Discusses Transmitting Changes Identified as Rev 59 to Security Plan for Dresden Nuclear Power Station,Units 1,2 & 3.Staff Determined That No NRC Approval Required in Accordance with 10CFR50.54(p)
ML20207L714
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 03/08/1999
From: Rossbach L
NRC (Affiliation Not Assigned)
To: Kingsley O
COMMONWEALTH EDISON CO.
References
TAC-MA4707, TAC-MA4708, NUDOCS 9903180243
Download: ML20207L714 (4)


Text

i March 8,1999 Mr. Oliver D. Kingsley, President Nuclear Generation Group Commonwealth Edison Company Executive Towers West lll 1400 Opus Place, Suite 500 Downers Grove,IL 60515

SUBJECT:

REVISION 59 TO THE SECURITY PLAN FOR DRESDEN NUCLEAR POWER STATION, UNITS 1,2, AND 3 (TAC NOS. MA4707 AND MA4708)

Dear Mr. Kingsley:

By letter of December 30,1998, Commonwealth Edison Company (Comed) transmitted changes identified as Revision 59 to the Security Plan for the Dresden Nuclear Power Station, Units 1,2, and 3, that were submitted under the provisions of 10 CFR 50.54(p). By letter dated January 14,1999, you were notified by our Region 111 office that this revision was being forwarded to our Headquarters office for review due to possible policy implications.

Based on Comed's determination that the changes do not decrease the effectiveness of the plan and after the staff's review of the changes, the staff determined no NRC approvalis required in accordance with 10 CFR 50.54(p). Implementation of these changes will be subject to inspection to confirm that the changes have not decreased the overall effectiveness of your security plan.

The enclosere to your letter contains Safeguards information of a type specified in 10 CFR 73.21 and win be withheld from public disclosure. In accordance with 10 CFR 2.790 of the Commission's regulations, a copy this letter will be placed in the NRC Public Document Room.

Sincerely, ORIG. SIGdED BY Lawrence W. Rossbach, Project ?.ianager Project Directorate 111-2 Ob10 Division of Licensing Project Management k0 Office of Nuclear Reactor Regulation F PDR Docket Nos.50-010; 50-237; 50-249 ..

Ei cc: See next page g DISTRIBUTION: I o Docket Filer PUBLIC PDill-2 r/f JZwolinski/SBlack SRicharda CMoore LRossbach RBurrows f TQuay RSkelton OGC,015B18 ACRS, T2E26 /,ck MRing, Rill JCreed, Rill

@/

.g g a pem>a m ucua DOCUMENT NAME: G:\P D 3-2tC MtD R ES D ENtLTRA4707.WP D T1 RECEIVE A COPY GF THIS DOCUMENT, INDICATE IN THE Box: "C" = COPY WITHouT Enclosures *E" = COPY WITH ENCLOSURES 'N" OFFICE PM.PD3-2 l C , LARD 8-2 hM:PDND PSGB M BC:PSGB D.PD3- C NAME LRossbach:s Ckob RBurrows # .RFSk,elton kh TOuay

  • SRichards 9h DATE 3/ Cf /99 3/ k /99 [ ll /99 3/ d /99 k O /99 3/ 7 /99 OFFICIAL RECORb COPY

. I '

Mr. R. M. Krich Viced President - Regulatory Services Commonwealth Edison Company Executive Towers West 111 1400 Opus Place, Suite 500 Downers Grove, IL 60515 l

SUBJECT:

DRESDEN NUCLEAR STATION, UNITS 1,2 AND 3 SECURilY PLAN (REV 59) l (TAC Numbers MA4707 and MA4708)

This letter acknowledges receipt of your letter dated December 30,1998 which transmitted j changes identified as Revision 59 to the Dresden Nuclear Power Station, Units 1,2, and 3  ;

Security Plan, submhted under the provisions on 10 CFR 50.54(p). On January 14,1999, you '

were notified by our Region til office that this revision was being forwarded to our Headquarters office for review due to possible policy implications.  ;

Based on your determination the changes do not decrease the effectiveness of the plan and ofter review of the changes, no NRC apprcvalis required, in accordance with 10 CFR 50.54(p). Implementation of these changes will be subject to inspection to confirm that the changes have not decreased the effectiveness of the plan.

The enclosure to your letter contains Safeguards Information of a type specified in 10 CFR

/[

73.21 and will be withheld from public disclosura.

l In accordance with 10 CFR 2.790 of the Commission's regulation, /a copy this letter will be i placed in the NRC Public Document Room.

Sincerely, Lawrence W. Ros'sbach Project Direct 0 rate 111-2 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos.: 50-010; 50-237; 50-249 ,/

License Nos.: DRP 2; DPR-19; DPR-25 /

cc: Region til /

Distribution:

Docket Files PSGB r/f L Rossbach T. Quay R. Skelton DOCUMENT NAME: G:skelton/dresdeitwpd i n ..i. . ..,, ., iw. o . inoie . i. ,s. 6..: e , copy wirs.oe .ee. cam.ntiencio.ur. r . co," with .et. chm.nti.ncio.u w . N.eepy OFFICE PSGB:DIPM , BC:PSGS;DIPM M PDill-2:NRR <

mO:IRIP G PDIII-2:NRR NAME RFSkeltonn M TRQuaM 9 LWRossbach Jfwf RBurrows D e 3Richards DATE 02/h99 V/ 02/n/99 ' D 02//B99 02/$99 02/ /99 F OFFICIAL RECORD COPY

R / :- #, _

te: .

p k UNITED STATES s* j- NUCLEAR REGULATORY COMMIS810N y.....)

WASHINGTON, D.C. 30006-coM March 8, 1999

~

Mr. Oliver D. Kingsley, President Nuclear Generation Group Commonwealth Edison Company Executive Towers West 111 1400 Opus Place, Suite 500 Downers Grove,IL 60515

SUBJECT:

REVISION 59 TO THE SECURITY PLAN FOR DRESDEN NUCLEAR POWER

- STATION, UNITS 1,2, AND 3 (TAC NOS. MA4707 AND MA4708)

Dear Mr. Kingsley:

By letter of December 30.1998 Commonwealth Edison Company (Comed) transraitted changes identified as Re~ vision 59 to the Security Plan for the Dresden Nuclear Power Station, Units 1,2, and 3, that were submitted under the provisions of 10 CFR 50.54(p). By letter dated January 14,1999, you were notified by our Region Ill office that this revision was being forwarded to our Headquarters office for review due to possible policy implications.

Based on Comed's determination that the changes do not decrease the effectiveness of the plan and after the staff's re%sw of the changes, the staff determined no NRC approvalis required in accordance with 10 CFR 50.54(p). Implementation of these changes will be subject to inspection to confirm that the changes have not decreased the overall effectiveness of your security plan.

! The a ' A e to your letter contains Safeguards Information of a type specified in 10 CFR 73.21 m .w be vehheld from public disclosure. In accordance with 10 CFR 2.790 of the Commission's regulatiors, a copy this letter will be placed in the NRC Public Document Room.

Sincerely, w/

.G< . W Lawrence W. Rossbach, Project Manager Project Directorate ill-2 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos.50-010; 50-237; 50-249 cc: See next page a

O. Kingsley -

Dresden Nuclear Power Station . j Commonwealth Edison Company Units 2 and 3

- oc:

Commonwealth Edison Company Mr. Gene H. Stanley Site Vice President- Dresden PWR Vice President 6500 N. Dresden Road Commonwealth Edison Company Morris, Illinois 60450-9765 Executive Towers West 111 1400 Opus Place, Suite 900 Commonwealth Edison Company Downers Grove, Illinois 60515 Dresden Station Manager 6500 N. Dresden Road Mr. Christopher Crane Morris, Illinois 60450-9765 BWR Vice President Commonwealth Edison Company U.S. Nuclear Regulatory Commission Executive Towers West ill Dresden Resident inspectors Office 1400 Opus Place, Suite 900 6500 N Dresden Road Downers Grove, Illinois 60515 Morris, Illinois 60450-9766 Mr. R. M. Krich Regional Admlaistrator Vice President - Regulatory Services U.S. NRC, Region 111 Commonwealth Edison Company 801 Warrenville Road Executive Towers West lil 4 Usle, Illinois 60532-4351 1400 Opus Place, Suite 500 Downers Grove, Illinois 60515 lilinois Department of Nuclear Safety Office of Nuclear Facility Safety Ms. Pamela B. Stroebel 1035 Outer Park Drive Senior Vice President and General Counsel Springfield, Illinois 62704 Commonwealth Edison Company P.O. Box 767 Chairman . Chicago, Illinois 60690-0767 Grundy County Board Administration Building 1320 Union Street Morris, Illinois 60450

, Document Control Desk-Licensing Commonwealth Edison Company 1400 Opus Place, Suite 400 Downers Grove, Illinois 60515 Commonwealth Edison Company Reg. Assurance Manager- Dresden 6500 N. Dresden Road Morris, Illinois 60450-9765 Mr. David Helwig Senior Vice President Commonwealth Edison Company Executive Towers West lli 1400 Opus Place, Suite 900 Downers Grove, Illinois 60515