Letter Sequence Other |
---|
|
|
MONTHYEARIR 05000346/19870321987-12-0101 December 1987 Partially Withheld Enforcement Conference Rept 50-346/87-32 on 871119 (Ref 10CFR73.21(c)(2)).Major Areas Discussed: Circumstances Resulting in Potential Violation of Licensee Security Plan Re Barrier Inadequate Penetration Resistance Project stage: Request IR 05000346/19880221988-08-10010 August 1988 Partially Withheld Insp Rept 50-346/88-22 on 880111-15 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Assessment Aids,Audits,Detection Aids - Vital Areas, Communications,Records & Repts Project stage: Request ML20151S6601988-08-10010 August 1988 Forwards Evaluation for B&W Owners Group Generic Rept, Design Requirements for Diverse Scram Sys & AMSAC (ATWS Mitigation Sys Actuation Circuitry). Most of Rept Sections Acceptable.Several Design Requirements Encl Project stage: Other ML20195E5931988-10-31031 October 1988 Discusses Util ATWS Design Requirements & Implementation Schedule.Util Plans to Design & Install ATWS Sys by End of Sixth Refueling Outage Project stage: Other ML20235W5371989-02-28028 February 1989 Forwards Design Summary Re plant-specific Info for ATWS Implemetation (10CFR50.62).Encl Provides Evaluation That Demonstrates That for All Loss of Offsite Power Scenarios, Control Rods Will Be Released Due to Loss of Voltage Project stage: Other ML20246E3091989-05-0303 May 1989 Forwards Request for Addl Info Re ATWS Rule (10CFR50.62). Subjs Include Diversity from Existing Reactor Protection Sys & Electrical Independence from Existing Reactor Protection Sys Project stage: RAI ML20246D2231989-06-30030 June 1989 Submits Rev to plant-specific Submittal for ATWS Implementation (10CFR50.62).Util Plans to Design & Install ATWS Sys by End of Sixth Refueling Outage,Scheduled to Begin in Feb 1990 Project stage: Other ML20248D8211989-09-29029 September 1989 Forwards Safety Evaluation Accepting Util 890228 & 0630 Proposed plant-specific Designs to Comply w/10CFR50.62 ATWS Rule Requirements.Proposed Date of May 1990 for Implementing ATWS Mods Also Acceptable Project stage: Approval 1989-02-28
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P2061999-10-26026 October 1999 Forwards for First Energy Nuclear Operating Co Insp Rept 50-346/99-17 on 990928-1001.Insp Was Exam of Activities Conducted Under License Re Implementation of Physical Security Program.No Violations Identified ML20217N3851999-10-20020 October 1999 Forwards RAI Re Licensee 990521 Request for License Amend to Allow Irradiated Fuel to Be Stored in Cask Pit at Davis-Besse,Unit 1.Response Requested within 60 Days from Receipt of Ltr ML20217N2321999-10-15015 October 1999 Requests NRC Approval to Use Alternative to Requirements of 10CFR50.55a(f)(4)(ii).Licensee Requests Extension to Specified Schedule for Implementing Updates to IST Program ML20217G9201999-10-14014 October 1999 Discusses Utils Request for Approval of Quality Assurance Program Changes PY-CEI-NRR-2438, Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl1999-10-14014 October 1999 Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl ML20217F8371999-10-0808 October 1999 Forwards Insp Rept 50-346/99-10 on 990802-0913.One Violation Occurred Being Treated as NCV ML20217A5641999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Davis-Besse on 990901.Informs That NRC Plans to Conduct Addl Insps to Address Questions Raised by Issues Re Operator Errors & Failure to Commit to JOG Topical Rept on MOV Verification ML20212L0691999-09-30030 September 1999 Forwards,For Review & Comment,Copy of Preliminary ASP Analysis of Operational Condition Discovered at Unit 1 on 981014,as Reported in LER 346/98-011 ML20216J6701999-09-24024 September 1999 Forwards Post Examination Documentation for Written Operator Initial License Examination Administered at Davis-Besse Nuclear Power Station on 990920.Without Encls ML20212D3501999-09-21021 September 1999 Forward Copy of Final Accident Sequence Precursor Analysis of Operational Event at Plant,Unit 1 on 980624,reported in LER 346/98-006 05000346/LER-1998-001, Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached1999-09-0909 September 1999 Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached ML20216E5961999-09-0707 September 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20211P3001999-09-0707 September 1999 Forwards FEMA Transmitting FEMA Evaluation Rept for 990504 Emergency Preparedness Exercise at Davis-Besse Nuclear Power Plant.No Deficiencies Identified.One Area Requiring C/A & Two Planning Issues Identified ML20211K6681999-08-30030 August 1999 Forwards Copies of Certified Personal Qualification Statement - Licensee (NRC Form 398) for Operator Candidates Listed Below.Without Encls ML20211K6611999-08-30030 August 1999 Forwards Copies of Operator License Renewal Applications for Individuals Listed.Operators Have Successfully Completed Appropriate Operator Requalification Training Program at Dbnps.Without Encls ML20211K0951999-08-30030 August 1999 Forwards Request for Addl Info Re Fire & Seismic Analyses of IPEEE for Davis-Besse Nuclear Power Station,Unit 1. Response Requested within 60 Days ML20211H0201999-08-25025 August 1999 Forwards semi-annual FFD Rept for 990101-0630 for DBNPS, Unit 1,IAW 10CFR26.71(d) ML20211D1171999-08-20020 August 1999 Forwards Insp Rept 50-346/99-09 on 990623-0802.Violations Identified & Being Treated as Noncited Violations ML20211G3911999-08-20020 August 1999 Forwards Update to Estimated Info for Licensing Action Requests Through 010930,re Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates PY-CEI-NRR-2411, Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl1999-08-19019 August 1999 Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl ML20211J9201999-08-13013 August 1999 Urges NRC to Find Funds for Stockpiling Radiation Pills for Residents Living Near Plant ML20211B0161999-08-13013 August 1999 Forwards SE Accepting Evaluation of Second 10-year Interval Inservice Insp Program Request for Relief Numbers RR-A16, RR-A17 & RR-B9 for Plant,Unit 1 ML20210T1061999-08-12012 August 1999 Forwards Preliminary NRC Forms 398 & 396 for Listed Candidates,Per Operator License Exam Scheduled for Week of 990913.Encl Withheld ML20210S6071999-08-11011 August 1999 Provides Final Response to NRC RAI Re GL 98-01, Y2K Readiness of Computer Systems at Npps ML20210P8051999-08-0909 August 1999 Forwards Insp Rept 50-346/99-15 on 990712-16.No Violations Noted.However,Several Deficiencies Were Identified with Implementation of Remp,Which Collectively Indicated Need for Improved Oversight of Program IR 05000346/19980211999-08-0606 August 1999 Refers to NRC Insp Rept 50-346/98-21 Conducted on 980901- 990513 & Forwards Nov.Two Violations Identified Involving Failure to Maintain Design of Valve & Inadequate C/A for Degraded Condition Cited in Encl NOV 05000346/LER-1998-009, Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl1999-08-0606 August 1999 Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl ML20210H6101999-07-30030 July 1999 Informs That Region III Received Rev 21 to Various Portions of Davis-Besse Nuclear Power Station Emergency Plan.Revision Was Submitted Under Provisions of 10CFR50.54(q) in Apr 1999 ML20210H0491999-07-28028 July 1999 Forwards Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, to Allow Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G5521999-07-28028 July 1999 Provides Addl Response to 980923 OL Licensing Exam Rept 50-346/98-301 Re OL Exam Administered in Aug 1998.Results of Root Cause Investigation & Corrective Actions,Discussed ML20210G3831999-07-27027 July 1999 Forwards Application for Amend to NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20211P3071999-07-26026 July 1999 Forwards Final Rept for 990504 Biennial Radiological Emergency Preparedness Exercise for David-Besse Power Station.No Deficiencies Identified for Any Jurisdiction During Exercise ML20210G4391999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumentation, & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20210G7151999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrument - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5151999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G3211999-07-26026 July 1999 Forwards Written OL Exam & Supporting Matl for Exam to Be Administered at DBNPS During Week of 990913.Listed Encls Withheld from Public Disclosure Until After Exam Complete ML20210C4381999-07-20020 July 1999 Forwards Insp Rept 50-346/99-08 on 990513-0622.Unidentified RCS Leak Approached TS Limit of 1 Gallon Per Minute Prior to Recently Completed Maint Outage.Three Violations of NRC Requirements Identified & Being Treated as NCVs ML20209G3681999-07-15015 July 1999 Advises That Info Submitted in & 990519 Affidavit Re Design & Licensing Rept,Davis-Besse,Unit 1 Cask Pit Rack Installation Project,Holtec Intl, HI-981933,marked Proprietary,Will Be Withheld from Public Disclosure ML20207H6401999-07-0909 July 1999 Discusses Closure of TAC MA0540 Re Util Responses to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Staff Has Revised Info in Rvid & Releasing It as Rvid Version 2 ML20209D1341999-07-0808 July 1999 Forwards Notice of Withdrawal of Application for Amend to Operating License.Proposed Change Would Have Modified Facility TSs Pertaining to Allowable as-found Pressure Lift Setting Tolerance of Two Pressurizer Code Safety Valves 05000346/LER-1998-012, Forwards LER 98-012-01,which Is Being Submitted to Provide Addl Info Re 981018 Occurrence.Commitment List Attached1999-07-0707 July 1999 Forwards LER 98-012-01,which Is Being Submitted to Provide Addl Info Re 981018 Occurrence.Commitment List Attached ML20209C3981999-07-0101 July 1999 Responds to NRC Re Violations Noted in Insp Rept 50-346/98-21.Corrective Actions:Developed Rev to Boric Acid Control Program & Work Process Guideline on Plant Leakage ML20209B5821999-06-24024 June 1999 Provides Justification for Rev to Completion Date for One of Insp follow-up Items Cited in Insp Rept 50-346/98-03, Designated as Inspector follow-up Item 50-346/97-201-10 ML20196G1251999-06-23023 June 1999 Responds to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants ML20196E5321999-06-17017 June 1999 Forwards Addl Info Re Relief Request RR-A16 to Support NRC Approval of Relief Request ML20195K2751999-06-16016 June 1999 Forwards Safety Evaluation Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195F9071999-06-10010 June 1999 Forwards Application for Amend to NPF-3,changing Tech Specs 3/4.6.4.4, Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20195F8851999-06-0707 June 1999 Withdraws 950929 License Amend Application,Proposing Mod to Allowable as-found Pressure Lift Setting Tolerance of Two Pressurizer Code Safety Valves ML20207G0751999-06-0707 June 1999 Forwards Insp Rept 50-346/99-04 on 990323-0513.Violations Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217N2321999-10-15015 October 1999 Requests NRC Approval to Use Alternative to Requirements of 10CFR50.55a(f)(4)(ii).Licensee Requests Extension to Specified Schedule for Implementing Updates to IST Program PY-CEI-NRR-2438, Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl1999-10-14014 October 1999 Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl ML20216J6701999-09-24024 September 1999 Forwards Post Examination Documentation for Written Operator Initial License Examination Administered at Davis-Besse Nuclear Power Station on 990920.Without Encls 05000346/LER-1998-001, Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached1999-09-0909 September 1999 Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached ML20216E5961999-09-0707 September 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20211K6611999-08-30030 August 1999 Forwards Copies of Operator License Renewal Applications for Individuals Listed.Operators Have Successfully Completed Appropriate Operator Requalification Training Program at Dbnps.Without Encls ML20211K6681999-08-30030 August 1999 Forwards Copies of Certified Personal Qualification Statement - Licensee (NRC Form 398) for Operator Candidates Listed Below.Without Encls ML20211H0201999-08-25025 August 1999 Forwards semi-annual FFD Rept for 990101-0630 for DBNPS, Unit 1,IAW 10CFR26.71(d) ML20211G3911999-08-20020 August 1999 Forwards Update to Estimated Info for Licensing Action Requests Through 010930,re Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates PY-CEI-NRR-2411, Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl1999-08-19019 August 1999 Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl ML20211J9201999-08-13013 August 1999 Urges NRC to Find Funds for Stockpiling Radiation Pills for Residents Living Near Plant ML20210T1061999-08-12012 August 1999 Forwards Preliminary NRC Forms 398 & 396 for Listed Candidates,Per Operator License Exam Scheduled for Week of 990913.Encl Withheld ML20210S6071999-08-11011 August 1999 Provides Final Response to NRC RAI Re GL 98-01, Y2K Readiness of Computer Systems at Npps 05000346/LER-1998-009, Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl1999-08-0606 August 1999 Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl ML20210G5521999-07-28028 July 1999 Provides Addl Response to 980923 OL Licensing Exam Rept 50-346/98-301 Re OL Exam Administered in Aug 1998.Results of Root Cause Investigation & Corrective Actions,Discussed ML20210H0491999-07-28028 July 1999 Forwards Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, to Allow Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G3831999-07-27027 July 1999 Forwards Application for Amend to NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G4391999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumentation, & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20210G7151999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrument - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5151999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20211P3071999-07-26026 July 1999 Forwards Final Rept for 990504 Biennial Radiological Emergency Preparedness Exercise for David-Besse Power Station.No Deficiencies Identified for Any Jurisdiction During Exercise ML20210G3211999-07-26026 July 1999 Forwards Written OL Exam & Supporting Matl for Exam to Be Administered at DBNPS During Week of 990913.Listed Encls Withheld from Public Disclosure Until After Exam Complete 05000346/LER-1998-012, Forwards LER 98-012-01,which Is Being Submitted to Provide Addl Info Re 981018 Occurrence.Commitment List Attached1999-07-0707 July 1999 Forwards LER 98-012-01,which Is Being Submitted to Provide Addl Info Re 981018 Occurrence.Commitment List Attached ML20209C3981999-07-0101 July 1999 Responds to NRC Re Violations Noted in Insp Rept 50-346/98-21.Corrective Actions:Developed Rev to Boric Acid Control Program & Work Process Guideline on Plant Leakage ML20209B5821999-06-24024 June 1999 Provides Justification for Rev to Completion Date for One of Insp follow-up Items Cited in Insp Rept 50-346/98-03, Designated as Inspector follow-up Item 50-346/97-201-10 ML20196G1251999-06-23023 June 1999 Responds to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants ML20196E5321999-06-17017 June 1999 Forwards Addl Info Re Relief Request RR-A16 to Support NRC Approval of Relief Request ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195F9071999-06-10010 June 1999 Forwards Application for Amend to NPF-3,changing Tech Specs 3/4.6.4.4, Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20195F8851999-06-0707 June 1999 Withdraws 950929 License Amend Application,Proposing Mod to Allowable as-found Pressure Lift Setting Tolerance of Two Pressurizer Code Safety Valves ML20207F4231999-06-0202 June 1999 Forwards Rev 1 to DBNPS Emergency Preparedness Evaluated Exercise Manual 990504, IAW 10CFR50.4.NRC Evaluated Exercise Has Been Rescheduled for 991208,since NRC Did Not Evaluate 990504 Exercise ML20207E9561999-05-28028 May 1999 Forwards Update to NRC AL 98-03,re Estimated Info for Licensing Activities Through Sept 30,2000 ML20207E2521999-05-28028 May 1999 Forwards Rev 18,App A,Change 1 to Davis-Besse Nuclear Power Station,Unit 1,industrial Security Plan IAW Provisions of 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML20207E7801999-05-21021 May 1999 Forwards Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capacity.Proprietary & non- Proprietary Version of Rev 2 to HI-981933 Re Cask Pit Rack Installation Project,Encl.Proprietary Info Withheld ML20206N0231999-05-0606 May 1999 Forwards License Renewal Applications for Davis-Besse Nuclear Power Station,Unit 1 for ML Klein,Cn Steenbergen & CS Strumsky.Without Encls ML20206D2421999-04-28028 April 1999 Forwards Combined Annual Radiological Environ Operating Rept & Radiological Effluent Release Rept for 1998. Rev 11, Change 1 to ODCM & 1998 Radiological Environ Monitoring Program Sample Analysis Results Also Encl PY-CEI-NRR-2382, Forwards 1998 Annual Rept for Firstenergy Corp, for Perry Nuclear Power Plant & Davis-Besse Nuclear Power Station.Form 10-K Annual Rept to Us Securities & Exchange Commission for FY98 Also Encl1999-04-21021 April 1999 Forwards 1998 Annual Rept for Firstenergy Corp, for Perry Nuclear Power Plant & Davis-Besse Nuclear Power Station.Form 10-K Annual Rept to Us Securities & Exchange Commission for FY98 Also Encl ML20206B8831999-04-17017 April 1999 Forwards 1634 Repts Re Results of Monitoring Provided to Individuals at Davis-Besse Nuclear Power Station During 1998,per 10CFR20.2206.Without Repts ML20205K5641999-04-0707 April 1999 Forwards Response to NRC 980415 RAI Re GL 96-06, Assurance of Equipment Operability & Ci During Design-Basis Accident Conditions. Rept FAI/98-126, Waterhammer Phenomena in Containment Air Cooler Swss, Encl ML20205K3871999-04-0707 April 1999 Forwards Copy of Application of Ceic,Oec,Ppc & Teco to FERC, Proposing to Transfer Jurisdictional Transmission Facilities of Firstenergy Operating Companies to American Transmission Sys,Inc.With One Oversize Drawing ML20205J1171999-03-29029 March 1999 Forwards Rev 1 to BAW-2325, Response to RAI Re RPV Integrity, Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity. Rev Includes Corrected Values in Calculations PY-CEI-NRR-2377, Submits Decommissioning Repts for Bvps,Units 1 & 2,Davis- Besse Nuclear Power Station,Unit 1 & Perry Nuclear Power Plant,Unit 1,per 10CFR50.75(f)(1)1999-03-29029 March 1999 Submits Decommissioning Repts for Bvps,Units 1 & 2,Davis- Besse Nuclear Power Station,Unit 1 & Perry Nuclear Power Plant,Unit 1,per 10CFR50.75(f)(1) ML20205F5961999-03-27027 March 1999 Forwards Comments on Preliminary Accident Sequence Percursor (ASP) Analysis of 980624 Operational Event at Dbnps,Unit 1, as Transmitted by NRC Ltr ML20205D4791999-03-26026 March 1999 Forwards Rept Submitting Results of SG Tube ISI Conducted in Apr 1998.Rept Includes Description of Number & Extent of Tubes Inspected,Location & Percent wall-thickness Penetration for Each Indication of Imperfection ML20205L2031999-03-26026 March 1999 Submits Correction to Dose History of Tj Chambers.Dose Records During 1980-1997 Were Incorrectly Recorded Using Wrong Social Security Number.Nrc Form 5 Not Encl ML20205C7371999-03-25025 March 1999 Certifies That Dbnps,Unit 1,plant-referenced Simulator Continues to Meet Requirements of 10CFR55.45(b) for Simulator Facility Consisting Solely of plant-referenced Simulator.Acceptance Test Program & Test Schedule,Encl ML20205E3551999-03-19019 March 1999 Requests That Proposed Changes to TS 6.8.4.d.2 & TS 6.8.4.d.7 Be Withdrawn from LAR Previously Submitted to NRC ML20204J6361999-03-17017 March 1999 Forwards Firstenergy Corp Annual Rept for 1998 & 1999 Internal Cash Flow Projection as Evidence of Util Guarantee of Retrospective Premiums Which May Be Served Against Facilities PY-CEI-NRR-2375, Forwards List That Details Util Insurers,Policy Numbers & Coverage Limits for Two Power Plants,Per Requirements of 10CFR50.54(w)(3) Re Reporting of Property Insurance Coverage1999-03-15015 March 1999 Forwards List That Details Util Insurers,Policy Numbers & Coverage Limits for Two Power Plants,Per Requirements of 10CFR50.54(w)(3) Re Reporting of Property Insurance Coverage ML20204E6821999-03-12012 March 1999 Requests That Listed Changes Be Made to NRC Document Svc List for Davis-Besse Nuclear Power Station,Unit 1 1999-09-09
[Table view] Category:UTILITY TO NRC
MONTHYEARML20065D0491990-09-14014 September 1990 Forwards Operator & Senior Operator Licensing Exam Ref Matl for Exam Scheduled for Wk of 901112,per 900607 Request ML20065D4951990-09-14014 September 1990 Forwards Updated Exam Schedule for Facility,In Response to Generic Ltr 90-07, Operator Licensing Natl Exam Schedule ML20059K4681990-09-14014 September 1990 Provides Supplemental Info Re Emergency Response Data Sys (Erds).Data Transmitted by Util ERDS Will Have Quality Tag of 4 & Point Identification for ERDS Renamed ML20059G2341990-09-10010 September 1990 Provides Response to Request for Addl Info Re Interpretation of Tech Spec 3/4.7.10, Fire Barriers. Interpretation Is Implemented & Unnecessary Compensatory Measures Removed.List of Fire Barriers Inspected on One Side Only Encl ML20059G4961990-09-0606 September 1990 Submits Voluntary Rept of Svc Water HX Testing During Sixth Refueling Outage.Expected Flow Rates Not Achieved.Periodic Tests Developed to Check Efficiency of Containment Air Coolers ML20064A6271990-09-0606 September 1990 Requests That Requirement Date for Installation & Testing of Alternate Ac Power Source & Compliance w/10CFR50.63 Be Deferred Until Completion of Eighth Refueling Outage ML20028G8611990-08-28028 August 1990 Forwards Davis Besse Nuclear Power Station Semiannual Rept: Effluent & Waste Disposal,Jan-June 1990. ML20059D4121990-08-28028 August 1990 Forwards Second 10-Yr Interval Pump & Valve Inservice Testing Program ML20059D5521990-08-24024 August 1990 Forwards Semiannual Fitness for Duty Rept for Jan-June 1990 ML20059B5291990-08-23023 August 1990 Forwards Updated Fracture Mechanics Analysis of Hpi/Makeup Nozzle,Per 900510 Meeting W/Nrc.Util Believes That Addl Analysis to Assess Structural Integrity of Nozzle Using More Conservative Fracture Model Supports Previous Analysis ML20058Q3911990-08-16016 August 1990 Requests NRC Concurrence on Encl Interpretation & Technical Justification of Tech Spec 3/4.7.10, Fire Barriers ML20058P7801990-08-10010 August 1990 Advises of Intentions to Revise Testing Requirements for Fire Protection Portable Detection Sys at Plant & Functional Testing of auto-dialer & Telephone Line Subsys from Daily to Weekly Testing ML20063P9981990-08-0909 August 1990 Submits Supplemental Response to Insp Rept 50-346/89-21. Util Rescinds Denial & Accepts Alleged Violation ML20056A5341990-08-0303 August 1990 Confirms Electronic Transfer of Payment of Invoice I0942 Covering Annual Fee for FY90,per 10CFR171 ML20058M7791990-08-0303 August 1990 Forwards Rev 10 to Industrial Security Plan & Rev 6 to Security Training & Qualification Plan.Revs Withheld ML20058L1821990-08-0101 August 1990 Forwards Davis-Besse Dcrdr Human Engineering Discrepancy Repts 1988 Summary Addendum 1,Vol 1, Per NRC Audit Team Request ML20056A8341990-07-23023 July 1990 Forwards Revised Monthly Operating Rept for June 1990 for Davis-Besse Nuclear Power Station Unit 1 ML20055H4601990-07-20020 July 1990 Discusses Resolution of Draft SER Open Item on Voluntary Loss of Offsite Power.Util Preparing License Amend Request Per Generic Ltrs 86-10 & 88-12 to Relocate Fire Protection Tech Specs & Update Fire Protection License Condition ML20055F9681990-07-17017 July 1990 Forwards Application for Amend to License NPF-3,adding Centerior Svc Company as Licensee in Facility Ol.Change Allows for Improved Mgt Oversight,Control & Uniformity of Nuclear Operations ML20055F8561990-07-17017 July 1990 Discusses Util Planned Activities Re Instrumented Insp Technique Testing Performed at Facility in View of to Hafa Intl.Relief Requests Being Prepared by Util for Sys on Conventional Hydrostatic Testing ML20044B3001990-07-12012 July 1990 Provides Written Confirmation of Util Electronic Transfer of Funds to NRC on 900711 in Payment of Invoice Number I1050 ML20044B1841990-07-10010 July 1990 Requests Approval of Temporary non-code Repair & Augmented Insp of Svc Water Piping,Per 900626 Telcon ML20055D9701990-06-29029 June 1990 Provides Written Confirmation of Util Electronic Transfer of Funds for Payment of Invoice 0111 Covering Insp Fees for 890326-0617 ML20043H5291990-06-14014 June 1990 Forwards Plans Re Reorganization & Combining of Engineering Assurance & Svc Program Sections ML20055C7521990-06-14014 June 1990 Responds to NRC Bulletin 89-002, Potential Stress Corrosion Cracking of Internal Preloaded Bolting in Swing Check Valves & Justification for Alternate Insp Schedule for One Valve. No Anchor Darling Swing Check Valves Installed at Plant ML20055F2261990-06-14014 June 1990 Forwards 1990 Evaluated Emergency Exercise Objectives for Exercise Scheduled for 900919 ML20043G5661990-06-14014 June 1990 Forwards Rev 9 to Industrial Security Plan.Rev Withheld (Ref 10CFR73.21) ML20043G7811990-06-12012 June 1990 Forwards Info Re Implementation of NUREG-0737,Item II.F.2, Inadequate Core Cooling Instrumentation, Per NRC 900214 Safety Evaluation.Item II.B.1 Issue Re Reactor Vessel Head Vent Also Considered to Be Closed ML20043F6091990-06-11011 June 1990 Forwards Util Comments on NRC Insp Rept 50-346/90-12, Per 900601 Enforcement Conference Re Core Support Assembly Movement & Refueling Canal Draindown.Refueling Canal Draindown Procedure Provides Specific Draining Instructions ML20043E1301990-06-0101 June 1990 Withdraws 870831 & 890613 Applications to Amend License NPF-3.Changes Requested Addressed by Issuance of Amend 147 or Can Now Be Made as Change to Updated SAR Under 10CFR50.59 ML20043D5601990-05-31031 May 1990 Forwards Application for Amend to License NPF-3,revising Tech Spec 3/4.6.4.1, Combustible Gas Control - Hydrogen Analyzers. Request Consistent W/Nrc Guidance,Generic Ltr 83-37,dtd 831101,NUREG-0737 Tech Specs & Item II.F.1.6 ML20043D5691990-05-31031 May 1990 Forwards Application for Amend to License NPF-3,requesting Extension of Expiration Date of Section 2.H to Allow Plant Operation to Continue Approx 6 Yrs Beyond Current Expiration Date ML20043D1451990-05-31031 May 1990 Forwards Rev 11 to Updated SAR for Unit 1.Rev Updates Table 6.2-23 Re Containment Vessel Isolation Valve Arrangements ML20043D1621990-05-29029 May 1990 Documents Util Understanding of NRC Interpretation of Plant Tech Spec 3.7.9.1,Action b.2 Re Fire Suppression Water Sys, Per 891206 Telcon.Nrc Considered Electric Fire Pump Operable Provided Operator Stationed to Open Closed Discharge Valve ML20043C2331990-05-25025 May 1990 Forwards Summary of 900510 Meeting W/B&W & NRC in Rockville, MD Re Hpi/Makeup Nozzle & Thermal Sleeve Program.List of Attendees & Meeting Handout Encl ML20043B1701990-05-18018 May 1990 Forwards Revised Exemption Request from 10CFR50,Section III.G.2,App R for Fire Areas a & B,Adding Description of Specific Limited Combustibles That Exist Between Redundant Safe Shutdown Components in Fire Area a ML20043A5441990-05-16016 May 1990 Discusses Status of Safety & Performance Improvement Program Portion of B&W Owners Group EOP Review Project ML20043A2311990-05-11011 May 1990 Responds to Violation Noted in Insp Rept 50-346/90-08. Corrective Actions:Results of Analysis of Radiological Environ Samples & Radiation Measurements Included in 1989 Annual Radiological Environ Operating Rept ML20043A4901990-05-10010 May 1990 Forwards Summary of Differences Between Rev 5 to Compliance Assessment Rept & Rev 1 to Fire Area Optimization,Fire Hazards Safe Shutdown Evaluation, Vols 1-3.Rept Demonstrates Compliance W/Kaowool Wrap Removal ML20042F9801990-05-0404 May 1990 Provides Written Confirmation of Util Electronic Transfer of Payment of Invoice Number 10716 to Cover Third Quarterly Installment of Annual Fee for FY90 ML20042F5781990-05-0303 May 1990 Provides Status of Hpi/Makeup Nozzle & Thermal Sleeve Program.Nrc Approval Requested for Operation of Cycle 7 & Beyond Based on Program Results.Visual Insp of Thermal Sleeve Identified No Thermal Fatique Indications ML20042F0951990-04-30030 April 1990 Responds to Violations Noted in Insp Rept 50-346/90-02. Corrective Actions:Maint Technician Involved in Tagging Violation Counseled on Importance of Procedure Adherence W/ Regard to Personnel Safety ML20042F0841990-04-27027 April 1990 Responds to Violations Noted in Insp Rept 50-346/89-201 for Interfacing Sys LOCA Audit on 891030-1130.Corrective Actions:Plant Startup Procedure Will Be Revised Prior to Restart from Sixth Refueling Outage ML20042E7311990-04-27027 April 1990 Forwards Application for Amend to License NPF-3,deleting 800305 Order Requiring Implementation of Specific Training Requirements Which Have Since Been Superseded by INPO Accredited Training Program ML20042F1961990-04-27027 April 1990 Informs of Adoption of Reorganization Plan Re Plants on 900424.Reorganization Will Make No Changes in Technical or Financial Qualifications for Plants.Application for Amends to Licenses Adding Company as Licensee Will Be Submitted ML20043F7261990-04-20020 April 1990 Requests Exemption from 10CFR55.59(a)(2) to Permit one-time Extension of 6 Months for Reactor Operators & Senior Reactor Operators to Take NRC 1990 Requalification Exam. Operators Will Continue to Attend Training Courses ML20042E7091990-04-17017 April 1990 Forwards Annual Environ Operating Rept 1989 & Table 1 Providing Listing of Specific Requirements,Per Tech Spec 6.9.1.10 ML20012F5091990-04-0303 April 1990 Forwards Completed NRC Regulatory Impact Survey Questionnaire Sheets,Per Generic Ltr 90-01 ML20012F6001990-04-0202 April 1990 Submits Supplemental Response to Station Blackout Issues,Per NUMARC 900104 Request.Util Revises Schedule for Compliance W/Station Blackout Rule (10CFR50.63) to within 2 Yrs of SER Issuance Date ML20012E0181990-03-22022 March 1990 Forwards Application for Amend to License NPF-3,changing License Condition 2.C(4) Re Fire Protection Mods to Fire Extinguishers,Fire Doors,Fire Barriers,Fire Proofing,Fire Detection/Suppression & Emergency Lighting 1990-09-06
[Table view] |
Text
..
1 TOLEDO EDISON A Centenor Energy Company DONAU] C. SHELTON Voe PrerchbNuch (4
Docket Number 50-346 License Number NPF-3 Serial Number 1638 February 28, 1989 United Stctes Nuclear Regulatory Commission Document Control Desk Vashington, D.C. 20555 Subj ect : Plant-Specific Submittal for ATUS Implementation (10 CFR 50.62)
(TAC 59086)
Gentlemen:
The attached " Design Summary" provides the plant-specific information requested by Nuclear Regulatory Commission (NRC) letter dated August 10, 1988 (Log Number 2664: "NRC Evaluation of BV0G Generic Report - Design Requirements for DSS and AMSAC") for the Davis-Besse Nuclear Power Station.
The equipment to protect against Anticipated Transients Without Scram at Davis-Besse vill be designed based on the generic design described in Babcock and Vilcox (B&W) Document 47-1159091-00, " Design Requirements for Diverse Scram System (DSS) and ATVS Mitigation System Actuation Circuitry (AMSAC)" and the additional guidance provided by the NRC Safety Evaluation Report (SER) transmitted with the August 10, 1988 letter.
Diverse power supply requirements described in SER Sections 5.6 and 6.1 vere further clarified in an August 17, 1988 NRC/ Babcock and Wilcox Owner's Group (BV0G) meeting. In this meeting and in a subsequent NRC letter [G. Holahan (NRC) to L. C. Stalter (BV0G) dated September 7, 1988] the NRC described three acceptable options that licensees could use to resolve the power supply independence issue. Toledo Edison has selected Option 2, which requires that a power source for the DSS be provided via a non-battery backed 480-volt bus that is independent [i.e., not associated with the Reactor Trip System (RTS)]
and non-class 1E. The attachment to this letter provides an evaluation that demonstrates that for all loss of offsite power scenarios the control rods i
vill be released due to loss of voltage to the 480-volt supply to the control rod holding mechanisms. Part i of the attached " Design Summary" addresses DSS design requirements.
b0 l
5 8903130081 890228 PDR ADOCK 05000346 P PDC THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO. OHIO 43652
Docket Numb:r 50-346 License Number NPF-3
. Sefial Number 1638 Page 2 To meet the requirements of the AMSAC, Toledo Edison vill utilize the existing Steam and Feedvater Rupture Control System (SFRCS). Part 2 of the attachment to this letter provides the basis for using the SFRCS to fulfill the AMSAC )
function since SFRCS performs the same. function. Part 3 of the attachment j includes an evaluation to demonstrate that common mode failures vill not !
propagate through the power supplies and disable both SFRCS and the RTS since SFRCS is partially powered through the same essential 120 VAC busses as the RTS. I Toledo Edison plans to design and install the ATUS systems by the end of the 1 Sixth Refueling Outage, which is currently scheduled to begin in February 1990. Toledo Edison is prepared to further discuss the attached design details with the NRC at a mutually convenient time. If you have any questions concerning this matter, please contact Mr. R. W. Schrauder, Nuclear Licensing Manager, at (419) 249-2366.
Very trul ours, EBS/dlm Attachments cc: P. M. Byron, DB-1 NRC Resident Inspector A. B. Davis, Regional Administrator, NRC Region III T. V. Vambach, DB-1 NRC Senior Project Manager l
~
Docket Numb 2r 50-346 Licensa Numbar NPP-3 Serial Number 1638
. Attachment Page 1 DESIGN
SUMMARY
Toledo Edison's conceptual design for equipment required to address the Anticipated Transient Without Scram (ATVS) rule relative to the design requirements specified in Section 5 of the NRC's Safety Evaluation Report (as transmitted by Reference 1 dated August 10, 1988) is provided in Parts 1, 2, and 3 below. Part 1 provides a description of the Diverse Scram System (DSS). Part 2 includes the basis and justification for using the existing Steam and Feedvater Rupture Control System (SFRCS) to satisfy the ATVS Mitigation System Actuation Circuitry (AMSAC) function. Part 3 provides an evaluation to demonstrate that common mode failures vill not propagate through the power supplies and disable both SFRCS and the .8.
Part 1 DESCRIPTION OF THE DIVERSE SCRAM SYSTEM (DSS)
A conceptual functional diagram of Davis-Besse's proposed Diverse Scram System (DSS) is provided in Figure 1. The DSS will consist of two channels of instrumentation, each having a reactor coolant pressure input to a bistable with a trip setpoint of approximately 2450 psig. The bistable output will be a contact closure that energizes new DSS relays in the Control Rod Drive Control System (CRDCS) cabinets. The DSS relay contacts will open programmer lamp circuits causing de-gating of one group of Silicon Controlled Rectifiers (SCR). A coincident second DSS channel actuation vill de-gate a second group of SCRs, thus removing the power from the Control Rod Drive Mechanisms and allowing the control rods to drop into the reactor core. Beth CRDCS groups' (channels "A" and "B") SCRs must de-energize to release the control rods.
Control Room indication of a trip initiated by DSS will be through an alarm.
In addition, all " rod bottom" lights will be lit on the Position Indication Panel in the Control Room.
The system vill be designed to be testable with the reactor on-line. While one channel is being tested, a DSS bypass will be provided to prevent an inadvertent reactor trip. A means to alert the operators that a DSS channel is in a bypass or tripped condition vill be provided.
DESIGN REQUIREMENTS FOR THE DSS This section presents the specific design requirements Toledo Edison plans to use to fulfill the design and implementation criteria for the Diverse Scram System. For convenienet, the paragraphs are numbered to coincide with comparable paragraphs of the NRC's Safety Evaluation Report. The generic design requirements are also addressed. Most of the generic design requirements have been addressed, at least in part, by the Babcock and Wilcox Owners Group (BV0G) " Design Requirements for DSS and AMSAC" document. Since Toledo Edison has not completed the final design for the DSS, design details, such as component location and specific vendors, have not yet been finalized.
Dockat Numb:r 50-346 ;
Licznsa Numb r NPF-3 )
Serial Number 1638 1
, Attachment l Page 2 1 5.1 DIVERSITY FROM THE EXISTING REACTOR TRIP SYSTEM The diversity of the DSS Equipment from the existing Reactor Trip System (RTS) vill include all signal conditioners, bistables, logic channels, logic power supplies, and the relays used to de-gate the silicon controlled rectifiers.
Sensors: The sensors that will be used for the DSS are independent of the existing sensors that input to the Reactor Protection System (RPS) equipment presently used at Davis-Besse Unit 1 to provide the reactor trip. The sensors that vill be used to provide the input to the DSS are Reactor Coolant Pressure Transmitters PT6365B and PT6365A (Rosemount Model 1154 transmitters designed and installed to be qualified to meet the post accident conditions for Davis-Besse Unit 1). The range of each transmitter is 0 to 3000 psig.
In addition to being independent of the Reactor Trip System (RTS),
the transmitters being utilized for the DSS are a different model than those used by the RTS. Rosemount Model 1152 transmitters are used in the RTS to measure reactor coolant pressure. The ATVS rule l (10CFR50.62) specifically excludes diverse design or diverse manufacturer requirements for the sensors.
i Signal Conditioners: The transmitter output signal (4-20 milliamps) is provided directly to the bistable. No signal conditioners are required. ,
Bistables: The bistables used for the DSS vill be from a manufacturer other than Bailey Controls Company (manufacturer of the l bistables used in the RTS).
Logic Channels: The DSS logic channels vill not use equipment manufactured by Bailey Controls Company (manufacturer of the logic ]
j channels used in the RTS).
Logic Power Supplies: The only DSS logic is the bistable used to compare the input signal representative of the RCS pressure to the internal setpoint to provide a contact closure to initiate a channel trip. Any power supply used for this bistable vill be of a different manufacturer than Bailey Controls Company (manufacturer of the power supplies used in the RTS). ,
Relays: The DSS relays used to de-gate the SCRs vill provide a mechanism for removing power from the Control Rod Drive Mechanisms that is diverse from the four reactor trip breakers used by the RTS to initiate the reactor trip. The RTS also de-gates the SCRs. The relays used for the DSS will be different from those used by the RTS.
5.2 ELECTRICAL INDEPENDENCE FROM THE EXISTING RTS
( The DSS will be electrically independent from the sensor output up to and including the relays that de-gate the SCRs in the CRDCS. The DSS will be installed as a non safety-related system and, as such, will be separate from the existing safety-related RTS circuits and components.
l l
Docket Numbrr 50-346 Liesnsa Number NPF-3 Serial Number 1638
' Attachment Page 3 Isolation of the sensor signal vill be provided through a Foxboro 2AO-VAI CUSTOM (ECEP 9206) STYLE A CS-N/SRC VOLTAGE-TO-CURRENT CONVERTER. The Foxboro Company Corporate Quality Assurance Laboratory Type Test Report (00AAB44 Rev A), which is proprietary to Foxboro, is available at Davis-Besse for NRC review. The report provides the validation of this isolation capability of the voltage to current converter, and includes the additional information requested by Appendix A of the SER. (See 5.6 for description of the power supply for the DSS.)
The Davis-Besse RTS utilizes four safety grade reactor trip breakers to provide the trip function, as shown in Figure 3. In addition, two of the reactor trip breakers contain " electronic trip relays" which trip the CRDCS "A" and "B" SCRs. The 1E to non-1E isolation is provided by the coil to contact isolation of the electronic trip relay as shown in Figure 4.
The DSS trip contacts are in the non-1E portion of the electronic trip circuit in the CRDCS. Therefore, requirements for Class 1E isolation of this portion of the DSS do not apply.
5.3 PHYSICAL SEPARATION FROM EXISTING RTS The DSS at Davis-Besse vill meet the BV0G requirements for physical separation from the RTS.
5.4 ENVIRONMENTAL QUALIFICATION The equipment vill be purchased and installed to meet the requirements for the environmental conditions expected in the locations selected for installation of DSS components.
5.5 0UALITY ASSURANCE FOR TEST, MAINTENANCE, AND SURVEILLANCE The DSS vill be controlled in accordance with the general requirements of the Toledo Edison Quality Assurance Program in a manner similar to that currently used for other non-safety related syatems. Testing, maintenance, and any specified surveillance vill be conducted and controlled in accordance with approved procedures. Collectively, the controls applied to the DSS vill meet or exceed the " Quality Assurance Guidance for ATVS Equipment That Is Not Safety Related," as set forth in Generic Letter 85-06.
5.6 SAFETY RELATED (1E) POWER SUPPLIES The power source for the DSS is not associated with the power sources (i.e.,
batteries) that are used by the RTS. The power source for the DSS bistables (logic) vill be via a separate transformer directly from off-site power that is not backed up by an emergency diesel generator. (See Figure 2, " Power Arrangement DSS Simplified Diagram")
l
'Dockat Numbar 50-346 Licznsa Numbar NPF-3 Serial Number 1638
, Attachment Page 4 The DSS function vill be fulfilled upon loss of off-site power as follows:
Coincident with the loss of the station main turbine generator, busses E2 and F2 vill be de-energized, resulting in interruption of power to each of the control rod drive mechanism groups. This feed is via bus E2 and F2 through the reactor trip breakers to the control rod drive control system.
Therefore, a loss of power from both E2 and F2 vould result in release of all control rods (See Figure 3, " Detailed Control Rod Group Power Arrangement").
With this arrangement, should either bus E2 or F2 be de-energized, either CRDCS "A" or "B" channel SCRs for each of the CRDHs vould lose power.
Each of the regulating and safety rod groups have two power sources. Each power source supplies one of the two CRDCS channels needed to hold the CRDM engaged. The two SCRs normally hold the roller nuts engaged. One energized SCR is sufficient to maintain engagement preventing a trip of the rod. If either E2 or F2 was energized providing power to one SCR, there would be power available for the associated DSS bistable to perform its intended function.
In summary, with total loss of power to the DSS the reactor is tripped without relying on the RTS. With loss of power to one channel of the DSS, the remaining channel of the DSS can trip the reactor without relying on the RTS.
5.7 TESTABILITY AT POVER The DSS will be testable with the reactor at power from the sensor output up to and including the interruption of power to the programmer lamp in the CRDCS. Testing vill de-gate either the "A" or "B" channel of power to the CRDMs.
Testing vill be performed by placing the opposite channel of DSS into the bypass condition, which will prevent an inadvertent trip, then introducing a test signal into the DSS channel being tested (Figure 1). Adjusting the test trip input to the trip setpoint vill turn off the associated programmer lamps and generate a programmer fault indication on the CRDCS panel in the control room.
The sensors that vill be used for input to the DSS will also be used for indication in the Control Room. The Control Room Operators will be able to readily determine sensor functionality.
5.8 INADVERTENT ACTUATION Inadvertent actuation of the DSS will be prevented by using a two-out-of-two channel logic to initiate a reactor trip. This meets the B&W generic design criteria as noted in the SER.
Dockat Numb 2r 50-346 License Number NPF-3 Serial Number 1638
. Att'achment Page 5
)
5.9 MAINTENANCE BYPASSES l The DSS design vill permit bypassing to allow maintenance, repair, test, or calibration during power operation in order to preclude inadvertent actuation of protective actions at the system level. This vill be accomplished by the use of the test switch, as shown in Figure 1, under key lock control. When the switch is placed in the test position, an indication in the Control Room will annunciate that the DSS is disabled. Access to the test switch vill be administrative 1y controlled by the Shift Supervisor.
5.10 OPERATING BYPASSES The DSS will trip the reactor on high RCS pressure. The design of the DSS does not include any operating bypasses, since there are no normal operating conditions where the RCS pressure is expected to exceed the trip setpoint.
5.11 INDICATION OF BYPASSES The test switch for the DSS will have an annunciator output to the control room annunciator panel to continuously indicate that the DSS has been disabled. When the test switch is returned to the normal position, the annunciator condition vill be cleared.
5.12 MEANS FOR BYPASSING See Section 5.9.
5.13 COMPLETION OF PROTECTIVE ACTION The DSS trip will result in a " fault" condition in the CRDCS which seals in per the CRDCS logic design. Reset of this trip condition vill require deliberate operator action at the Diamond Control Panel, and vill not be possible until the programmer lamp current is restored. The Diamond Control Panel is mounted on the Main Control Panel in the Control Room.
5.14 INFORMATION READ 0UT The DSS design vill provide the operator complete, accurate, and timely information concerning system status. If any channel is in the tripped condition, the status will be provided to the operator via the plant computer.
In addition, the operator vill receive a CRDCS system fault annunciator alarm along with a programmer lamp fault light on the Diamond Control Panel in the main control room. The high pressure condition vill also be indicated on the Post Accident Monitoring Panel in the main control room.
The alarmed conditions will clear when the tripped condition is reset by the operator. Indications of test, and maintenance are as previously described in Section 5.9.
i Docket Numb 2r 50-346 Licensa Number NPF-3 Serial Number 1638
. Attachment i Page 6 ]
l 5.15 SAFETY RELATED INTERFACES As shown in Figure 3, the RPS input is via the undervoltage device (UVD) relays in the CRD trip breakers. The function of these breakers is to interrupt power to the CRDCS transformers. This removes power from the CRDCS SCRs, and the CRDMs. As shown in Figure 4, the DSS contacts, which de-gate the SCRs, are twice removed from the reactor trip breaker UVD. Thus, there vill be no direct interface between DSS and RPS. In addition, there vill be no interfaces between DSS and the Safety Features Actuation System (SFAS).
Therefore, the existing RPS and SFAS continue to meet all applicable safety criteria.
i 5.16 TECHNICAL SPECIFICATIONS The technical specifications requirements for surveillance and testing of the DSS will be addressed by the Technical Specification Improvement Program (TSIP). The NRC previously acknowledged that this was a reasonable position during its August 17, 1988, meeting with the B&W Owners Group. Toledo Edison vill test, maintain, and perform surveillance as described in our response to SER Section 5.5.
Dockst Numb r 50-346
'Licensa Numbzr NPF-3 Serial Number 1638
. Attachment Page 7 l-Part 2 SFRCS COMPARISON TO AMSAC DESIGN REQUIREMENTS The AMSAC design requirements in 10CFR 50.62 " Requirements for Reduction of Risk From ATVS Events for Light-Vater-Cooled Nuclear Power Plants" are specified as follows:
"Each pressurized water reactor must have equipment from sensor output to final actuation device that is diverse from the reactor trip system to automatically initiate the auxiliary feedvater system and initiate a turbine trip under conditions indicative of an ATVS. This equipment must be designed to perform its function in a reliable manner and be independent (from sensor output to the final actuation device) from the existing reactor trip system."
The existing Steam and Feedvater Rupture Control System (SFRCS) installed at Davis-Besse satisfies this requirement. SFRCS is a Class-1E system which actuates auxiliary feedvater (AFW) and initiates a turbine trip for the following conditions:
Lov steam generator level High steam generator level Lov steam generator pressure High steam generator to main feedvater differential pressure Loss of four reactor coolant pumps As requested by Reference 1, a discussion of the method of detecting total loss of feedvater flo. is provided below.
Following a loss of main feedvater event, a lov steam generator level (10 inches collapsed liquid level above the lover tube sheet) vill initiate SFRCS which vill actuate the AFV system and trip the main turbine. A Davis-Besse specific ATVS analysis was recently performed by B&W (Reference 3) to determine the peak RCS pressure for an SFRCS initiation using the existing lov steam generator level signal. This new analysis was performed to account for the numerous modifications tc th- SFRCS and AFV systems which have been implemented since the Davis-Besse June 9, 1985 event which affect the previous BV0G ATVS analysis. The analysis was performed to demonstrate the acceptability of using the existing SFRCS to fulfill the AMSAC function. The analysis shows that SFRCS initiation on lov steam generator level occurs approximately 27 seconds following the loss of feedvater event. Auxiliary 1 Feedvater flow is established, in either case, approximately 30 seconds following SFRCS initiation due to auxiliary feedpump turbine acceleration time. The resultant peak RCS pressure for this case is 4103 psia.
The results of the analysis demonstrate that the peak pressure falls within the range (3621 psia to 4190 psia) previously identified for the B&W plants in the earlier BV0G ATVS analysis. This range of pressures has been previously evaluated by the NRC (Reference 4) and found acceptable. Additionally, B&W evaluated (Reference 5) and found acceptable for an ATVS event, peak pressures up to 4300 psia at Davis >Besse.
Docket Numbar 50-346
' License Numbar NPF-3 Serial Number 1638
, Attachment Page 8 Therefore, the existing SFRCS design satisfies the requirements of the ATVS rule for AMSAC. Since SFRCS is partially powered from the same inverters as.
the RTS, an analysis is required to show that faults will not propagate
'through the power supplies and disable both SFRCS and the RTS. This andvsis has been completed (See Part 3). The analysis concludes that no credible failures can propagate through the common power supplies and disable both SFRCS and the RTS.
Part 3 of this attachment addresses the design requirements associated with i
diversity from existing RPS and safety-related (1E) power supplies. The l remaining design requirements specified in Section 5 of the SER are those l
required for a Class-1E System. As noted above, SFRCS is a Class-1E system.
l- Therefore, an item by item comparison for SFRCS is not provided.
l l
I Docket Number 50-346 License Numbsr NPF-3 Serial Number 1638
, Attachment Page 9 Part 3 - SFRCS POVER SUPPLY CONFIGURATION AND OPERATIONAL REQUIREMENTS SFRCS Power Supply Configura" on Each SFRCS Logic Channel is powered from a separate 120 VAC 1E vital bus (Figure 5). Two Logic Channels (one in each Actuation Channel) are powered from battery backed inverters which also provide power to two RPS channels.
The remaining Logic Channels are powered from Emergency Diesel Generator backed sources which are independent of the RPS power supplies.
SFRCS System Power Specifications The SFRCS system voltage and frequency specifications for vitrl (logic) AC power are:
Voltage 120 VAC i 10%
Frequency 60 Hz 1 2%
The incoming 120 VAC is converted to 28 or 48 VDC to power the SFRCS logic components by internal power supplies. The internal DC Logic power supplies have a transformed input power specification of:
28 VDC: 22.55 VAC 1 2.82 VAC (12.5%) @ 60 Hz 1 3 Hz (5%)
48 VDC: 39.78 VAC 1 4.8 VAC (12%) @ 60 Hz 1 3 Hz (5%)
Loss Of Power Effects On SFRCS The SFRCS is designed as a Class-1E system. Failure of one of the 1E vital busses to zero volts vill result in the system reverting to a one-out-of-one trip configuration for the actuation channel affected. Failure of both 1E vital buses on a single actuation channel vill result in a turbine trip and initiation of respective Auxiliary Feedvater train due to the de-energize-to-trip design of the SFRCS.
On a Loss of Offsite Power, power to all four Reactor Coolant Pumps is lost.
This results in actuation of SFRCS which trips the turbine and initiates Auxiliary Feedvater.
SFRCS Operation Vith An Overvoltage Or Undervoltage Condition The SFRCS power supplies are non-regulated and simply rectify and filter the incoming AC. Because the power supply DC output voltage follows the incoming AC voltages, the power supplies vill not limit an overvoltage or undervoltage condition. The limiting undervoltage components are the opto-isolators used in the field buffers and the relay drivers. The voltage requirement for the opto-isolators is approximately 12 VDC. Based upon a 28 VDC normal output from the power supplies, the devices will still provide their intended function with a 57% decrease in voltage. The limiting overvoltage components are the capacitors in the 48 VDC and 28 VDC power supplies. The capacitors
Docket Number 50-346 License Number NPF-3 Serial Number 1638 Atfachment Page 10 have a vendor approved operating voltage which is approximately 12% above the actual power supply normal operating voltage. The capacitors have a maximum surge rating of approximately 75% above power supply normal operating voltage.
A failure of the capacitors will depend on the amount of time and percentage above these vendor approved voltages. Even with a capacitor failure, since the SFRCS is a de-energize to trip system, the power supply failure vill only revert the SFRCS to a one-out-of-one trip for the affected actuation channel.
5FRCS Operation With An Overfrequency Or Underfrequency Condition There is no effect on the SFRCS from an overfrequency or underfrequency conditions. The only result will be an increase or decrease in input impedance to the transformers. This has no effect due to the sizing of the transformers and the small normal load required by the SFRCS components.
Vital Bus Power Supplies - System Operation l Inverter Output Specifications Output Voltage 118 VAC i 1%
Output Frequency 60 Hz i 1%
Each inverter is supplied with 125 VDC from a station battery and 3-phase rectifier povered from a 480 VAC diesel backed bus. The 480 VAC is rectified and then diode auctioneered with the 125 VDC from the station battery. This DC output from the diode auctioneering circuit is the input to the inverters.
During normal operation the inverter frequency is synchronized to an AC i source. On loss of the AC reference voltage, the inverter frequency is controlled by an internal oscillator which has a'specified frequency of 60 Hz i i 1/2%. Thus, loss of either the station battery or the 480 volt bus will not cause the loss of the inverter output. j Conclusions j
- Loss of Offsite Power or loss of the AC power supplies to the SFRCS has no effeet since the SFRCS is a fail-safe system (de-energize to trip). The loss of power results in a turbine trip and initiation of auxiliary feedvater.
- Undervoltage is not considered a credible failure since the voltage change required for an undervoltage is >50% and as noted above, system functionality vill still be maintained for a 57% decrease in voltage.
- Overvoltage has no detrimental effect upon the system until a power supply capacitor failure occurs. At that time, the power supply fails and the SFRCS is reverted to a one-out-of-one trip requirement for the affected actuation channel.
- Overfrequency and underfrequency have no effect on the operation of the system due to the sizing of the transformers and small normal load required by the SFRCS components.
l l
I Docket Number 50-346 License Number NPF-3 Serial Number 1638 Attachment Page 11
- The failure of one channel in either SFRCS or the RTS cannot prevent either system from performing its design function.
l[ i It is also TE's position that SFRCS is not part of the Reactor Trip System, that the SFRCS equipment is diverse from the RTS equipment, and that there is no common failure mechanism which can prevent both systems from performing their intended function based on the following:
- Manufacturing Processes: The Bailey 880 RTS equipment and the SFRCS equipment are manufactured by two different companies (Bailey Metering Company and Consolidated Controls Corporation), at two different manufacturing facilities utilizing independent manufacturing procedures.
- Principle of Operations: The SFRCS is primarily digital in operation while the RTS is primarily an analog system.
- System Interfaces: The SFRCS uses primarily optical isolation technology for its interfaces while the RTS systems uses relay contacts and operational amplifiers.
' Docket Number 50-346 License Number NPF-3 Serial Number 1638 Attachment Page 12 References
[1]. Letter to Mr. Donald C. Shelton (Toledo Edison) from Albert V. DeAgazio (NRC) dated August 10, 1988; NRC Evaluation of BWOG Generic Report -
" Design Requirements for DSS and AMSAC".
[2]. Letter to Mr. L. C. Stalter (Chairman of the BV0G ATVS Committee) from Gary Holahan (NRC Staff), dated September 7, 1988; August 17, 1988, B&V/NRC ATVS Meeting
[3]. B&W Calculation 32-117357-00 "DB-1 LOFV ATVS analysis", dated February 28, 1989.
[4]. Reference 4 of the NRC SER dated February 1988, Safety Evaluation of
} Topical Report (B&V Document 47-1159091-00) " Design Requirements for DSS (Diverse Scram System) and AMSAC (ATVS Mitigation System Actuation Circuitry)"
[5]. B&W Report 12-1174341-00 "DB-1 ATVS Justification", dated February 9, 1989.
DAVIS BESSE UNIT 1
" RCS1 RCS2 '
Pressure, , Pressure, ISO ISO 1 r 1
r TEST input ** ' *< TEST input i i f f
120 VAC from YAR > < 120 VAC from YBR BIST BLE BISTABLE 09 -
- To ANNUNCIATION Open when DSS 2 is in " TEST" ef 7 ,
if'm Open when DSS 1 is in " TEST"
' t y To To CRDCS CRDCS "B" SCR's "A" SCR's DIVERSE SCRAM SYSTEM FUNCTIONAL DIAGRAM FIGURE 1
1 l
J
( .-
'o .
S S
O g l
4 R Y M L E L F AR E I
F F D E
N N
L E f I
I I
T C
A P @ U D
A GW I
SF S ,
S l E C -
E R R N l A
V -
D 5
T R
l 2 D
l R
E T
R 2
0 1
- }
E t
m C E i
C O V j M
s f V N A t l I
! R u s 2 -
C 1
- S E :.l' 1
- S -
F C
C I
- ! R E
- V -
M 2 - - I D
L A 0 2
= '
I T Y - :
N L - 2 E E -
S S
E L_ - C N
A P
O -
V l V C E -
0 5 A -
8 R 2 R V A -
4 0 E 1
+ E 2 -
T 1 -
5 l R -
E l P
2 E
E V
1 Q R D N I
5 l -
I E I
- M F
T I I
I T ]
- TA I C E
R O -
NR N R u
S N
- EG U
l
[
E S
M EI A
E
- GD 2 S
l R
3 Y
]
R
- ND E S
EI L
F u O
S N
- A RIE R F
I N M E RI GFU E T C P A
E T [
S -
ALP R B 1 E
C l
n E
R N I
l R
C A
V h S 1 R
D EM l
C E E 0 S -
S M c T 2
P I
L 5 a B R 1
I
]
R WS I
A m C I E R O V I T
N c O V
V N I o R T S N OS A - P S E I I I E
S s O -
S D
l S 2 T -
D E V
1 C
A
[
0 8
4 I
E R
1 D -
1 Y
L E
I L_
___ C D
V s
t F
N A
P S C _
E R e A -
D t. V -
5 u 5 0 -
2 -
1
] ~
t
- a c
l R
P1 I
I R O
~
~
i u E D S -
t I
R IN B
u N I I T
I E
u I C [
S E
l R
C D A 2 E V E l E L 0 L l 8M 4 OS RR E
IT f - C A
VM CY 2
1 TE NI F OIT CC S NE E T
E OR l
C r I
C u T C
A 2 I
t S (D VF ,
0 - C 8M 4
A Vm
. 0y 2
1
,I l l '1! lil{i
m DAVIS BESSE UNIT 1 i 13.8 KV BUS A 13.8 KV BUS B l 1 i l i i WW- wW i i mm m% e i i 8
1 I i l 480VBUS E2 480V BUS F2 l i i I l
' i i wW wW ,
i mm mm i 8 i l 120 VAC PANELYAR 1 120VAC PANELYBR l i-8 I i
i..__ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ . . . . _PO_WE_R_S_O_URQES.
_ _ _ _ __________________. .______)
i RPS1(B) RPS 2 (A) e i
8 l 3 UV RPS 3 (D) [3 UV RPS 4(C) !
i i i 1f i l' ? Uv ") yl REA i____________ _ _ _ _CTOR TRIP SYSTEM_
_____________ _ _ _ _ _ _ _ _ _i _ _ _ _ _ '
mm mm l l
, i 1
i 5
l i 100V AC 30 'B' SCR SUPPLIES 100V AC 30 'A' i 9
i r ,e i r ,
DSS 1 ' 8 DSS 2
< BISTABLE, l ( l <BISTABLg U !
l 1 2 3 4 5 6 7 8 i x i
' I I I I I I l l SCR Gate Drives e i .
8 I
_ _ _ _ _ _ _ _ C_O_ N_T_R_O_L _RO_ D_ _D_RI_V_E _C.O. .N. .TR.O_L_S_Y_ST_EM_ _ _ _ _ _
DETAILED CONTROL ROD GROUP l
POWER ARRANGEMENT FIGURE 3 i
7 __ ___
Y- ,.
120vAC [Y3(D), or Y4(C)]' DAVIS BESSE UNIT 1
- RPS (C or D]
o Manuai Trip Switches t>
0
- ARTS IE to non IE isolation 7_____. .___ _ ___. ______,
-a , 't i 8 8 <
1 UVD K2 l :L:K2 :
i i I , I I i l REACTOR TRIP l l
' Egg ry_Crge , _ _ _ , _ . ,___ _ _i t
l' 120 VAC '
', iI s
8 8 KI A TIIROUGli K7A RI1AYS 3
' CORRESPOND TO GROUPS 1 7 l i
I i
8 e
8 e
8 KIA l II + 'H e (Yd t 8
i 8 GROUP 1 PROGRAMMER l s
A1 f g -
LAMP I i 100VAC I
s 1
I
' O l GROUP 1 GROUF SUPPLY ,
l I a e, GATE DRIVE C f M ,
l GP 2 PROGRAMMER LAMP 'A'(T*) l 1
GP 3 PROGRAMMER LAMP *A* (T*) l l GP 4 PROGRAMMER LAMP *A* (T*)
GP 5 PROGRAMMER LAMP *A* (T*)
l' GP 6 PROGRAMMER LAMP *A* (T*) l l GP 7 PROGRAMMER LAMP *A* (T*)
i i I i
CONTROLROD DRIVE CONTROL SYSTEM i l .. dss 8120 VAC t
{ BISTABLE l CRDM i
DIVIRSE SCRAM SYS'IDi l DIVERSE SCRAM SYSTEM INTERFACE WITII RPS ELECTRONIC TRIP FIGURE 4
. _ _ _ _ . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ . _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ A
R I 2
O N
T l ]
L A R 4 R E L
E R f E Y O N M
SM-EE I
F L
E t
E S
N N DC I
1 1 i T
S E A I
A C P Y S
S H il-I E C
[ C -
R N A uL O , N 8
- R 2 R V R 8 T e l D 0 T
]
R O ' "
E N T I
EmgI IS T m T 2
1 O 0 A R E
F I I R ,
C 9 U TP O =
C C
I E
V I
1 E
R 4
P T AR WT D N I U T S C V P [
A DE" l I 1
U EP F 5 H R E
2 S 1 R ] 1 F U
B R
E T
A L
E FB"U T
G L__._
t W N NO
[NA D N P
A W E E
S 2 F H E L D r AI D 2 ON - C '
T N
Y L
A M
] N O i E A R S
S L_ - C T
A I E T
O S
T I
E I P
S A D P N U V l V C E T 0 5 A S C 8
4 R 2 R V [
A e E 0 2
I I
u 1+
I T
R 1
E
=
C l
PI 2
0 V B R N 4 l E I R
l 1 I I
I T ]
C R T
I E
R ,
O S
1 N
N l
E S
U I I
[
l E R E
3 Y .
S I RI L
E N T S I T C P A '
N E I E C
]
R E
R R N A O M B 1 I e
u l
D 1
R E
T V
0 2
r 1
M S
N EI E I I R
1 E
E S G S S U =
C C
D I
E V
T S
[
N I B V N I Y A V R G
l 5
2 I
I S R A W S
1 N
P I
R D L A I
_ T A R
I T _ R N O E
S T C
E W
1 S ]
E D A E
V 0
1 Y
r R O t
- N P i
8 R 4 O
L_ C L
E T D N [
A I V A LR E 5 PI S
E R CI EEN 2
e 1 A DG l E
c + R E
T V
0 2
=
1 l
P1 I
I R ]
R C R D E ER T E V 0 9
SE I I I B
F I
N I
l E
t I
N TO F I T E OF C [
S E
R l
D '
^E2 E L
L o w' S OS O C ,S RR R w~ A V R A
, D TE NR A E R f UY 2
OiT M fS4 1 CC N NE O TO F
OR OP -
C U C I
S
^r2 Y
S w-C ,S AR ,
D d w VD cY 2
1