ML20198P225

From kanterella
Jump to navigation Jump to search
Insp Rept 50-302/97-21 on 971203.Violations Noted.Major Areas Inspected:Noncompliances in Design control,10CFR50.59, Procedural Adequacy,Reportability & Corrective Actions.No Notice of Violation Being Issued in This Case
ML20198P225
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 12/29/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20198P142 List:
References
50-302-97-21, NUDOCS 9801220038
Download: ML20198P225 (6)


See also: IR 05000302/1997021

Text

,

- -

.

,

U.S.' NUCLEAR REGULATORY COMMISSION

REGION II

i

'

- Docket No.

50 302

License No.

DPR 72-

Report No -

50 302/97 21-

,

Licensee::

Florida Power Corporation

Facility:

Crystal . River 3 Nuclear Station

Location:

15760 West Power Line Street

Crystal River, F1 34428 6708

. Date:

December 3, 1997

,

. Inspectors:.

S. Cahill, Senior Resident Inspector

T. Cooper, Resident Inspector

R. Schin, Reactor Inspector

S. Ninh, Project Engineer

Approved-

K. Landis, Chief, Projects Branch 3

'

Division of Reactor Projects

.

A

^

'

_g12

7g29

O

PDR

-

,

.

-4

-

.,

.

EXECUTIVE SUMMARY

Crystal River 3 Nuclear Station

NRC Inspection Report 50 302/97 21

This special inspection report included a review of Licensee Event Reports

(LERs) submitted by Florida Power Cc7 oration (FPC) from 1995 through 1997.

These LERs documented engineering design deficiencies at Crystal River 3

Nuclear Station.

Based on results of our review, the inspectors determined that violations of

NRC requirements occurred. These violations involve a number of examples of

noncompliances in design control,10 CFR 50.59, procedural adecuacy/ adherence,

reportability, and corrective actions. These examples includec unanalyzed

conditions and conditions that were outside the design basis of Crystal River

Unit 3.

Some of the deficiencies have existed since plant licensing. A list

of the conditions identified and the corresponding LERs is attached. The

majority of these conditions were identified by your staff during a

comprehensive review of the Crystal River engineering program and a

reassessment of the plant design margins.

The inspectors determined that the information regarding the reasons for the

violations, the corrective actions taken and planned to correct the violations

and prevent recurrence are adequately addressed on the docket in the LERs you

have'provided to the NRC. Although no additional information regarding

corrective actions is required at this time, the NRC will continue to examine

the implementation of your corrective actions during future inspections.

As discussed in detail in the cover letter, the NRC has concluded that while

violations did occur associated with the events documented in the LERs,

enforcement discretion in accordance with Section VII.B.2 of the " General

Statement of Policy and Procedures for NRC E:1forcement Actions" (Enforcement

Policy), NUREG 1600, is warranted. Therefore no Notice of Violation is being

issued in this case.

The exercise of enforcement discretion in this case is identified as non cited

violation (NCV) 50 302/97 21 01, Examples of Noncompliances in Design Control,

10 CFR 50.59 Evaluations, Procedural Adequacy / Adherence, Reportability, and

Corrective Actions. This NCV will be used to track the exercise of

enforcement discretion and will be used as a reference upon satisfactory

completion of your corrective actions for the individual LERs.

Attachment: List of Licensee Event Reports (LERs)

Included in NCV 50 302/97-21 01

.

__

_

_

.

. ..

LIST OF LICENSEE EVENT REPORTS (LERs)

INCLUDED IN NCV 50 302/97 21 01

LER NUMBER

Title

EVENT DATE

REPORT DATE.

95 001

INSPECTION DETERMINES CONTROL COMPLEX HABITABILITY ENVELOPE

01/24/95

IN LEAKAGE AREA EXCEEDS REQUIREMENTS RESULTING IN CONDITION

03/07/95

POTENTIALLY OUTSIDE DESIGN BASIS.

95 004

PERSONNEL ERROR CAUSES CONTROL COMPLEX HABITABILITY ENVELOPE

03/21/95

BREACH RESULTING IN OPERATION OUTSIDE DESIGN BASIS.

04/12/95

95 019

SERVICE WATER SYSTEM REVIEW DISCOVERS LEAK INSTRUMENTATION

09/29/95

UNABLE TO PERFORM ITS FUNCTION RESULTING IN OPERATION OUTSIDE

10/26/95

THE DESIGN BASIS OF THE PLANT.

95 021

INADEQUATE PIPE SUPPORTS ALLOW STRESS ON MOTOR COOLER N0ZZLE

10/04/95

RESULTING IN OPERATION OUTSIDE THE DESIGN BASIS.

11/03/95

95 026

UNQUALIFIED FLOW INSTRUMENT USED IN DETERMINING HPI PUMP

11/07/95

RUNOUT CONDITIONS CAUSED BY FAIL!.'RE TO RECOGNIZE

12/07/95

APPLICABILITY OF REG GUIDE 1.97

95 028

OPERATION OUTSIDE DESIGN BASIS CAUSED BY PERSONNEL ERRORS AND

12/13/95

INADEQUATE DOCUMENTATION OF B0 RATED WATER STORAGE TANK VACUUM

01/12/96

BREAKER CAPACITY.

96 004

POTENTIAL LEAKAGE INTO CONTROL COMPLEX HABITABILITY ENVELOPE

01/12/96

AB0VE DESIGN LIMITS DUE TO WORN AND HISSING DAMPER.

02/08/96

96 008

AMBIGU0US NOTE CAUSES MISINTERPRETATION AND FAILURE TO

03/04/96

PERFORM REQUIRED SURVEILLANCE PRIOR TO MODE ASCENSION.

04/02/96

~

96 015

PERSONNEL ERRORS CAUSE CABLE SEPARATICN/ ISOLATION CONCERNS

04/08/96

RESULTING IN OPERATION OUTSIDE THE DESIGN BASIS. (Toxic Gas-

05/20/96

Monitors)

96 019

CLASSIFICATION OF TRANSFER SWITCH CAUSES POTENTIAL FOR LOSS

06/13/96

0F POWER TO ES STATUS LIGHTS.

07/15/96

96 021

DELAYED ENTRY INTO TECHNICAL SPECIFICATION ACTION FOR IN0P

09/28/96

RPS CHANNEL

L

10/28/96-

96 022

DESIGN ERROR REGARDING HOT SHORTS RESULTS IN OPERATION

11/22/96

0UTSIDE 10 CFR 50 APPENDIX R DESIGN BASIS.

12/20/96

Attachment

1

-

. . - .

--

- -

.

---

.

- _.

.

..

-

-

-

!

.,

.

LIST OF LICENSEE EVENT REPORTS (LERs)

Page 2

INCLUDED IN NCV 50 302/97 21 01

LER NUMBER'

Title-

EVENT DATE'

REPORT DATE-

97 004-

THERMAL RELIEF VALVES INSIDE THE CONTAINMENT DO NOT MEET THE

02/07/97

REQUIREMENTS FOR DESIGN BASIS ACCIDENTS

03/10/97

97 006

SURVEILLANCE TESTING RESULTS IN REDUCTION OF EMERGENCY DIESEL

02/19/97

GENERATOR RATING LIMIT DUE TO INADEQUATE ACCEPTANCE CRITERIA.

03/20/97

97 008

DISCOVERY OF ORIGINAL DESIGN CONFIGURATION RESULTING IN

03/07/97

UNANALYZED CONDITION REGARDING HIGH PRESSURE INJECTION PUMP

04/07/97

RECIRCULATION LEADING TO POSSIBLE PUMP FAILURE AND DOSE

CONSEQUENCES.

97 011

POTENTIAL DESIGN BASIS CONDITION FROM PRESSURE LOCKING 0F

05/29/97

EMERGENCY FEEDWATER ISOLATION VALVES CAUSED BY INSUFFICIENT

06/27/97

OVERSIGHT / REVIEW 0F CALCULATIONS.

97 012

PORTIONS OF INDUSTRIAL COOLING SYSTEM NOT DESIGNED TO

05/31/97

APPLICABLE CODE RESULTING IN OPERATION OUTSIDE THE DESIGN

,

06/26/97

BASIS.

97 013

EMERGENCY DIESEL GENERATOR ROOM COULD EXCEED MAXIMUM DESIGN

05/30/97

TEMPERATURE DURING OPERATION DUE TO INADEQUATE R00H COOLING.

06/26/97

'

97 014

DUE TO ENGINEERING DESIGN ERRORS. REACTOR BUILDING

06/11/97

PENETRATIONS DO NOT MEET APPLICABLE CODES RESULTING IN A

07/11/97

CONDITION OUTSIDE THE DESIGN BASIS.

97 015

NON CONSERVATIVE DIFFERENTIAL PRESSURE RATING FOR LETDOWN

06/12/97

LINE INBOARD CONTAINMENT ISOLATION VALVE PROHIBITING SAFETY

07/11/97

FUNCTION PERFORMANCE.

97 016

DUE TO ENGINEERING ERROR. OMISSIONS IN REACTOR BUILDING

06/13/97

C0ATING CALCULATIONS RESULT IN CR 3 BEING IN AN UNANALYZED

07/11/97

CONDITION.

97 017

PERSONNEL ERROR CAUSED INADEQUATE ELECTRICAL SEPARATION OF

06/21/97

THE HIGH PRESSURE FLOW INDICATORS.

07/21/97

97 018

A HIGH ENERGY LINE BREAK IN THE INTERMEDIATE BUILDING'(IB)

07/02/97

COULD RESULT IN LOSS OF CHILLED WATER TO THE CONTROL COMPLEX

07/26/97

VENTILATION SYSTEM DUE TO DESIGN ERROR.

97 019-

ELEVATED EDG SUPPLY AIR TEMPERATURES DUE TO EDG RADIATOR

07/03/97

DISCHARGE AIR RECIRCULATION EFFECT.

08/01/97

.

y

-

,-

-

-

_

._

_

. _ _ _

.

.g

LIST OF LICENSEE EVENT REPORTS (LERs)

Page 3

INCLUDED IN NCV 50 302/97 21 01

LER NUMBER:

Title

EVENT DATE-

REPORT.DATE:

97 020

MISINTERPRETATION LEADS TO NONCOMPLIANCE WITH TECHNICAL

07/18/97

SPECIFICATION CRITERIA INVOLVING PAST IN PLACE FILTER

08/18/97

TESTING.

97 021

LOSS OF "A" BATTERY LEADS TO THE INABILITY TO BYPASS ES

07/21/97

ACTUATION SIGNALS AS A RESULT OF INADEQUATE SYSTEM KNOWLEDGE.

08/20/97

97 022

CALCULATION ERRORS ASSOCIATED WITH CONTROL COMPLEX

07/21/97

HABITABILITY ENVELOPE UNFILTERED AIR INLEAKAGE COULD ALLOW

08/18/97

OPERATOR DOSE LIMITS TO BE EXCEEDED.

97 023

DESIGN ENGINEERING PROCESS ALLOWS INSTALLATION OF VITAL BUS

07/30/97

INVERTERS CONTAINING AN UNANALYZED TRIP CIRCUIT.

08/25/97

97 024

FEEDWATER VALVES DO NOT MEET THE REQUIREMENTS FOR MAIN STEAM

07/31/97

LINE OR FEEDWATER LINE BREAK EVENT HITIGATION DUE TO

08/27/97

INADEQUATE DESIGN AND CALCULATION ERRORS.

97 026

FAILURE TO PERFORM A FIELD VALIDATION RESULTED IN A DEVIATION

08/14/97

TO 10 CFR 50 APPENDIX R REQUIREMENTS.

09/13/97

97 027

FAILURE TO ADD ANTIFREEZE TO THE DIESEL GENERATOR COOLANT

07/07/97

RADIATORS MAY RENDER EMERGENCY DIESEL GENERATOR INOPERABLE

10/03/97

DURING SUB FREEZING TEMPERATURES.

97 028

FLOW ELEMENT ACCURACY UNCERTAINTY MAY BE GREATER THAN ASSUMED

09/02/97

DUE TO A DESIGN ERROR.

10/02/97

97 029

FAILURE TO PERFORM A FIELD VALIDATION RESULTED IN A DEVIATION

09/17/.7

0F 10 CFR 50 APPENDIX R REQUIREMENTS.

10/14/97

97 030

INSTALLATION ERROR RESULTS IN A CONTAINMENT ISOLATION CHECK

09/23/97

VALVE DISC STICKING IN THE OPEN POSITION.

10/21/97

97 032

INADEQUATE ELECTRICAL ISOLATION ON A SAFETY RELATED POWER

04/06/97

SUPPLY DUE TO A DESIGN ERROR

11/05/97

97 033

LOSS OF CONTROL COMPLEX VENTILATION SYSTEM DUE TO ELECTRO

08/07/97

THERM 0 LINK AND FUSIBLE LINK FIRE DAMPER AUTOMATIC CLOSURE

11/10/97

.

._.

. . ..

._ _ .

.-. _ .

_ _ ____ __ . .. _ ._. . _ _

.

1

.

.

,

l

. LIST OF LICENSEE EVENT REPORTS (LERs)'

Page 4.

INCLUDED IN NCV 50 302/97 21 01.

LER'NUSER:

Title;

<

EVENT DATEi

-

m

REPORT DATEv

R:

-

97 034

NONCONSERVATIVE ASSUMPTION IN BREAKER SETPOINT CALCULATIONS

10/08/97-

COULD PREVENT STARTING 0F MOTOR OPERATED EQUIPMENT

11/06/97-

1

97 035-

A DESIGN ERROR RESULTED IN THE INABILITY TO PROVIDE REACTOR-

10/16/97

COOLANT SYSTEM INVENTORY MAKEUP DURING A POSTULATED APPENDIX

11/13/97

R EVENT

97 036-

THERMAL OVERLOAD RELAYS IN MANUAL RESET POSITION RESULTED IN

10/24/97

OPERATION OUTSIDE DESIGN BASIS.

11/21/97

97 037

CONTAINMENT INTEGRITY CANNOT BE PROVEN FOLLOWING CALIBRATION

10/24/97

0F BUILDING SPRAY PRESSURE SWITCHES AND TRANSMITTERS

11/21/97

97 038

AN ENGINEERING OVERSIGHT RESULTED IN OPERATION OUTSIDE DESIGN

03/17/97

BASIS FOR THE WASTE GAS DISPOSAL SYSTEM.

11/22/97

97 039

UNQUALIFIED MATERIAL LEFT IN REACTOR BUILDING DURING-

06/02/97

CONSTRUCTION COULD AFFECT POST LOCA C00LDOWN CAPABILITY.

12/03/97.

97 040

INADEQUATE ENGINEERING DOCUMENTATION FOR SAFETY RELATED LARGE

01/08/97

BORE PIPING ANALYSIS AND PIPE SUPPORTS.

12/04/97

97 041

CONTROL COMPLEX CHILLER MAY BE RENDERED UNAVAILABLE DUE TO

11/10/97

DESIGN ERROR.

L

12/10/97

.

fi

>*F'>

  • 97'*

v

-

= - -

v-

--l-

.,

?

w

w-

N

e

-

mw---

- - - -"