Site Source (observed entire procedure);
-SP-179, Containment Leakage Tests - Type B and C (AHV-1C and ID observed);
-SP-416, Emergency Feedwater Automatic Actuation (turbine driven pump only);and,
-SP-422, Reactor Coolant System Heatup Surveillanc As a result of these observations, the following items were identified:
During a review of SP-112, Calibration of the Reactor Protective System, (RPS), for the purpose of verifying compliance with Technical Specifications, the inspector discovered that the RPS hot leg resistance temperature detectors (RTD's) were not included in the calibration procedure for the reactor outlet temperature channel. This issue was discussed the licensee and the inspector's findings were acknowledged.
- . - - --- -
an - - .---n-, ,- - - - - - ,
i
,
1 . .
l Technical Specification 4.3.1 requires the RPS reactor outlet channel to be calibrated at least once every 18 months. Technical Specifi-cation 1.9 requires a channel calibration to encompass the entire channel including the senso Contrary to Technical Specifications, the RPS reactor outlet RTD's were not included in the reactor outlet temperature channel calibratio Violation (302/81-23-03): Failure to include the reactor outlet RTD's in RPS outlet temperature channel calibratio A further review of SP-112 indicated that the existing reactor outlet channel calibration allows acceptance of a total error of + 3.065* This total includes a sensor error of + 0.065 F, a process error of +
-
2.5*F, and a bistable error of +0.5*F, in addition, the + 3.065*F does not include the readability error of the signal converter meter used to calibrate the process equipment. This issue was discussed with the licensee and the inspector's comments were acknowledge Final Safety Analysis Report (FSAR) section 7.1.2.2.3 specifies a worst case assumption for the total error from sensor, processing equipment and trip bistable of the reactor outlet trip channel to be +1 Contrary to the above, allowable total channel error of the reactor outlet temperature trip channel exceeds the + 1*F worst case assumptions of the FSA Deviation (302/81-23-04): Failure to meet the worst case assumptions for allowable reactor outlet temperature trip channel total error of +-
1"F, as required by the FSA (9) flaintenance Activities - The inspector observed maintenance activities to verify that:
-correct equipment clearances were in effect;
-Work Requests (W/R's), Radiation Work Permits (RWP's), and Fire Preventive Work Permits, as required, were issued and being followed;
-Quality Control personnel were available for inspection activities as required; and,
-Technical Specification requirements were being observe The following maintenance activities were observed:
-Pfl-145, Reactor Coolant Pump Motor Disassembly and Inspection (work package review); i l
l
_ -. .
. .
(
-11P-150, Disassembly and Reassembly of fluclear Service Seawater and Decay Heat Seawater Pumps (work package review of RWP-1A work);
-ftP-119, Relief Valve Removal, Repair and Reinstallation (D0V-33 work);
-!!P-130, Pipe Snubber liaintenance (testing, and rebuilding of numerous hydraulic snubbers);
-f1P-123, Disassembly and Reassembly of fluclear Services Closed Cycle Cooling Water Pumps (coupling alignment of SWP-1A);
-Pft-133, Equipment Lubrication Procedure (oil addition on SWP-1A);
-itP-166, Reactor Coolant Pump Seal Package Refurbishment and Testing (testing of RCP-3D seal);
-MP-147, Adjustment of Containment Purge Valves (AliV-1D seat adjustment work package review);
-itAR-79-10-86, Installation of Safety Grade Anticipatory Reactor Trip (work package review and observation of wiring modifications in RPS channel "B");
-f1AR 81-3-87, Reactor Building Purge Duct Supply Heater (review of work package);
-11AR 78-8-15, Power Level Upgraue Isolation System (portions of reactor coolant pump power monitor (RCPPM) installation);
-!!AR 78-8-159 Installation of Testing of RCPPM (time response testing observation;) and,
-itAR 81-5-28, CAV-1, 3, 4, 5 and 126 Relocation (review of work package and observation of CAV-1, 3, 4 and 5 relocation).
fio problems were identified in this are (10) Refueling Activiites - Refueling activities were observed and procedures were reviewed to verify that:
-approved procedures were being used;
-qualified personnel were perfoming the activities;
-procedures were adequate to accomplish the required activities;
-calibrated equipment (as required) were utilized; and,
-Technical Specification requirements were being followe _ _ _ _ _ - - _ _-
. .
The following activities were observed:
-FP-203, Defueling and Refueling Operations;
-SP-406, Refueling Operations Daily Data Requirements; and-SP-532, Reactor Building Fuel Handling Bridge Electrical Interlock Checks (main bridge only).
Flo problems were identified in this are (11) Pipe hangers seismic restraints - Pipe hangers and seismic restraints (snubbers) on safety-related systems were observed to insure that fluid levels were adequate and no leakage was evident (where appropriate), that restraint settings were appropriate, and that anchoring points were not bindin The inspector was notified of possible snubber installation deficiencies associated with the major refurbishment job being performed on all of the' reactor building (RB) hydraulic snubber The specific deficiencies cited were associated with possible missing adapter bushings on itSH-164 and 165 hydraulic snubber Based on this information, the inspector verified the installation of 16 snubbers that were rebuilt and reinstalled in the RB, including itSH-164 and 16 flo missing adapter bushings were found. The licensee was also notified of the alleged deficiencies in the snubber installation The licensee's inspection of the two snubbers revealed no missing adapter bushings but did indicate a missing spacer on f1SH-165. To assure an adequate level of confidence in the mechanic and the inspector associated with the f1SH-165 installation, the licensee
,
reinspected 10 additional snubber installations in which these
'
individuals participate Flo discrepancies were noted. Based on the inspector's review and the licensee's action to this issue,
, the allegation of missing adapter bushings is considered
- unsubstantiated and the inspectors have no further questions on this issue at this time.
- Review of Licensee Event Reports and ilonconforming Operations Reports The inspector reviewed Licensee Event Reports (LERs) to verify that
-The reports accurately describe the events;
, -The safety significance is as reported;
!
-The report satisfies requirements with respect to information provided and timing of submittal;
[
-Corrective action is appropriate; and,
__
_ ._ _ _ _ _
_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
. .
I
-Action has been take Ler's 81-63, 81-68, 81-69, 81-71, and 81-72 were reviewed. This review identified the following items:
(1) LER 81-63 reported that various hydraulic snubbers were discovered to be inoperable during surveillance testing. The resident and regional inspectors have followed the licensee's snubber rebuilding activities including observing selected snubber rebailding and testing and reviewing associated documentation. As discussed in paragraph 3 of this report in inspector followup item (302/81-15-06), the licensee has completed rebuilding snubbers located in inaccessible areas and has committed to rebuild snubbers in accessible areas. These canmitments are discussed in NRC Inspection Report 50-302/81-29. Two items remain to be completed, rebuilding of accessible area snubbers and completion of an engineering study to evaluate snubber failure Inspector Followup Item (302/81-23-05): Review accessible snubber rebuilding activities and the results of the snubber failure engineering evaluatio (2) LER 81-68 reported an omission in the accident analysis concerning the High Energy Line Break Outside Containment (HELG0C) due to a change in the operation of the turbine driven emergency feedwater pump (EFP-2). An engineering design evaluation is in progress to determine what modifications will be necessary to ensure HELB0C protection for these steam line '
Inspector Followup Item (302/81-23-06): Review the engineering evaluation and modification progress for the EFP-2 HELB0C concer (3) LER 81-71 reported an error in the accident analysis for the steam generator tube rupture accident. The licensee has commenced additional analysis to verify that the release limits of 10 CFR Part 100 would not be exceede The licensee expects to complete this analysis by April, 198 Inspector Followup Item (302/81-23-07): Review the revised accident analysis for the steam generator tube rupture acciden b. The inspector reviewed NCOR's to verify the following:
-Compliance withthe Technical Specifications;
-Corrective actions as identified in the reports or during subsequent .
reviews have been accomplished or are being pursued for completion; l-Generic items are identified and reported as required by 10 CFR Part 21; and, l
- - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ . _ _ . - _ _ _ .
_
. .
l
l-Items are reported as required by the Technical Specification r 81-326 81-359 81-393 81-414 81-437 81-327 81-360 31-394 81-416 81-457 81-342 81-362 81-395 81-417 81-459 81-343 81-366 81-397 81-419 81-458 81-344 81-369 81-420 81-420 81-464 81-345 81-370 81-400 81-421 81-346 81-372 81-404 81-422 81-347 81-373 81-402F 81-427 81-348 81-374 81-405 81-428 81-350 81-375 81-406 81-429 81-352 81-377 81-407 81-432 81-353 81-385 81-409 81-431 81-354 81-386 81-410 81-433 81-355 81-387 81-411 81-434 81-357 81-388 81-412F 81-435 As the result of this review, the following item was identified:
NCOR 81-409 reported the failure of a bypass relay to de-energize during performance of surveillance test SP-132, Engineered Safeguards Channel Calibration. The failure of the relay to de-energize was traced to an induced voltage being generated in the control circuitry wire causing a Crydon solid-state triac relay to fail to turn off. The licensee has been replacing Hamlin solid-state triac relays with Crydon solid-state triac relays due to the unavilability of the Hamlin relay The licensee has identified additional problems with the Crydon relays (involving failure to pass receipt inspection and testing) and has presently stopped installation of these relays. The licensee is re-evaluating the use of the Crydon relays based upon these recent finding Inspector Followup Item (302/81-23-08): Review the licensee's evaluation of Crydon solid-state triac relays in ESFA . Environmental Protection On November 16, the inspector accompanied a health physicist from Florida's Department of Health and Rehabilitative Services (DHRS) during the weekly tour to check and collect samples fran the six sampling stations located around the Crystal River plant. The following sampling stations were checked:
-(C-26) located near the Florida Power Corporation (FPC) substation in Beverly Hills;
-(C-07) located near the water tower in Crystal River;
.
-(C-46) located on FPC property near the fossil Unit No. 4;
-(C-04) located at the hydrodam near Yankeetown;
-(C-18) located near the Yankeetown water tower; and,
-(C-40) located on FPC property near the quarr The inspector discussed the sampling collection techniques with the health physicist and reviewed the sampling documentatio No inadequacies were identifie . Non-Routine Events Reactor Coolant System (RCS) Overflow From Borated Water Storage Tank On November 6,1981, at 2013, with the plant in 11 ode 6 (Refueling)
operations, approximately 1650 gallons of reactor coolant system (RCS)
water overflowed the partially drained RCS and flowed into the reactor building (RB). The water was contained in the RB with most of the water flowing into the RB sump. There were no releases or personnel contamination as a result of this even The cause of this overflow was failure of the operator to follow operations procedure OP-404, Decay Heat Removal System, during switching from the "B" Decay Heat train to the "A" decay heut trai Procedure OP-404 requires the closing of the borated water tank (BWST)
suction valve DHV-34 prior to starting the "A" decay heat train. Since the operator did not follow the procedure, DHV-34 was left open when the "A" train was started. This allowed water from the BWST to be pumped into the RCS thus raising the level in the partially drained system. Though the reactor vessel head had been placed upon the vessel, the head was unbolte the increasing level caused water to flow out around the reactor vessel flange, the control rod drive nozzles, the incore closure flanges and the once through steam generator (OTSG) upper manway When the operators received a " Low BWST Level" alarm, they immediately shut DHV-34, thus stopping the overflow. The excess water was then pumped back to the BWS Failure to follow procedures is contrary to the requirements of Technical Specification 6.8.1 and is considered to be another example of the violation identified in paragraph 5.a of this repor The licensee took immediate corrective action to prevent recurrence of this event. This corrective action included:
-Revised surveillance procedure SP-320, Operability of Boron Injection Sources and Pumps, to make the return to operation valve lineup mode
. .- -
,
E J
'
'
. , c
-
'
,
b '
.
'
dependent therefore assuring the BUST suction valves DHV-34 and DHV-35 ',
are shut following completion of the surveillance procedure while in '
'
'
(The leaving of DHV-34 open following completion of
'
11 odes 5 and SP-320 contributed to the overflow event); and, - 7-Discussion with the operator involved and with other operating shifts to emphasize the importance of following procedure ,
The inspectors reviewed the corrective action and have# determined that no additional response to this item is require ,
- l, b. 11ake-up System (fiUS) Overflow /
, ,
-
.
/ I On flovember 15, 1981, at approximately 1930, with the plant in' hode 5 ' -
(Cold Shutdown) operations, approximately 100 gallons of reacts coolant system (RCS) make-up water flowed from the flus to the auxiliary'
building (AB) via an open drain valve (t1UV-339). 'The watcr.was '
'
contained in the AB with most of the water flowing into the AB sum There were no releases or personnel contamination aso ' f , result of'this s
'
even ,
The 11US had baen " tagged out" in accordance with a system clearance (10-365) to .tllow maintenance on the system. .Following completion of maintenance, clearance 10-365 was released thereby allowing the 110S to be refilled. Though the operator released the clearance in accordance with procedures, the operator failed to check the clearance log to insure that there were no additional outstanding clearance.t on the MU An additional clearance (10-310) was still outstanding on de i1VS and left drain valve i1VV-339 open. Since the licensee's method of operation includes a walk-down of a system when it is returned to
!
service for refilling, the open drain valve was quickly identified and
! shut thus stopping the flo The licensee took immediate corrective action to prevent recurrence of-this event. This corrective action included: /' ,
-
'
-Issued a memorandum to all Nuclear Shift Supervisors (NSS) >dascribing this event and the "practive actions that need to be implemente '
The fiSS were dirr to to review this memorandum with their shift; s
' ' '
personnel; aM-Revised the herot: _n Section Implementation fianual (OSIri) as revision 6 to require operations to review all outstanding clearances on a system prior to releasing the clearanc The inspectors reviewed these corrective actions and have -no further questions on this item at this tim c. Reactor Coolant System (RCS) Overflow Frc.1 Spent Fuel Cooling' System
.
On flovember 17, 1981, at approximately 1230, approximately 3000 gallons of spent fuel pool (SFP) cooling water was pumped into the RCS via the
__
.
. .
%
. 17 9 decay heat removal (OHR) syste This water caused the RCS, which was partially drained and in fiode 5 (Cold Shutdown) at the time, to fill the reactor. vessel and dump water into the drained coolant loops which then ran out~of.the open loop drain valves to the reactor building (RB)
sump. The amount of water flowing from the open drain valves was in excess,of'the RB drain capacity therefore allowing some water to flow onto the RB floor. There were no releases or personnel contamination
'
as a result of this even The cause of this event was an open valve (SFV-54) which cross
, cennected the decay heat removal system with the spent fuel cooling system. The, licensee was in progress of lining up the DHR and SFP systems to allow use of the SFP cooling purification system to purify
^
the RCS water. The proper valve lineups were conducted with operators verifying correct valve positions by initialling valve lineup sheet Some time during the completion of the valve lineup (which shut SFV-54)
~
and the commencing of RCS purification via the SFP system, valve SFV-54 was opene <
The licensee investigated this event and could not identify a reason for the reopening of valve SFV-54. The vtIve lineup was completed at about 0700 and the SFP purification flow started about 112 The inspector's review of this event included a review of associated documentation, interviews of on-duty operators, and a walk through of
, the valve lineup procedure for SFV-54 with the operator involved. The inspectors were also unable to determine cause for the even To prevent recurrence the licensee has taken the following actions:
-SFV-54 is a manually operated valve utilizing a chain operator. The liensee has locked all chain operated valves for systems that contain radioactive fluids or are required for reactor safety; and,
-Issued Short Term Instruction (STI) 81-92 directing operators to perform double valve verification on all critical systems for the remainder of the outag The inspectors have reviewed the licensee's actions including a walk
- through the verify all specified chain operated valves were locked and have no further questions on this item at this tim d. Inadvertant Engineered Safeguards (ES) Actuation
'
On November 29, 1981, at approximately 0715 a spurious ES actuation occurred. The plant was in flode V operations (cold shutdown) with "A"
,
decay heat train in servic "A" vital power bus was being returned to service subsequent to maintenance when a spurious trip was received on-
"A." ES system resulting in the actuation of "A" ES trai Due to plant
.
r m -
., .
conditions at the time of the actuation (equipment secured and/or tagged out for outage work) "A" Emergency Diesel Generator was the only ES equipment actuated. The ES train was reset immediately by the operator The problem was attributed to a voltage surge caused when reenergizing "A" vital bus, flaintenance on "A" vital bus was completed and returned to service with no additional ES problems occurring. The inspectors reviewed this event and have no further question i
[
}
i
!
/