Forwards Amend 195 to License DPR-61 & Safety Evaluation. Amend Deletes Certain TSs Either No Longer Applicable to Permanently Shutdown & Defueled State of Reactor or Duplicate Regulatory Requirements
ML20217K316
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 10/19/1999
From: Fredrichs T
NRC (Affiliation Not Assigned)
To: Mellor R
CONNECTICUT YANKEE ATOMIC POWER CO.
Shared Package
ML20217K319 List:
References
TAC-MA5756, NUDOCS 9910260097
Download: ML20217K316 (4)


Text

Mr. Russell A. Mellor i October 19, 1999

,Vica President .Oper:tions end D;commis:loning Connecticut Ytnkso Atomic Power Compiny 362 injun Hollow Road .

y East Hampton, CT 06424-3099

SUBJECT:

' HADDAM NECK PLANT - ISSUANCE OF AMENDMENT RE: RELOCATION OF

. REQUIREMENTS TO LICENSEE-CONTROLLED DOCUMENTS t

~(TAC NO. MA5756)

)

Dear Mr. Mellor:

l

,g: l

, in response to your application dated June 3,1999, as supplemented by letter dated August 24, i1999, the Commission has ismed the enclosed Amendment No.195 to Facility Operating License No. DPR-61 for the Haddam Neck Plant.

The' amendment relocates certain Technical Specification (TS) requirements to l licensee-controlled documents. The administrative controls section of your TSs has been revised to more closely conform to standardized TSs. Administrative controls have been added for the control of radioactive effluents.' A TS Bases Control Program has been added The weight limit for loads carried over the spent fuel pool has been increased.' The amendment deletes certain TSs that are either (1) no longer applicable to the permanontly shutdown and '

defueled state of the reactor, or (2) duplicate regulatory requirements, or (3) duplicate j

information located in the Updated Final Safety Analysis Report. A number of editorial changes

. were made to clarify the language used, te correct typographical errors, to renumber the listings, to remove section numbers that no longer contain requirements, and to renumber the pages in the TSs.

- A copy of our related Safety Evaluation is enclosed. The Notice of Issuance will be included in

' the Commission's next biweekly Federal Hegisternotice.

Sincerely, ORIG. SIGNED BY Thomas L. Fredrichs, Project Manager Decommissioning Section

, Project Directorate IV & Decommissioning 9910260097 991019 . Division of Licensing Pro,iect Management i DR ADOCK 0 23 Office of Nuclear Reactor Regulation Docket No. 50-213 Enclosurw 1. Amendment No.195 to DPR-61

2. Safety Evaluation cc w/encis: See next page QlSTRIBUTION: c K ^ MN Docket File *'OGC- RScholl (email SE only)

PUBLIC ~ ACRS/ACNW GHill (2)

PD#1V-D Reading KBrockman, RIV WRaymond, R1

' SRichards (clo) ' WBeckner DScrenci, RI Jo receive a copy of tnis document, indicate "C" in the box >

%' OFFICE PDIV-3/PM C PDIV-3/L6 n C IOMB* OGC* PDIV-3/SC NAME T.FredrichsF L. Berry @ RLatta APH M.Masnik N /$

DATE /0 / /(/99 0/16 /99 10/06/99 09/30/99 l 0/ I3 /99

  • SE incorporated w/ minor revisions DOCUMENT NAME: G:\PDIV-3\Haddam\amda5756.wpa OFFICIAL RECORD COPY

>See previous concurrence.

W Mr. Russell A. Mellor Vice President - Oper;tions end D; commissioning Connecticut Ycnkee Atomic Power Comprny 362 Injun Hollow Road East Hampton, CT 06424-3093

SUBJECT:

HADDAM NECK PLANT - ISSUANCE OF AMENDMENT RE: RELOCATION OF REQUIREMENTS TO LICENSEE-CONTROLLED DOCUMENTS (TAC NO. MA5756)

Dear Mr. Mellor:

In response to your application dated June 3,1999, as supplemented by letter dated August 24, 1999, the Commission %s issued the enclosed Amendment No. to Facility Operating License No. DPR-61 for the Haddam Neck Plant. -

The amendment relocates certain Technical Specification (TS) requirements to W.s ~

licensee-contrcbd documents. The administrative controls section of your TSs have been revised to more closely conform to standardized TSs. Administrative controls have been added for the control of radioactive effluents. A TS Bases Control Program has been added. The weight limit for loads carried over the spent fuel pool has been increased. The amendment deletes certain TSs that are either (1) no longer applicable to the permanently shutdown and defueled state of the reactor, or (2) duplicate regulatory requirements, or (3) duplicate information located in the Updated Final Safety Analysis Report. A number of editorial changes i were made to clarify the language used, to correct typographical errors, to renumber the '

listings, to remove section numbers that no longer contain requirements, and to renumber the pages in the TSs. /  !

A copy of our related Safety Evaluation is enclosed. The Notice of issuance will.b included in the Commission's next biweekly Federa/ Register notice. /

Sincerely, Thomas L. Fredrichs, Project Manager Decommissioning Section' Project Directorate IV & Decommissioning Division of Licensing Project Management Office of Nuclear Reactor Regulation

/

Docket No. 50-213 / i

Enclosures:

1. Amendment No. to DPR-61 / l
2. Safety Evaluation /

cc w/encis: See next page / ,

DISTRIBUTION:

Docket File OGC j[ RScholl (email SE only)

PUBLIC ACRS/ACNW / GHill (2)

PD#1V-D Reading KBrockman, ,RIV WRaymond, RI SRichards (clo) WBeckner f DScrenci, RI

/

To receive a copy of this document, indicate "C" in the box OFFICE - PDIV-3/PM ,C, PDIV-3/LA / C IOMB* OGC PDIV-3/SC MAME T.FredrichsN L. Berry RLatta [N -

M.Masnik DATE 9 / qu/99 /' /99 8 / U /99 / /99 / /99

  • SE incorporated w/ minor revisions .

DOCUMENT NAME: G:\PDIV-3\Haddam\amda5756.wpd OFFICIAL RECORD COPY

i p

[ %g t UNITED STATES j

i

f NUCLEAR REGULATORY COMMISSION l V 't WASHINGTON, D.C. 20616 4001
          • October 19, 1999 Mr. Russell A. Mellor i Vbe President - Operations and Decommissioning I Connecticut Yankee Atomic Power Company I l 362 Injun Hollow Road l East Hampton, CT 06424-3099

SUBJECT:

HADDAM NECK PLANT - ISSUANCE OF AMENDMENT RE: RELOCATION OF REQUIREMENTS TO LICENSEE-CONTROLLED DOCUMENTS  :

(TAC NO. MA5756)

Dear Mr. Mellor:

. In response'to your application dated June 3,1999, as supplemented by letter date'd August 24, 1999, the Commission has issued the enclosed Amendment No.195 to Facility Operating l

License No. DPR-61 for the Haddam Neck Plant.

1 The amendment relocates certain Technical Specification (TS) requirements to licensee-controlled documents. The administrative controls section of your TSs has been revised to more closely conform to standardized TSs. Administrative controls have been added for the control of radioactive effluents. A TS Bases Control Program has been added. The weight limit for loads carried over the spent fuel pool has been increased. The amendment deletes certain TSs that ara either (1) no longer applicable to the permanently shutdown and  ;

defueled state of the reactor, or (2) duplicate regulatory requirements, or (3) duplicate j information located in the Updated Final Safety Analysis Report. A number of editorial changes  ;

were made to clarify the language used, to correct typographical errors, to renumber the  !

listings, to remove section numbers that no longer contain requirements, and to renumber the  !

pages in the TSs.

A copy of our related Safety Evaluation is enclosed. The Notice of issuance will be included in

. the Commissior/s next biweekly Federal Register notice. l Sincerely, l- 7 6-j A / / ' W / '"

l Thomas L. Fredrichs, Project Manager Decommissioning Section Project Directorate IV & Decommissioning Division of Licensing Project Management i Office of Nuclear Reactor Regulation Docket No. 50-213

Enclosures:

1. Amendment No. 195 to DPR-61 l 2. Safety Evaluation l

cc w/encis: See next page L

+

Haddam Neck Plant .

1 y cc:. ._ c . . . . _

. ' Mr. Allan Johanson, Assistant Director- Mr. G. P. van Noordennen j

'ONice of Policy and Management- Manager- Nuclear Licensing Policy Development and Planning Division Northeast Utilities Service Company 450 Capitol Avenue - MS# 52ERN 362 injun Hollow Road

P. O. Bo 341441, ~ East Hampton, CT 06424-3099 L . Hartfords CT 06134-1441-Mr. D. K. Davis ~ l

. Regional Administrator' Chairman, President and Chief i Region I . .

. Executive Officer 1

(. ' U.S. Nuclear Regulatory Commission Connecticut Yankee Atomic Power Co.

. 475 Allendalo Road . 580 Main Street

' King of Prussia, PA 19406 Bolton, MA 01740 -

Board of Selectmen Mr. T. W. Bennet Town Office Building Vice President and Chief Financial officer Haddam, CT 06438 Connecticut Yankee Atomic Power Co.  !

580 Main Street Mr.' James 'S. Robinson Bolton, MA 01740  ;

Manager, Nuclear investments and Administration Director i New England Power Company Monitoring and Radiation Dmsson 25 Research Drive - Department of Environmental Protection Westborough, MA 01582 '79 Elm Street Hartford, CT 06106-5127 -

MCM Rh Connecticut Yankee Atomic Power.Co. - Mr. G. H. Bouchard, Unit Director Ropes & Gray'- Connecticut Yankee Atomic Power Co.

'One International Place 362 Injun Hollow Road Boston, MA 02110-2624 East Hampton, CT 06424-3099 Mr. 4 J. Heider, Decommissioning Director Mr. J. D. Hasettine '

, Connecticut Yankee Atomic Power Co. Strategic Planning Director 362 Injun Hollow Road Connecticut Yankee Atomic Power Co. 4

East Hampton, CT 06424-3099 - 362 Injun Hollow Road East Hampton, CT 06424-3099 Mr. M. D. Cavanaugh

- Communications Manager. Ms. Rosemary Bassilakis Connecticut Yankee; Atomic Power Co. Citizens Awareness Network

- 362 Injun Hallow Road 54 Old Tumpike Road East Hampton,' CT 06424-3099 ' Haddam, CT 06438 Y Ms'. Debo' rah B. Katz, President

- Citizens Awareness Network

- 4 P. O. Box 83 Shelburne Falls, MA 01370-0083 1

,