Forwards Exemption from Schedular Requirements of 10CFR50.48 to Switchgear Room & Related Plant Areas,To Assure Adequate Level of Fire Protection.Exemption Requires Submittal of Implementation Plan by 860930
ML20212M876
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 08/25/1986
From: Harold Denton
Office of Nuclear Reactor Regulation
To: Opeka J
CONNECTICUT YANKEE ATOMIC POWER CO.
Shared Package
ML20212M877 List:
References
NUDOCS 8608270350
Download: ML20212M876 (1)


Text

/ Yw? -

Mt No. 50-213 August 25, 1986 ,

Mr. John F. Opeka, Senior Vice President Nuclear Engineering and Operations Connecticut Yankee Atomic Power Company Post Office Box 270 Hartford, Connecticut 06141-0270 .

Dear Mr. Opeka:

SUBJECT:

FIRE PROTECTION EXEMPTION - HADDAM NECK PLANT The Commission has issued the enclosed exemption from the schedular requirements pf Section 50.48 and Appendix R to 10 CFR Part 50, in response to your letter dated March 7, 1986. This exemption, which is being forwarded to the Office of the Federal Register for publication, pertains to the extension of the completion date for modifications to the switchgear room and related plant areas, to assure an adequate level of fire prctection at the Haddam Neck Plant.

As described in Section IV of the enclosed exemption, the staff will require that, by September 30, 1986, you submit a detailed implementation plan including major project milestones for which you will submit bimonthly progress reports.

g This exemption is also contingent upon completion of the cormitments in your letter of July 3, 1986, which resulted from the fire protection audit conducted on June 16-20, 1986. Failure to meet these project milestones by more than 30 days will constitute a violation of the exemption for which appropriate compliance / enforcement action will be taken.

Sincerely, -

Orlinal signed ay

()L R. Denton Harold R. Denton, Director Office of Nuclear Reactor Regulation

Enclosure:

Exemption DISTRIBUTION cc w/ enclosure: 1 Docket File HDenton See next page NRC PDR RVollmer D. Crutchfield Local PDR ACRS (10)

J. Calvo ISAP Reading NSIC -

C. Grimes FMiraglia -0iity 0GC-B F. Schroeder Edordan BGrimes JPartlow AWang PAnderson FAkstulewicz ISAP:DPL-f r( ISAP:DPL-BJb ISAP:DPL- ISAP:DPL- PEISB:D L-B OELOW AWang:mn FAkstulewicz PAnderson C# CGrimes JCalvo /< WShields 08/$/86 08/7/86 08/4/86 08/t/86 08/// /86 08//(/86 D d eder ia er n 08/gq f86 08//2//_86 08/ /86 8/g/86 08/[/86

/