ML20245K296
| ML20245K296 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 08/10/1989 |
| From: | Casto C, Conlon T, Ruff A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML20245K282 | List: |
| References | |
| 50-302-89-17, NUDOCS 8908180390 | |
| Download: ML20245K296 (16) | |
See also: IR 05000302/1989017
Text
F.
I
l:
~
.
Moo
UNITED STATES
/g~ ~ '
.
'
NUCLEAR CECULAT!RY COMMIS$10N
~
.
,[
C E' lON ll
l
,
. gr
j
101 MARIETTA STREET,N.W.
t
,
u
.S
-
ATLANTA, GEORGI A 30323
.
j
Report No.:
50-302/89-17
' Licensee:
Florida Power' Corporation
J
3201 34th Street, South
St., Petersburg, FL 33733
Docket No.:
50-302
License No.:
Facility Name:
Crystal River 3
Inspection Conducted:
une'19-20, 1989
Inspectors:
lu -
d
h/8'O
.m
C. C1rrto'
Date Signed
j
"
Y
$ /0 < P19
A. Ruff
/
Date Signed'-
"'
Approved by:
b
f-/# -N
T. Conlon
C/
g/
Date Signed
l
SUMMARY
Scope:
l
This routine announced inspection was conducted as a follow-up to the events-
surrounding the loss of off-site power transient experienced on June 16, 1989.
i
The scope of this inspection included review of the plant and operator response-
!
to the transient, the root cause, and corrective actions taken by_the licensee
to prevent future occurences of this nature.
i
Results:
Increased management attention to control the interface between the Units 1
and 2, switchyard and the Unit 3 Start-up transformer is' needed.
The current
plant design relies solely on the Unit 3 Start-up transformer as the primary
i
source of power to the Emergency System and Unit buses. An additional source .
of off-site power would enhance the response to a single failure of the Unit 3
'
transformer. Additionally, during the event of June 16, 1989, the Emergency
Feedwater Pump-1 failed to automatically start after the Emergency Diesel
Generator powered the Emergency Buses.
This failure may have been prevented
had proper testing of the logic string for this sequence been tested. The
inadequate testing was not identified during the root cause analysis completed
by the licensee.
8908180390 890811
FDR
ADOCK 05000302
Q
FDC
_ - _ _ _ - _ - - _ - - - - - _ .
-
_ _ _ _ _ _ _ _ _ _ - _ _ _ _
__
-
.-
i
.'
. , -
.
-
'
.
1
l '
i
'
REPORT DETAILS
i
1.
Persons Contracted
Licensee employees
D.' Beach, Supervisor, Technical Engineering Services
M. Fitzgerald,- Supervisor, Electrical Engineering
- R. Fuller, Senior Nuclear Licensing Engineer
E. Gallion, Shift Supervisor
- S. Johnson,. Manager, Site Nuclear Services
B. Marckese, Electrical Engineer
- P. Mckee, Director, Nuclear Plant Operations
L. Moffatt, Supervisor, Nuclear Safety
R. Murgatroyd, Superintendent, Maintenance
B. Muzzi, Senior I&C: Engineer
V. Roppel, Manager, Nuclear Plant Maintenance
- W. Rossfeld, Manager, Nuclear Compliance
H.-Tillman, System Protection and Control Technician (CR-1 and 2)
E. Welch, Manager Nuclear Electrical /I&C Engineering Services
- R. Widell, Director, Nuclear Operations Site Support
- M. Williams, Nuclear Regulatory Specialist
A list of acronyms and initialisms used herein is provided at the end of
this report. Figures I and 2 outline the Crystal River off-site power
supplies.
2.
Overview and Background Information
An alert was called by the licensee on June 16, 1989, when a LOSP occurred
during the ascension of power for Crystal River Unit 3.
CR-3's ES buses
were being sepplied with power from CR-3 Start-up transformer.
The LOSP
was the result of a personnel error and a failure of a Fault Detector
Relay.
The FSAR states that the preferred off-site power source for CR-3's ES
buses is the Unit 3' Start up transformer and the alternate and independent
source is the Units 1 and 2 (Fossil Units) Start-up transformer via a
direct cable connection.
Transfer to the alternate source is by manual
operations. The on site Emergency Diesel Generators assume the ES bus
loads in the following manner:
a.
Manually if the ES bus voltage has not failed.
b.
Automatically if the ES bus voltage fails to approximately 55 percent
of nominal ES bus voltage or degrades to approximately 90 percent of
nominal ES bus voltage. The former involves a relay scheme were two
out of three relays are activated and the later involves a relay scheme
were three relays out of 3 relays are activated.
The NRC's 1974, SER states the CR-3 off-site power is from two separate
feeders emanating from' different breaker-and-a-half configuration bays
in the 230KW switchyard.
These power source are connected to two separate
.
_ _ _ . _ _ . _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ . . _ . _ _ _ _ - _ _ _ _ - _ _ _ - _ . _ _ - _ _ - _
_ _ _ _ _ _ - _ _ _ _
_-
.'
'
,
'
.
2
Start-up transformers of which one is assigned to CR-3 and the other is
shared between CR-1, 2, and 3.
The shared Start-up transformer, feeder
lines, and associated breakers have sufficient capacity to handle all
required load demands from the 'three units. .The TS for CR-3 states that-
these' two physically independent circuits between the off-site transmis-
sion network and'the.on-site ES bus are to be available for CR-3, when in-
operating Modes 1, 2, 3, and 4 (as defined in the TS). The TS also gives
requirements that must be fulfilled when the conditions are not met.
The licensee issued a Licensee Event Report dated May 9,1989, that'
described an event on April 9,1989, -where it was. determined ' that the
alternate power source could not supply power to CR-1, 2, and 3 for all
operating configurations. _ The event happened when CR-3 was .in a safe shut
down condition with minimal decay heat and with all three. units being
supplied power from the alternate power source. A 3500 HP pump was started
in Unit I and a voltage drop occurred on the ES buses (degraded voltage
l
on ES buses). The Emergency Diesels Generators started on degraded voltage-
signals. None of the safeguards' equipment was lost in this event. As a
result of this event administrative controls were implemented to assure
that the loads on CR-3's alternate off-site power source were regulated
to satisfy the TS requirements for Crystal River 3 when it was in modes 1,
2, 3, or 4.
In addition, a plant modification was made to annunciate any
overloading conditions of this alternate power source. The annunciation
is made in CR-3's control room so that operators can take the appropriate
TS actions,
i
3.
Response to the Event
'
a.
Description of the Sequence of Events, June 16, 1989
0255
Could not receive control rod 100% Out Limit or Group Out
Limit for Control Rod 5-3, complied with the actions of
,
0315
Inserted all Regulating Rods back into the core and ensured
i
a 1 percent Shutdown margin. Entered Mode II and initiated
maintenance on Axial Position Indication for Rod 5-3.
,
Exited the actions of TS 3.1.3.3.
!
0800
Completed surveillance testing for Control' Rod 5-3.
0915
Unit 2 Start-up in progress, loading of the Units 1 and 2
Start-up Transformer exceeds 1500 KW; therefore, that
i
source of offsite power is inoperable enter TS 3.8.1.1
l
(72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> LCO).
0945
Units 1 and 2 Start-up Transformer loading is reduced to
I
<1500 KW, exit actions of TS 3.8.1.1.
1110
Enter Mode II
1203
Enter Mode I
,
,
,
_.
_ _ _ _ - _ - _ . - _
_ _ _ _ -
-
. _ _ _
_
__
l-
,-
.
.
.
3
)
d
l
1325
Breaker 1691 opens due.to an inadvertent test of the fault
)
protection on the Brookridge'230 KV line. A fault detector
j
relay sensed a failure of breaker 1691 to'open (the breaker
'
l
- did operate successfully), causing. breaker 1692 to open.
This action de-energized the Unit 3 Start-up Transformer
i
causing a ' loss of power to all . AC. buses. . A reactor trip
occurred and the EFW pumps started to supp.ly feed to the
Steam' Generators.
EFP-1 : tripped on ES bus undervoltage,
the Emergency-Diesel Generators started and supplied power
to the ES busses. EFP-1 did not sequence back on the bus;
j
however, thel operators wert able to manually start the
1
A
pump. An unexplained RPS trip was received on one channel-
for the flux / delta flux / flow trip and the vital inverters
did not indicate an alternate source was available.
1330
When the emergency classification of the " Alert" was
declared, the proper notifications were_ made and the TSC
was manned. The conduct of business in the TSC was profes-
1
sional and timely.
l
1
1431
Breaker 1692 reclosed; Unit 3 Start-up Transformer
re-energized.
1432
Breaker 1691 reclosed.
1445
"A" ES Bus paralleled to the Units 1 and 2 Start-up Trans-
former.
1447
"B" ES Bus paralleled to the Unit 3 Start-up Transformer.
1449
4160V Unit Buses are energized providing power to the
secondary plant.
1500
All 4160V Buses have been- restored, crews are restoring
equipment and instrumentation as required. The Emergency
j
Diesel Generators-are still running, an RCP would be' started
when all attendant instrumentation had been restored. The'
H
cause of the loss of power-is _known to be a loss of the
Brookridge line and subsequent failure of a fault sensing
4
relay.
j
1620
Unit 2 tripped causing a loss of Units 1 and 2 Start-up
'!
Transformer,
"A" ES loads are transferred to the Unit 3-
Start-up Transformer,
j
1709
"B" RCP is started returning the RCS to forced circulation.
l
All RCS parameters indicate satisfactory after the pump
j
start..
!
!
1712
"C" RCP is started.
l
1715
Based on the successful start of two RCPs the event is-
,
downgraded from an Alert to a NOVE.
l
a
.I
.______--___A
_ _ ___
-
-
,
N
.'
!
-
.'
l
4
i
l
1728
Verification Procedure VP-580 has been completed, all
parameters indicate normal.
Intent is to de-classify
,
emergency.
1
'
1732
Breaker 1691 has been closed back in restoring normal
breaker alignment to the Start-up Transformer.
l
l
1735
Based upon successful completion of VP-580, NRC conference
,
call and determination of the root-cause, the NOUE has
I
been terminated.
b.
Operator / Plant' Response
!
The reactor was at 12 percent power with the main turbine latched end
l
rolling at 400 rpm. The reactor tripped and an automatic initiation
'
of EFW and Emergency Diesel Generators occurred. The loss of all
RCPs placed the RCS in natural circulation. The operators responded
by performing the immediate operator actions of the Emergency
Operating Procedures (AP-580, 530, 450 and 770). Natural circulation
1
was verified on "A" OTSG; However, due to an instrument malfunction,
natural circulation could not be immediately verified on the
"B"
0TSG.
Letdown was terminated due to the filter isolation valves
,
closing (letdown would be re-established later in the transient).
'
Due to the cool down from EFP-2, OTSG steam pressure dropped to ~450
i
psi at 1400 hrs. Manual Pressurizer and Makeup Tank level control
were established. The plant was stabilized at ~1950 psi at a cool
down rate of ~30 degrees F/hr.
The plant was returning to service
j
i
l
from an outage; therefore, the decay heat load was minimal.
The
l
operators attempted to minimize the steam flow and subsequent cool
down by isolating non-essential equipment, e.g. , closing the Main
Steam Isolation Valves. During the event Hot Leg temperatures ranged
from 537 degrees F. at 1400 hrs. to 440 degrees F. at 1555 hrs,
Cold Leg temperatures ranged from 461 degrees F. at 1400 to 419
degrees F. at 1555 hrs.
The loss of the Unit 3 Start-up transformer was attributed to a relay
technician who had inadvertently depressed a fault test pushbutton
which cleared the Brookridge line, additionally, a fault sensing
relay failed to sense the opening of breaker 1691 causing the relay
to initiate the opening of breaker 1692.
Crews were dispatched to
determine the cause of the Unit 3 Start-up Transformer failure.
Also, the centrol room operators dispatched personnel to survey the
Diesel Generators and restore power when available.
The licensee
elected to stabilize the grid by waiting on Unit 2 to complete a
Start-up before restoring off-site power through the Units 1 and 2
Start-up transformer. After this source of power was restored, the
operators placed one division of ES on the Unit 3 transformer and one
division of ES on the Units 1 and 2 transformer.
Eventually, all
loads were transferred to the Unit 3 transformer, two RCPs were
started establishing forced circulation and the event terminated.
L_
.
.
.
5
Operator response to this event was satisfactory. The operators were
,
aware of electrical sources which had failed, and those available to
'
them.
The control room personnel dispatched personnel as necessary
to take local actions as appropriate.
Procedure actions appeared
adequate in providing guidance to the operators in responding to this
l
event,
c.
Two weaknesses were noted during the recovery from this event:
(1) The root cause analysis of the start failure of the motor driven-
emergency feed pump was less than adequate. It was later, after
restart, shown by test that the failure of' an untested relay -
string prevented the automatic start of EFP-1.
The assumption
was that the malfunction of a time delay was the cause of the
start failure.
(2) Lack of string testing of the start logics contributed to the
failure to recognize the failure of the AJ relay in addition to
the time delay relay. Also the lack of string testing of this
logic string contributed to the existence of a relay that was
not surveilled in the automatic start logic of a safety related
component.
4.
Specific Problems Discovered as result of LOSP on June 16, 1989,
a.
Loss of Start-up Transformer for CR-3
The non-nuclear switch yard personnel were checking the carrier
signals of the Brookridge transmission system from metering cabinets
in CR-1 and 2 (fossil units) control room areas.
This would
normally have no effect on the transformer configuration and switch
yard breaker line up that was supplying power to _ CR-3 Start-up
transformer. However, a relay technician inadvertently hit a test
circuit switch (a Push Button [PB) that is not normally used) that
simulates a fault on the system's transmission lines and two
switch yard breakers opened (1690,1691).
One of these breakers
(1691) is in parallel with another breaker (1692) that supplies
power to CR-3 Start-up Transformer.
The opening of (1690, 1691) two breakers would- not have caused the
loss of CR-3 Start-up transformer since breaker 1692 should have
remained closed. However, a fault detector relay, which should have
indicated that breaker 1691 was open, failed and indicated that
breaker 1691 was still closed. As a result the next breaker, 1692,
automatically opened to clear the non-existent fault. This isolated
CR-3 Start-up transformer and CR-3 had a LOSP event. The Emergency
Diesel Generators started and assumed the ES loads.
The relay that failed in the above event was last calibrated in 1986,
and was found to be satisfactory. The periodicity of calibration for
this relay is on a normal two year cycle. It was not calibrated when
its two year period became due because of more urgent work.
The relay
was removed after the event, checked out and re-cailibrated success-
fully and returned to service.
_
7
-
. - - _ - _ _ _ _ - _ _ _ _ _ _ - _ _ _ _______ -
m
.
. , .
,
,
'
.
6
These switchyard relays are scheduled for replacement by a solid
state system that is more reliable.
The replacement is anticipated
to occur during .the next CR-3 refueling.
Since the PB circuit is
only accessible by a hinged cover.that is fastened by screws opposite
,
the hinced end (The cover also has to be removed to check the carrier
)"
signals), it is considered by the' licensee'that rio additional protec-
tion is needed for the PB.
In the : interim, before .the solid . state
system is installed, the r'elay department is considering the permanent-
.
disabling of the PB. switch since they are not used. This event was
caused by personnel error and a faulty relay.
I
b.
Emergency Feedwater Pump (EFP) One Failed to Start Automatically
!
1
The event caused the. motor driven Emergency Feedwater Pump EFP-1 to
l
1
receive an automatic start signal; it tripped :off of . the line
shortly after initiating and failed to restart automatically when
the Emergency Diesel Generator (3A) assumed the ES loads.
i
After the Diesel Generator's ' output . breaker closes, one circuit is
activated that energizes a relay that has a contact in a string for
the automatic starting circuit - for EFP-1.
The contact in this
starting string should have closed in five seconds after the DG's
output breaker closed and EFP-1 should have started automatically..
l
The operator noted this discrepancy and manually started the pump by
j
positioning the switch in the control room.
The action taken after the event showed the following:
,
1
(1) The relay with a five second time delay for. closing a contact was
i
checked. This check showed that the contact did not-close. The
l
relay was taken to the shop for further bench testing. In the
shop it worked as designed.
It was tested and cycled several
i
times in the shop and was placed back in the' circuit. It was
~
tested in the installed configuration and worked as designed.
It was cycled several times in its installed configuration and
worked each time. - It was considered that a poor electrical
connection may have cause the relay to fail during the LOSP
l
event.
(2) The relay had been satisfactorily tested on October 19, 1988.
The test at that time was in accordance with Crystal River's
l
SP 137, Engineered Safeguards Actuation System Time Delay Relay
Calibration.
The installed tests, mentioned in 1. above, were
the same, or similar, to this test.
.
(3) As a result of NRC inquiries concerning the testing of the
'
er. tire string for an automatic starting circuit for EFP-1, NRC
was notified on June 23, 1989, that the AJ relay, which also
provides a close contact in the EFP-l's string for automatic
starting, has not been tested. The AJ relay was subsequently
l.
tested and found to be defective.
Therefore, even if the five
_
_ _ _ - _ - _ - - - - - - - - - - - - _ . . . , - - - - . _ -
1
'
-
.
,
%
7
t
second-time-delay relay had worked properly, the EFP-1 would
not have started because of an open contact up stream of the
s
time-delay
relay.
This
is
considered to
be a violation
I
identified as
50-302/89-17-01,
Inadequate Testing to Prove
Operability of a String for the Automatic Starting of EFP-1.
I
c.
Synchronizing Lights for Inverters A, B, and C were noted to be off
j
after the LOSP Event
j
On Wednesday (June 14, 1989), prior to the event, the licensee was
)
performing the SP-417 and transfer switch VB-XS-1A transferred to
1
alternate supply which was- not energized.
VA-XS-1A remained in the
!
correct position.
The transfer switch changes positions when it
!
senses an under voltage or over current condition.
Extensive checks
1
were performed to determine why this anomaly occurred and no circuit
j
discrepancies or erroneous set points could be found. As a result of
I
the LOSP event 'on Friday (June 16, 1989), and the anomaly indicated
above, the inverter panels were checked shortly after the LOSP event.
,
The transfer switches functioned as designed, however, it was
i
observed that the synchronizing lights for inverters A, B, and C were
!
not on.
The D inverter was on. The lights should indicate that
power is available on the vital bus.
In that the vital bus was
energized by the DG assuming the ES bus loads, the lights should
,
have been on.
1
It was observed that the lights did come on when the DG speed was
increased during the paralleling and synchronizing operations to put
the ES bus back on switch yard power.
The inverter lights are set
for a frequency of 59.3 to 60.7 cycles per second.
They were
re-adjusted to as close to the mid-band setting as possible. SP 417
in this area was repeated and the inverter circuitry functioned as
designed. The DG high speed limit was set at the high end of the
specification (900 RPM) and a MAR is being considered to increase this
high speed limit to 905 RPM.
5.
Acronyms and Initilism
CR
Crystal River
-
Diesel Generator
-
Emergency Feedwater
-
Emergency Feedwater Pump
-
Engineered Safeguard
-
Horsepower
-
KV
Kilo-Volt
-
KW
Kilowatt
-
LCO
Limiting Condition for Operation
-
LOSP -
Loss of Off-Site Power
Modification Approval Record
-
,
NOUE -
Notification of Unusual Event
OTSG -
Once Through Steam Generator
i
PB
Push Button
-
l
Reactor Coolant Pump
-
____-____________ _
,
.
.
8
Reactor. Coolant System
-
Revolutions per minute
-
Safety Evaluation Report
-
Surveillance Procedure
-
TS
Technical Specifications
-
-
<
!
I
a
i
l
.
-
'
"
,
I
a3 e
te
e
e
e
i
1
]
g
[t
g
'
.
,
e
,
s
s
u
1
1
]
g
[t
g
S
i
T
.
ge
U
R S
o
A
e
.
B
C E
s
e
u
t
i
D
]
-
R
[1
g
e
1
A
R
-
E
1
E
Y
~
R
s
U
D
4
1
G
H
L
9
I s
e
I
F
O
8
N
e
C
H
1
e
1
T
g
g
g
I
N
W
e
.
S
T
ge
.
N A
e
E L
i
C F
a
e
a
e
V
a
e
K
.
g
g
0
4 ~
g
3
T -
-
2
I U
e-
N /
4
U S
aa
-
a
_
.
_
.
g
-
_
.
.
.
_
_
.
_
_
_
_
.
_
_
.
,.
'
.
4
,
_
_
o
.
s
_
.
T
_
_
I
NU
.
.
.
.
.
0
-
.
-
.
.
.
.
~h'
5
l'_QF!!!
o
I
- -
i
~
-
.:
~
-
2
-
o- a g
! g,
I
"
.
4, " "
7= . a
p
'
~
gg ~=Ii
I
s
1
3-
>
x
>
.
,.
.
-
$
I ~8
.
o#
-
L.
1
1Y
y g.
g,
., s
_
-
-
-
-
'il +n
- I
<> *
!
llg g%-
]{g
g
2- *
l
- l-
%g-
~
g
a ,,
a
g
gl
7 1
y
g:
s
h
ga
-
-
1
_
$
T.
-
ll
-
m
2
i
-
_,
-
i
,=, e
,
-
2 *g
-t
'g
!
I I
Ill
$! I
.>
i
A=l
-l.
3E
g
- 1
-
g
_
a
!
. I :gfd,,,
p =i l
-
-
_/
2
-
,
- ,
7 1
!
-
-~
=
7 i SE [h.
b
ahl
g
j, g
s]
@
!
SE i*
- =
-
-
-
n
,
.
t
6
_ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ - _ - - - - - _ - - - - - - - - - - - - - - -
--
.,
ROI 2210 REY. 1, ENCLOSURE 4
.
.
,
'
~
INSPECTION RESULTS AND SALP INPUT
Sumary of Inspection Results
Facility
C,.oc A /
/fhe-
Report No.
W-
/7
r-
-
,
AREAS INSPECTED
L oc s 0
ELs J /t
fM M
' 4/n/p r
m
/
.
.
NEW VIOLATIONS (SL), DEVIATIONS (DEV), OR OTHER NEW ITEMS (UNR & IFI)
L
s L 'l
r?. L a +n n ~
u adrer
4
k vk m
rC ' rp o
na
a e c,. m.s
e A .
A u ,* '
< eo
e. o. v "
)
STATUS OF PREVIOUS ENFORCEMENT MATTERS AND OTHER ITEMS
//h
MODULES INSPECTED, PERCENT FOR EACH UNIT (IF NOT 1001, LIST NUMBER OF LINE
ITEMSCOMPLETED)
.i
g % ~)O 3
/Oc Po
I
INSPECTOR OBSERVATIONS AND AREAS OF CONCERN
11n nAA A
ci, Aw;14 ~ -
(DL
(L su L.L4
m
t-ck A & =- A s s m
+ 1?v Lu
u.,
'
4 [ d J l-43r" & d l w i f % $ /s
U
/
[
5/3/88
,
o
V
y
2
ROI 2210 Rev. 1. Enclosure 4
, , -
,
,
,
, ' '
'.
, . .
,
SALP EVALUATION
Complete one SALP evaluation for each functional area inspected.
Complete.
I
during inspection if time permits.
'
Key: 0 - Not ins;Neted; 1 - Above average; 2 - Average; 3 - Below average
..
. EVALUATION CRITERIA
ASSESSMENT
1.
Management involvement in assuring quality
0 1@3
2.
Resolution of technical issues from a safety standpoint
0 1 @3
,
3.
Responsiveness to NRC initiatives
j 1 2 3
4.
Enforcement history
$1 2 3
5.
Reporting and analysis of reportable events
@1 2 3
j
6.
Staffing (including management)
@1 2 3
7.
Training and qualification effectiveness
@1 2 3
AREA INSPECTED
OVERALL ASSESSMENT
0 1 2 3
CO M NTS:
Lohn kk
k.-s)- b2
,. LM drCO p m,
~.L
strJ
FaM '
I
r
!
'
'
/
i
!
!
)
NOTE:
Please attach additional sheets if needed for consnents or for other
SALP functional areas.
j
LEAD INSPECTOR (f d
DATE
9/h/( 9
f
DISTRIBUTION
I
Branch Ch(af
,
Section unfef
!
Project Section Chief (for reactor inspections)
~. .{
5/3/88
.
- - _ _ . . - - _ . . _ - - _ _
- -
l
.__ - __ _ _ _ ________ -_ _
u.s.souc[ii.teovsAton, conauissa:m 4.,
evo.,
, ,
'-w,2 as
"
"
INSPECTOR's REPORT
~
.
~
Office of inopoetion and Enforcement
j
-
""2% /o . Af# /Nws 4e"
%),%
'
j
-
j
a'.g'a
Sc,;g, g
=;mac a.',
--,
. . , . . .
,
,
_
,,
F/V
Cnda i Asht - 7 V-~""
g o
-
3 o z
l
l l
s ,
1 7
.
I
I I
e
l
.
mte,
l
l l
c
...u
~...M. ..N.
l l
l llllE
I
~ ~
- -
-
E
.
. ..... ....... .
g ,. =.
mg
.
i
..
v . . ..
.
a .. .
.
_,
i,
i - i ...
..
-
........n
--
-
-
rIgIo cl
ls
,.~.
-..a - . ~ u~
,
_
___ _._ _
_
.c,_
r
- , _ .. _ ... . _ _ _
a- - -
I
.. o,n,
. .
, ,
. . - =
..
_
_,,
i. e
..
. . =ca.,
c..nem
ii . .v., n.
_
s .
n.,s..
i
_
_
_
. .
. ,,..a sc,
. .... a ,
..
.
.. . ..
-
-
--
. .
. .
. . . ,.cc,
. . .
,
i
i
'.cr.. M, ,,..=4
,,'ga ;
.
aw.;;
a==
.a,.',c,a;,*g=
c..
-
,,
- * cle
on-o.
. , , , , , , , ,
.,. ,,,,,,
I
. . et
g=,
.y
I
- .*4,
,
I
- -s~~,=
l.l.
e lo lal,
c
.
..
I.leIclel
I
l m, l
1 = I , l = l
I
'-"**'*aorw m
i g, l
g;
. . , , ,
_ _ _ _ _ ,,
<y
_
,
,
,
,
. ... _ ._. _
~ .
...
. _ , _ ,
n
~ ,
... ..
,
i - ... .
~. = -i
,,
i
. ... _
l l l ll
l !il l!
!l ll
l il l l ll
l ,(ll
!.lll .l
'
6 u 7aal-
N u g ici
1.,1
.' e w aTicH l..l..lli,i
,1!
.
.
,
_
11
1.,1
W I . ,1, , I l l . i . . il
'
, ,
, ,
,
ll
li,1
H l . . l . . l l l ,1
.J
'
, ,
. .
,
11
I.,1
Hl.
l.,Ill.ii.i
-
, ,
, ,
,
li. 1-
11
1.,l.
,1..lHl
l..lll.i..'
.
.
,
, ,
, ,
,
,
11
1,,1
WI.
l..lll,1.,
'
, ,
, ,
.
ll
1..I
Wl...l..lll,1
,
'
i ,
, ,
,
11
l..I
WI..l.
lll.i.,
'
, ,
, ,
.
,li, Ia
II
I,,1,
,1,,IHl..l.,ll.l.i.,
- i
, ,
, ,
,
,-
11
I,il
Hliil,illlili,
'
, ,
, ,
.
Il
1..I
MI..l..lll.i.,
=
, ,
, ,
,
,,Il
1.,1
Hl..l.,Ill,1.,
'
, ,
,
11
I..I.
,1.
IMI,ili,lllit.,
il.,l
'
t i
, ,
, ,
,
,
,,11
l..I
WI
.I,,Ill.ii,
'
, ,
,
,,ll
l.,1
Hl
.l..lll
I.,
'
, ,
,
8
M
'
'~
____
- - -- - -
.
>
+
,
.N ===A
.:
esauf mo .
om m
assear
-v.een
i.
UXame
"* "'
"8**""
-
,
me.
esa
,,,,,,
L.!
. INSPECTOR'S R P AT
m'a=neomy.
.-
a
(Continuation)
e.
8%IL
,
,
,
,
,
,
Office ofinspection and Entwcoment
c
p
~
. .
-
~ wnon on urnaham asm r w e raw r- _ . er ==a a==. e me ==__
n-
o
m...
_, _ . - _
m
mes se e. a-aeer. e .Fw
,7
2_
_ w
. ...,,,,,,_
_ ~ _
s.
l
t
a
d I
a
e
f
e
s
e
et
_,
et
sa
se <
s
4
19
o
0
0
31
O
a
5
m
.
s
P
s
a
m
P
w
w
F
w
h
.
r
.
-
U.S.leUCLSAA RESULATORY CommeSt
- - _ _ _ - _ _ _ -
.
_ . . . . . . . . _
_
.
.
.
.
...
_.
__
I
%
-
.
-
_.
o
8
-
-
-
_-
>
~.
-
_4
-
,o
4
m
{
x
-
m
m
n
m
-
_._
-
_
o
l
x
t
I
b
l
2
g
Mm
2
2
2
(
_
%
2
~4
d
_
C
-
C
-C
-
c
2
x
x
4
-s
2
g-
o=
-
_
=
w
_
_m
m
-
m
._i_
i
m
-
_i
m
i
m
.
-
=
w
w
_e
w
-
w
-
p
.
c-
g
.
-
3
-
,
-
_N._
-
-
-
n
%
-e
S
-
'3
~4
W
I
w
_4
-
'a
4
%
4
4
-
-
-
,
!=
m
- n-
__.
m
_m
m
_._
3
<:.
a
O
a
r
s
+
-
-
er
-
~.
-
= J
<
x
x
_x
@
_._
_ _.
o
o
_._
4
n
2
o
o
o
, x
-
-
C
C
o
1 11
o
4"
w
-
r-
_
r
c
o
-
m
m
m
c
-
o
r-
w
m
-
._._
3
_
3
m
_
__.
_
.
2
-
m
m
,
3
y
.
=
-
B
%
-
s
___
_
-
>
>
>
o
>
k.
s
w
-
-
,
n
w
-
m
m
m
.
A
m.
>
>
2
-
-
~
2
t
_v__
-
s
___
_
!
$
o
o
-
e
o ,
-
t
i
-
c.
m
m
2
m
m
'
g
m
l
m%
""""
T, %\\
'
M.
M
, T1
M
m
m
~
cr
n
n
n
m
s
n
x
,a
.
5
w
w
h
<
w
,
,
5
5.,
w
w
m
o
,
s
-q
-
.
-
,-
,m
u
<
a n
,
d
-
d
-
d
s
d
_
_.
p
c
-
<.
<
<
3
<
o_ L.
<
m
m
-
-
m
m
-
-
<
f""
-4
'
e.4
.h
k
-.4
-"I
H
-.
-
c
{
-
A
.
-4
"I
(
m
"""
8"*
r-
3*
,N
r-
3=
n
c
>
m
2*
m
' n
m
m
-
O
-7
(
% -
-
ng
g
c
-
M
a
.H
.
-
-
"1
l
O
!
O
-
o
o
-
__l
I
=
2
2
-z
3
-
-
o
-
@
-3
C
o
-
_'
C
-
-
m
.
m
-,,
m
___
-
o
k
G
i
U
>
-3
-
2-
w
T
2
-
-
m*
""""
'
'"'""
m
m
-
-
g
-
-
-
,
__.
_
3
.
' - ' * *
N
O
O
n
n
'^
=*a
w
-
5
g
-
g
w
-
g
m
-
m
l
m
_
m
s
m
=
___
t
m
I
m
T
m
m
--
O
-o
_:._. o
_
o
o
.
.
-
C
c
3
H
=4
h
.
(
m
-
(
-
-
-
-
- -
3
--
-
T,
_
,
y
{ n
,
o
g
n
g
o
4
.m
d
--s
-4
,
=
-
-
_
-
e
O
o
-
-
o
M
o
@
(A
-
2
2
2
2
8
-
c
>>
=
-
-
-
-
n
e
M*
3o
~4
K
%4
%
"
N
M
M
O"
'
+
e.
.-
s
.
o.
I
W
c
t-
s
['
d $'h.,jg, :'-
'
' k,, ,4 ;
-
,
.
y..
,
y.~
r.
,
b
'
5 .
J
'
~ '
~
'
. .! .
'
a
v.
..
.