ML20206C463

From kanterella
Revision as of 14:35, 11 December 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Discusses NRC Understanding Resulting from 870319 Telcon Re Draft Response to Insp Rept 50-443/86-52,including Employee'S Legal Project Intent to Conduct Addl Insp & Amplify Original Issues
ML20206C463
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 04/02/1987
From: Kane W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Tracy S
EMPLOYEE'S LEGAL PROJECT
References
NUDOCS 8704130064
Download: ML20206C463 (35)


See also: IR 05000443/1986052

Text

.

_ ,

_ _ _ _ _ _ _ _ _ - _ _ - _ _ - - _ _ _ _ _ _ _ _ _ __ _ ___ _

__

,

' .s w. '

'g Lf

. sp w ..,;.

'

'

"

APR0a n

.

- Docket' Nos.' . 50-443; 50-444' 'i

Employee's Legal Project -

. ATTN: Ms..Sharon Tracy.

.

.P.O. Box 633-

Amesbury, Massachusetts 01913

. Dear Ms. Tracy: *

s I ;p' l ,

On March 19, 1987, Mr. .J. Durr of this office contacted yodby telephone regarding ,

the." Employee's Legal Project Draft Respons,e to NRC Special Inspection No. 50-443/

86-52,"-(ELP Draft Response) which had been mailed by your organization to our

resident inspector at Seabrook. Specifically, the purpose of that telephone con- -

versation was to determine whether the ELP, Draft Response was a complete set of

allegations or a " draft" for which we would expect to. receive additional allega-

tions. We understand that the ELP Draft Response should be considered a final-

response to the special inspection (50-443/86-52) conducted by this office in

November 1986. Therefore, your response, as an enclosure to this letter, is being

.placed in the Public Document Room and is being provided to the normal distribution

list for Seabrook Station. We also understand that you intend to provide us-with '

further clarifications of some of the original set of allegations;and that you in-

tend to provide us with those clarifications during the first week of April 1987.

7

During the telephone conversation ~with Mr. Durr, he indicated our. intent to conduct

an additional inspection at Seabrook Station to further evaluate those areas where

your response appears to provide either additional or clarified information rela-

stive to that which you provided with -the original allegations and subsequent in-

.terviews. Since you stated-that, while there are no new allegations, further

amplification of the original issues is forthcoming. We again request that this

additional data.be provided to us-as soon as possible, so that we may include it

in our inspection plan. ,

{

Mr. -Durr also indicated that after the conclusion of the follow-up inspection at

Seabrook Station, relative to your further clarification of the existing concerns,  ;

we intend to propose a meeting.with you to address those concerns and any further

questions you may have relative to our inspection program of Seabrook Station con-

. struction'. We will coordinate this future meeting with you shortly after comple-

tion of our follow-up inspection.

If you believe our understanding of any of the above information is incorrect or

if you feel you cannot provide additional details and amplification of the speci-

fics of the existing allegations, as was stated by the first week in April, please

contact us as soon as possible.

Sincerely,

William F. Kane, Director

Division of Reactor Projects

8704130064 870402 A

PDR ADOCK 05000443-  ; <

f_ 0]

G PDR

V/

Il

.. . .-

_- _

_

s *e

e; 4

. Employee's Legal Project 2

q 3

Enclosure: As Stated

'

cc w/ enc 1:

Seabrook Hearing Service List ~

R. J. Harrison, President and Chief Executive Officer

Ted. C. Feigenbaum, Vice President of Engineering and Quality Programs

William B. Derrickson, Se_nior Vice President

Warren J. Hall, Regulatory Services Manager

Donald E. Moody, Station Manager

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

.NRC Resident Inspector

State of New Hampshire

.

bcc w/ encl:

Region I Docket Room (with concurrences)

Managemc6t Assistant, DRMA (w/o enc 1)

DRP Section Chief

Robert J. B' ores, DRSS

A. Cerne, SRI

T. Elsasser, 3RP

J. Durr, DRS

E. Wenzinger, DRP -

iW. Kane, DRP

A. Shropshire, 0AC

v

..

SM

gCerne/meo

%"

Elpasser

"l%

Durr h"G

pzinger

  1. /gf

) 3/30/87 QM37 $g/ T7

OFFICIAL RECORD COPY

_

'

Seabrook'1 Service Hearing List

Thomas Dignan, Esq E. Tupper Kinger, Esq.

John A. Ritscher, Esq. Assistant Attorney General

Ropes and Gray Office of Attorney General

225 Franklin Street 208 State House Annex

Boston, Massachusetts 02110 Concord, New Hampshire 03301

Mr. Bruce Beckley, Project Manager Resident Inspector

New Hampshire Yankee Seabrook Nuclear Power Station

P.O. Box 330 c/o U.S. Nuclear Regulatory Comm.

Manchester, New Hampshire 03105 P. O. Box 1149

Seabrook, New Hampshire 03874

Dr. Murray Tye, President Mr. John C. DeVincentis, Director

Sunn Valley Association Engineering and Licensing

209 Summer Street Yankee Atomic Electric Company

Haverhill, Massachusetts 08139 1671 Worcester Road

Framingham, Massachusetts 01701

Robert A. Backus, Esq. George D. Bisbee, Esq.

O'Neill, Backus, and Spielman Assistant Attorney General

116 Lowell Street Office of the Attorney General

Manchester, New Hampshire 03105 25 Capitol Street

Concord, New Hampshire 03301

Mr. Phillip Ahrens, Esq. William S. Jordan, III

Assistant Attorney General Diane Curran

Office of the Attorney General Harmon, Weiss, and Jordan

State House Station # 6 20001 S. Street, N.W.

Augusta, Maine 04333 Suite 430

Washington, D.C. 20009

Jo Ann Shotwell, Esq. D. Pierre G. Cameron, Jr. , Esq

Office of the Assistant Attorney General Counsel

General Public Service Company of

Environmental Protection Division New Hampshire

One Asburton Place P. O. Box 330

Boston, Massachusetts 02108 Manchester, New Hampshire 03105

Ms. Diana P. Randall Regional Administrator, Region I

70 Collins Street U.S. Nuclear Regulatory Commission

Seabrook, New Hampshire 03874 631 Park Avenue

King of Prussia, Pennsylvania 19406

Richard Hampe, Esq. Mr. Alfred V. Sargent

New Hampshire Civil Defense Agency Chairman

107 Pleasant Street Board of Selectmen

Concord, New Hampshire 03874 Town of Salisbury, MA 01950

Mr. Calvin A. Canney, City Manager Senator Gordon J. Humphrey

City Hall ATTN: Tom Burack

126 Daniel Street U.S. Senate

Portsmouth, New Hampshire 03810 Washington, D.C. 20510

_ - _

, .

Ms. Letty Hett Mr. Owen B. Durgin, Chairman

Town of Br:ntw:od Durhaa B2ard of Selectmen

RFD Dalton Road Town of Durham

Exeter, New Hampshire 03833 Durham, New Hampshire 03824

Ms. Roberta C. Pevear Charles Cross, Esq.

Town of Hampton Falls Shaines, Mardrigan, and McEaschern

Drinkwater Road 25 Maplewood Avenue

Hampton Falls, New Hampshire 03844 P. O. Box 366

Portsmouth, New Hampshire 03801

Ms. Anne Verga Mr. Guy Chichester, Chairman

Chairman, Board of Selectmen Rye Nuclear Intervention Committee

Town Hall c/o Rye Town Hall

South Hampton, New Hampshire 03827 10 Central Road

Rye, New Hampshire 03870

~

Mr. Angie Machiros, Chairman Jane Spector

Board of Selectmen Federal Energy Regulatory Comm.

for the Town of Newbury 825 North Capitol Street, N.E.

25 High Road Room 8105

Newbury, Massachusetts 01950 Washington, D.C. 20426

Ms. Rosemary Cashman, Chairman Mr. R. Sweeney

Board of Selectmen New Hampshire Yankee Division

Town of Amesbury Public Service Company of

Town Hall New Hampshire

Amesbury, Massachusetts 01913 7910 Woodmont Avenue

Bethesda, Maryland 20814

, Honorable Peter J. Matthews Mr. Donald E. Chick, Town Manager

Mayor, City of Newburyport Town of Exeter

Office of the Mayor 10 Front Street

City Hall Exeter, New Hampshire 03823

Newburyport, Massachusetts 01950

i

Mr. Warren J. Hall Mr. William B. Derrickson

Public Service Company of Senior Vice President

New Hampshire Public Service Company of

P. O. Box 300 New Hampshire

Seabrook, New Hampshire 03874 P.O. Box 700, Route 1

Seabrook, New Hampshire 03874

Administrative Judge Administrative Judge

Alan S. Rosenthal, Chairman Bary J. Edles

Atomic Safety and Licensing Appeal Atomic Safety and Licensing Appeal

Board Board

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission

-Washington, D.C. 20555 Washington, D.C. 20555

Administrative Judge Administrative Judge

Howard A. Wilber Helen F. Hoyt, Chairman

Atomic Safety and Licensing Appeal Atomic Safety and Licensing Appeal

Board Board

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission

Washington, D.C. 20555 Washington, D.C. 20555

- _ _ _ _ _ _ _ _ ______ _ _____

, .

Administrativa Judg] Administrativ2 Judge

Emmeth A. Lusbka Jerry Harb:ur

Atomic Safety and Licensing Board Atomic Safety and Licensing Board

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission

Washington, D.C. 20555 Washington, D.C. 20555

Edwin J. Reis, Esq. H. Joseph Flynn, Esq.

Office of the Executive Legal Assistant General Counsel

Director Federal Emergency Management Agency

U.S. Nuclear Regulatory Commission 500 C. Street, S.W.

Washington, D.C. 20555 Washington, D.C. 20472

Edward A. Thomas Carol S. Sneider, Esq. I

Federal Emergency Management Agency Assistant Attorney General

442 J. W. McCormack (P0CH) Office of the Attorney General

Boston, Massachusetts 02109 One Ashburton Place, 19th Floor

Boston, Massachusetts 02108

Paul McEachern, Esq. Richard A. Haaps, Esq

Shaines and McEachern Haaps and McNicholas

25 Maplewook Avenue 35 Pleasant Street

Portsmouth, New Hampshire 03801 Concord, New Hampshire 03301

J. P. Nadeau Allen Lampert

Board of Selectmen Civil Defense Director

10 Central Street Town of Brentwood

Rye, New Hampshire 03870 20 Franklin Street

Exeter, New Hampshire 03833

William Armstrong Sandra Gavutis, Chairman

Civil Defense Director Board of Selectmen

Town of Exeter RFD #1, Box 1154

10 Front Street Kensington, New Hampshire 03827

Exeter, New Hampshire 03833

Anne Goodman, Chairman William S. Lord

Board of Selectmen Board of Selectmen

13-15 Newmarket Road Town Hall - Friend Street

Durham, New Hampshire 03824 Amesbury, Massachusetts 01913

Michael Santosuosso, Chairman Jerard A. Croteau, Constable

Board of Selectmen 82 Beach Road

South Hampton, New Hampshire 03827 P. O. Box 5501

Salisbury, Massachusetts 01950

Stanley W. Knowles, Chairman Judith H. Mitzner

Board of Selectmen Silverglate, Bernter, Baker, Fine,

P. O. Box 710 Good, and Mitzner

l

'

North Hampton, New Hampshire 03862 88 Broad Street

Boston, Massachusetts 02110

Norman C. Katner Bary W. Holmes, Esq.

Superintendent of Schools Holmes and Ells

School Administrative Unit No. 21 47 Winnacunnet Road

Aluani Drive Hampton, New Hampshire 03842

Hampton, New Hampshire 03842

Jane Doughty

Seacoast Anti-Pollution League

5 Market Street

Portsmouth, New Hampshire 03801

_ _ _ _ _ _ _ _ _ _ _

. . .

.

9

e ; .

Employec's legal Project

P.O. Box 633

Amesbury MA 01913

(G17) 3884Mi20 -

Employee's Legal Project Draft Response to NRC Special Inspection

No. 50-443/86-52

INTRODUCTION

This is an analysis by former Seabrook nuclear plant employees of

the Nuclear Regulatory Commission's (NRC) Special Inspection

Report No. 50-443/86-52. The NRC Report ostensibly dismisses .

former employees' concerns about safety violations in the

Seabrook nuclear plant's design, construction, and documentation.

The NRC terms these concerns "not substantiated." The

Employee's Legal Project (ELP) and these former employees

believe the NRC report raises more questions about the Seabrook

nuclear plant's overall safety than their original allegations

did.

Most of the information used in this analysis comes directly from

information provided by the NRC in their special report; the page

numbers and allegation numbers refer to the NRC's report. In

several cases, some meaningful historical information is included

to give a context for questions allegers have raised concerning

the NRC report.

,

It may be helpful to provide here a brief outline of how the NRC

,

Special Report and this analysis of it came to be. In September,

1986, the ELP made public a number of safety concerns raised by

1

_ ._ . _. . . . . _ . __ _ . .

.

. -

.

-

  • ;-. '

~

.

former Seabrook. nuclear plant employees who askeyl their

.

identities remain confidential. Those allegations.were sent to

Massachusetts Governor.Dukakis, were made public at a press

conference, and were simultaneously sent to the NRC's Region 1

in

head, Richard Starostecki with whom the ELP had already been

contact. Starostecki had been reassigned, and William Kane-took

his~ place. Apparently during that transition, the ELP's

'- information was misplaced. The NRC received it a week later from

a media source. The NRC restated, numbered, and categorized the

allegations.

In October, two former Seabrook employees, Douglas Richardson,

,

who had been an as-built piping inspector for Pullman-Higgins,

k and Raymond Lavoie, a former electrician, made their concerns

l' about safety problems at the Seabrook plant public at a press

I conference..In early November, the NRC sent up a team of 6

! inspectors to investigate the allegations. Engineer Jacque Durr

1

!

-interviewed ELP coordinator Sharon Tracy on November 4 in the

presence of the ELP attorney to " clarify" allegations from

,

anonymous former Seabrook workers. Later that evening he

'

interviewed Raymond Lavoie, whose own attorney was present. The

next day, he interviewed Douglas Richardson.

!

Within two weeks, the NRC investigators had completed their work;

i the Special Report was released on December 24, 1986.

1

i

l

l

l 2

i

, . . - - - - . - - - , - . , - . . - , , , , . . . , - . - - , - - , , - , , , , - , , , , , , , , , - - - - . - _ - . - , - , , . . - , - , , , - , _ , , - _ , , , , , - _ -

_- - _ - ____ - _ _ _ _ _ . .. .

.. .

. .

.

. .

.

e ; s

.

The first section of this response to the NRC report analyzes

.information cited by the'NRC throughout their report regarding

cold pulling, poor design control and construction practices,

training,.and quality assurance. The ELP analysis then examines

and critiques specific NRC allegation responses and asks

questions elicited by the NRC report: Does the-NRC information

show a major breakdown in design control, construction practices,

training, and quality assurance and control by both the major

piping contractor and the licensee and a breakdown in NRC

oversight? Are NRC assurances that procedures exist to

prohibit certain unsafe practices enough to show those practices

did not take place?

This is an analysis of one small NRC rep' ort out of many, many

others written over the years. What questions would be raised by

an analysis of those other reports? It should be noted that'the

NRC says in their report that the agency has put in 20,000 man-

hours of Seabrook plant investigation. On the surface, that may

.seem-substantial, but it works out to one full-time person on the-

job for the life of the construction; not much when the magnitude

of the project is considered.

OVERALL QUESTIONS RAISED BY NRC REPORT 50-443/86-52

Cold Pulling (Cold Springing)

  • Pullman-Higgins (P-H) was the piping contractor for the Seabrook

3

__________

.. -. - .. . . . . -

> e

.

. . .

nuclear plant. Various sections of the. report seem to show P-li

< was unaware of regulations prohibiting " cold pulling" (" cold

'

stretching" or " cold springing). This is a practice where pipes

which don't fit up properly are forced into place using a come-

along or ropes and pulleys, thus putting undue stress on the

'

1

pipes and welds.

1

Allegations #40 and #46 on page 74 show the scope of the problem.

After the licensee discovered P-H was engaged in cold pulling,

"the licensee determined that the contractor.was not fully

cognizant of the details of Specification No. 9763-006-248-51

which required that no mechanical means could be used to move

pipe more than 1/8 inch off its centerline position."

+

Allegations 840 and #46 are about cold pulling incidents. The NRC

says these allegations refer to "a well documented licensee-

identified cold pull incident" in the main steam feed line.

However, neither allegation referred to that particular cold

pulling incident ( Nonconformance Report No.80749). Although the -

  1. 40 and # 46 seems to indicate there

4

NRC response to allegations

l

f is only one documented case of cold pulling, there is evidence

,

. throughout the report to show that cold pulling was a serious

problem.

,

For instance, allegation #46 (see also allegation #55, page 91)

refers to cold pulling in the condenser piping (extraction

system), not the main steam feedwater system mentioned by the

l ,

NRC. Allegation 47, page 28, refers to cracking in the cement of

i

4

l,

.--r-w- ,m-.. .-m..r.. - - - , _p# .--.w.e , ,%,,-_,r ..-p,-_ .y-.1 w. --m.v e.,, ,,-m,-,,. , - - _ _ , ,y.e e,

_

, .

.

e , e

the cenent-lined service water pipes. In 1984, the NRC staff

reviewed licencee records (Inspection Report No. 50-443/84-12),

and visually inspected 40 feet of a 42-inch service water pipe to

" determine the conditions and controls applicable to pipe cold

springing." The service water pipe "is classified as safety-

related ;,SME Class 3, Seismic."

Apparently cold pulling was so serious a problem that the licensee

submitted a Construction Deficiency Report (CDR) to the NRC in

1982 evaluating seventy piping systems for the effects

of cold pulling. The CDR also said " procedures were revised to

preclude recurrence," and the NRC report states the corrective

actions were in place by January 1983 (pages 74 and 75).

Although the NRC 1984 report decided "it is unlikely that the

cement lining would have been subjected to sufficient forces to

cause signifigant cracking by cold springing during pipe

installation," the report said "The lining did contain hairline

cracks, although these were of a width much less than the 1/32

inch acceptance criteria." This implies cold pulling was

responsible for pipe lining cracks in the service water system,

a safety-related system.

The contractor was not aware of prohibitions against cold

pulling; the licensee inspected 70 piping systems in relation to

cold pulling; and the allegers were referring to different cold

I

pulling incidents than the one acknowleged by the NRC. There are

l

1

l

5

l

l

l

-

t

-

,

.

. . .

indications the problem.was vastly more widespread than simply

'one incident.

It-is interesting to note that the licensee's service water

system report dealing with cold pulling was date.d 1984, but

procedures were changed in 1983 so cald pulling would not recur

(page 75). Did cold pulling continue to be a problem after the

procedure was rewritten?

Poor Construction Practices

The NRC speaks to allegers' concerns about the poor relationship

-

between P-H, the piping contractor, and United Engineers and

Constructors (UE&C), the construction manager (allegations #33,.

834, #47, #59, and #60, pages 66-68). The NRC says this bad

relationship was due to P-H's poor job performance. "In

the early 1980s, significant concerns with P-H's job performance

were-identified by the NRC...primarily with design control and

the use of construction practices which were in conflict with

-

UE&C specifications" (page 67).

According to the NRC, corrective actions regarding the piping

,

contractor 's poor job per formance resulted in a major

l reorganizational effort, " organizational and procedural changes

i

! which ultimately led to increased licensee and UE&C control of

P-H activities" (page 67). Coupled with the statement P-H did not

!

know cold pulling was a prohibited practice, and the inspectionn

!

f

of the 70 piping systems, this major reorganization indicates the .

,

6

[

L

. _. . _ _

. .. . .__

--.- ,

.

. . .

,

possibility of an extensive piping problem.

l

t

I How extensive was- this problem? It was discovered af ter the

-

piping in the plant was substantially installed. According to the

allegers, there were numerous instances of cold pulling neither

the licensee nor the NRC knew about, since the NRC says there was

i

only one documented report of cold pulling.

1

L

Poor Design Control

The NRC report shows an overall design control problem, and

,

cites such a problem in relation to Pullman-Higgins' work. Further

i examples of design control problems may be found in the NRC

.

response to allegations 851,(page 86) and 854 (page 90).

Allegation #54 says parts of the air conditioning / refrigerant

i system of the Control Building Air Handling (CBA) system were

i

built without design drawings. Although the NRC says this

'

allegation could not be substantiated, and says design drawings

4

have been issued on the system in question, when were those ~

! drawings issued?

4

!'

.

According to the alleger, the CBA system as originally designed

called for two identical air conditioning systems. Because the

original system lacked sufficient capacity, two more supplemental

systems had to be added. The tubing for these supplemental

1

1

systems was field run, or put in without design drawings for

.

guidance. Just the fact those supplemental systems had to be

,

added shows there were design problems.

t

7

- - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ _ .-_

- --__ _ _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. ..

.

. . .

Another issue pointing to either design control or construction

practice problems is raised in the NRC response to allegation

  1. S4, the CBA system: steel piping was installed originally, then

had to be replaced by copper piping. The code as cited says "all

piping associated with the system is rigid copper piping. Steel

piping is not used in any part of the system." Yet steel was used

the first time around. Were design specifications unclear, or was

the design not properly followed?

Another instance where the correct specifications were not made

known can be found in the NRC response to allegation #51, page

86. Although to NRC says, "all piping (in the CBA system) is

seismically supported...," the alleger, an as-built piping

inspector for P-H in 1982, was not told about specifications

requiring those pipes to have seismic supports. Did the

regulations change, or did piping inspectors and perhaps even

piping installers, receive incorrect or insufficient information?

Training

Adequate and appropriate technical training for craftspeople

engaged in nuclear plant construction is essential for making

sure the plant is properly inspected and safely built. The NRC

response to the allegations that training was poor and not well

monitored ("not substantiated") raises questions of how closely

the NRC actually oversaw the Seabrook plant.

8

..

_ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. , .

.

6 ; ,- ..

'

The NRC response cites a number of reports saying the training

was. fine and that the " quality of the training programs was

ultimately ^ reflected in the quality of the equipment

installations. The quality of equipment installation was

extensively examined by the NRC" (page 35).

Yankee Nuclear Services Division conducted 11 audits between May,

_1978 and December 1981; UE&C conducted 10 internal audits on

training between July 1974 and October 1985. "No significant

deficiencies were found...The NRC inspected training and

qualification programs as a routine part of the inspection,

program during the construction phase"(page 35).

Allegation ill, page 37, refers to' communication and

comprehension problems for engineers and other employees whose

first language was not English. "If the communication problem was

severe, it would be reflected in unacceptable work and be

detected by the multiple checks and counterchecks." -

p-H was a contractor with a major role in building the plant:

installing the miles of piping which makes up a nuclear power

plant. Yet it wasn't until 1983 that the licensee took action

because p-H did not know cold pulling was prohibited, and had job

performance problems with " design control and use of construction

practices" (page 67). If a major contractor had major problems

which weren't acted on until seven years after construction

l ,

I began, what does that say of training, quality of equipment

9

_ ._ . , _ - - . ._. - _ _ _ _ _ . _ _ _ . _ _ _ _ _ _ . _ __ ______ _

-e ..

-

.

~

'o ,- .

,

i installation, and the NRC's oversight of either?

,

As far as being able to track people's training records, the NRC

,

states on page 35 that qualifications for contractors performing

1.

'

welding or quality control work were documented and are

available. And again, on page 63, the NRC states that during the

hiring. process the " individual had to demonstrate his

,

j

qualification. Examples of these are welders and nondestructive

examiners." And, " Nondestructive examination personnel were

tested to assure their qualifications met the code..., the

i individual's experience record was verified..."

i

I

1

I How well did the system work? James Padavano, a weld inspector,

i

falsified his qualifications on his resume, then went on to

I

i falsify documentation on 2,399 weld inspections. Some of those

,

' welds were safety related, and some were inaccessible due to

i

concrete pours by the time Padavano was caught (in 1983) and

convicted (in 1985), and could not be checked. His

! -

" qualifications" may have been documented, but they were

1 ' certainly never checked. Only after Padavano's case went

! before a Grand Jury was it was discovered he falsified his

i

i

j resume and references.

!

(

4

Allegations #12 and #27 (pages 38 to 41) refer to improperly

trained welders. The NRC report cites many inspections of l

4

1

training programs and welding procedures. But how good were these

l

!

'

programs and procedures? The NRC performed "in excess of 26

i 10

i

..- ,m_~,-.. _..-,.,_,__,........_,.,,_m--- m ., _ _ _. , - -, - , - _ _ . , , , _ _ - - , _ _ ---,,.m,._ .

_ . _ _ _ - _ _ _ _ _

. ..

.

o g .

inspections" and "over 592 independent examinalions of welds at

Seabrook." Of all the thousands of welds in the plant, only "145

pipe welds were selected by the NRC and examined by

radioagrapnic, ultrasonic, magnetic particle, or liquid penetrant

testing methods." The rest of the 592 were visually examined,

according to the NRC.

The NRC is satisfied with welder training and qualification

programs, and is satisfied that procedures were understood.

Again, responding to allegation #25, page 60, that construction

procedures were written in ambiguous language, up to

interpretation by the reader, the NRC says, "a formal process

existed for clarification of procedures or interpretation of

technical requirements." How well did that formal process

actually work?

On page 1-5,the Executive Summary, the report says workers were

trained and qualified to American National Standards Institute

requirements. However, Doug Richardson, an as-built piping

inspector for P-H was not certified to these requirements and

never heard of " ANSI N45.2.6."

It seems , at least in the case of P-H, welders were not aware

If training is not truely

, cold pulling was a prohibited practice.

adequate, construction work quality suffers.

11

_- _ _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

,....

-

.. .. .

.

i ; e

,

-Quality Assurance / Quality Control

The NRC explains the quality assurance program as a three-tiered

system, the first level being inspections by the contractor, the

second and third being audits and surveillances of the

contractors' inspections by Yankee Atomic Electric Company. The

NRC then audited.those audits. It is up to the contractor doing

the work to police themselves, then the NRC examines the

contractor's inspection reports.

On page 69 allegation #36, the NRC finds no problems with the

quality assurance, quality control program at the Seabrook plant.

-However, the apparent breakdown in other aspects of the NRC's

oversight procedures raises questions about the NRC's assurances

here.

NRC presence at the Seabrook site was not omnipresent. Prior to _

1980, there was no on-site NRC inspector, so the NRC performed

only flying inspections. In 1982, a second NRC inspector was

assigned to Seabroon. Considering the 8,000 to 10,000 people

working onsite at any given time, and that a good part of an NRC

inspector's job is paperwork, it would be extremely difficult for

t_ NRC inspectors to discover the smallest fraction of violations.

The 20,000 man-hours the NRC puts forward as evidence of the

.

quality of.NRC oversight is somewhat misleading in light of the

size of the job site and the number of people who worked there:

12

_ _ _ _ _ _ _ _ -

_ _ _ . - _ _ __ - . - . _ _ . - - - - . - _ - _ _ . _ _ _ _ _ _ _ _._ ._ __

.' ..

.

- :o g .

.

one inspector for the entire. project over ten years.

.

1

i

An example of quality assurance breakdown is.found on page 74 (70

piping systems were evaluated) where the NRC verified that

supports were " installed on piping systems... assuring that the

effects of cold pull...were minimal." But cold pulling should

never have occurred. It was apparently determined in the summer

.

=of'1982 thatiP-H did not know about the prohibition against cold- ,(

i

pulling. New procedures to reinforce the cold pulling prohibition

.

,

! were produced in 1983. Two years later, the service water system

!

was tested and found to have cracks in the cement lining,

1

possibly due to cold-pulling. Was cold pulling continuing despite

,

procedures being rewritten to prohibit it? (see page 75).

!

) Pu llmar. Powec Company, P-H's parent company is "N" qualified by

,

>

j- the NRC to perform nuclear plant-related work. How reliable is

j that "N" qualification if P-H didn't even know about an important -

c

prohibition? Does this point not only to a generic problem with

P-H understanding of quality assurance / control, but to questions

on the understanding of the other constractors as well?

i'

Although the NRC's inspections, procedures, and quality

.

l

assurance / quality control programs are cited extensively to prove

! allegers' charges are unsubstantiated, they clearly failed in one

w

major case (P-H and cold pulling). Shouldn't procedures and rules

l

, be considered suspect in declaring the allegations

i

!

13

!

.

. -. -- . . - . . - - . . -. . .- . . .-

,

. . ..

+

.

1 -.j .

1

.

! " unsubstantiated"? Is it possible all piping installations up

i

until 1983 are questionable?

The 'NRC says all quality assurance / quality control requirements

were met, but is this accurate? P-H, piping contractor for major

,

work, had its role severly curtailed when cold pulling and

construction practice problems were discovered. At that point the'

y

plant had been under construction for seven' years,

b '

i

! One issue not addressed in the NRC report, but related to

i

} contractors' quality of work and interrelationships, has to do

1

4

with UE&C. In 1984, Public Service Company of New Hampshire

4

(PSNH), the lead owner.of the Seabrook nuclear power plant, was  !

<

in severe financial straits. Construction was shut down, and

!

there were massive layoffs
6,000 people. At that time, there was

,

mention in the media that PSNH was considering suing UE&C. That

1

'

suit never came about, so it is_ unclear why PSNH was looking into.

'

that option. PSNH owed UE&C money. When the project restarted

I

{

(after Merill-Lynch got involved in restructuring the project's -

i

financing), Pullman-Higgin had been fired, but UE&C was still on

! the job. UE&C had changed the debt PSNH owed into a loan.

i

4

i In a more recent development, a stockholders' suit against both

t

PSNH and UE&C in Federal District Court for mismanagement, among

i

other things, was settled out of court in November of 1986.

].

L PSNH's insurance company agreed to pay $1) million to ratepayers

a

j

to settle the suits against both UEEC and PSNH. Why was PSNH

I 14

i

, _ . . _ . - _ . _ _ . _ _ _ - . _ - . _ . , _ . _ _ . . _ . . - _ _ _ - _ . _ - . , . _ . . _ . _ . . . _ _ . . _ . . . . . ._._ _ _

._. . . . . - _ -- . .- . -. - - .-

C

, .. ..

.

, j .

contemplating a suit against UELC _ iti 1984? Why did PSNil decide

not to file suit,'and why was UELC retained?

j

>

1

[ CRITIQUE OF SPECIPIC ALLEGATION RESPONSES

.

Page 1 of the NRC's Executive Summary states investigators are

'

authorized "to expend whatever resources were required to resolve

the issues." Yet the report also says that by the time the NRC

made their investigation into the allegations , the specific

contractors referred to by the allegers were no longer on site.

Consequently, the-NRC gathered only secondhand information from

- the licensee staff, and made no effort to contact companies

responsible for the work on systems examined.

'In many cases, the NRC refers to programs which were instituted

} after construction was substantially complete, notably the

I security, drug.and alcohol testing, and personnel programs.

The NRC also relied almost exclusively on previously generated

.

}

paperwork.

!

!

When Jacque Durr, the engineer heading the NRC inspection,
interviewed the allegers, he baldly stated he expected to find

t

! nothing. wrong, demonstrating an unacceptable degree of wishful

i thinking. lie also told the ELP coordinator, in the presence of

the ELP attorney, he flatly refused to interview whistleblowers

! if they wanted the ELP coordinator to be present. In addition, he

!

said the ELP was interfering with the NRC, and that there was no

!

15

,

l

'

_ . _ . _ _ _ _ . _ , , . _ _ . , . _ _ . , _ . _ . _ _ . _ , . _ _ _ _ _ . . , , _ , _ _ _ . , , _ _ _ _ . . _ .

_

. . - - .- - _ _ , _ - . - ~ . . . _ . - - . -

. ...

.

e. 4 e

,

4

role for the ELP since whistleblowers should g directly to the.

'

NRC. Ilowever, people in contact with the ELP are hesitant to go

to-the NRC believing the agency will whitewash their concerns and

could compromise their confidentiality as has occurred at other

nuclear plants. The charge of interference was puzzling since the

4

NRC would never have been aware of these allegations without the

4

help of the ELP.

CRACKS IN Tile CONTAINMENT CONCRETE (allegations #1,#2, 83, #4,

and $17, pages 15 to 23). Allegers refer to major c, racks, some

'

leaking water. The NRC reply only addresses reports on surface

cracks concerning surface cracks, finding the allegations are

!

"not substantiated." Bdt the NRC does in passing mention there

'

are some cracks which leak water (page 22). If the cracks leak

' water, then aren't they more than simply " surface cracks"? The

I NRC says the cracks leaking water are adequately patched, and

cite reports on inspections done in late summer and early fall.

Since the water table is usually at its lowest then, is it

possible the cracks would leak when ground water was higher?

1

t

The NRC says minor cracks in the containment are acceptable

i

because the reinforcing bars prevent containment failure , and

l!

because surface cracks don't affect the rebar, cracks as a

l

i-

,

problem is "not substantiated." There is no discussion of the

i

cracks which did leak water (NRC reports in 1982, 1984, and 1986,

i

page 23), and the water's effect on the rebar. The NRC discussion

i

'

of the structural integrity test implies the containment will

l

l

'

16

-. - . . - -- - - . - . - - - - - . - - - . . . . - - - - . - - . . . . - - . . - . -

.. ,.

.

o ; e

flex, and that weak spots are susceptible to pressure.

Isn't it possible that when the concrete leaks, the rebar loses

its protection from corrosion, so losing its tensile strength?

-

This would create weak spots. As the rebar weakens with age, the

containment loses its margin of protection as it increasingly

needs it. Also, if water can leak in, can't radiation leak out in

a pressurized situation?

Allegation #2, a rejected batch of concrete was poured anyway,

was dismissed by the NRC. Even though that allegation had been

clarified, showing the incident occurred in Unit II, the NRC

dismissed the allegation, citing records from Unit I.

Even though the rods supporting the containment were improperly

severed, the NRC says that was not a problem because the rods

were reattached using the "cadweld" process. The NRC statement

that this process makes the rods stronger than if they had never

been improperly severed is debatable. .

THE FIRE PROTECTION SYSTEM'S CLOGGED PIPES addressed in

allegations #6, #49, and #50 (pages 25 to 27) drew an inadequate

response from the NRC. The following analysis was provided by

Raymond Lavoie, a former electrician at the Seabrook plant, who

saw 12-inch pipe so clogged there was only a 4-inch diameter

hole.

On page 25, paragraph 2, he did not find it helpful to learn that

17

.

.

. _ . .

. ..

.

. s .

the inspector simply reviewed documents and ensured that

procedures were in place for maintenance of the fire protection

equipment. Some effort should have been made to inspect the pipes

which he observed to contain thick sedimentation. The fact that

surveillance and testing programs are in effect is not evidence

of ability to implement them, even if they are adequate. It would

also be helpful to know what specific procedures exist.

Page 25, paragraph 3: the NRC inspector reported that "to

establish the condition of the fire protection system," he

observed fire hydrant testing, sprinkler system testing, and

examined screens. It is not sufficiently clear when this was

done, i.e., 1983 or during the onsite visit in 1986, whether it

was the onsite 1986 inspector who observed the testing, or

whether it was a report that the onsite inspector observed of

testing done on some other date. The report also fails to

indicate from where the screens were removed. The remainder of

paragraph 3 again only refers to review of written documents and

-

procedures that had been provided. The paragraph also refers to

" inspection of fire pump house piping." One assumes the reference

is to piping inside the fire pump house and not outside the pump

house where the actual piping was observed to contain thick

sedimentation. Overall, the review appears to be only a paperwork

review.

Page 26, paragraph 1, an interview with the American Nuclear

. Insurers representative reportedly took place. Since the nuclear

industry backs ANI, any conclusions arrived at by the NRC may

18

_ _ _ _ _ _ - _ _ _ _ _ _ _

, , , , , , , , , ,. . _ . . . . _ . _

.. ,.

.

. .

lack credibility. Again, paragraph i does not provide us with any

dates. At best, it appears that the NRC reviewed a memorandum

dated October 22, 1986, prepared by ANI.

Page 26, paragraph 2, the NRC report indicates that on November

4, 1986, (the same day Raymond Lavoie was interviewed, the NRC

" observed insurance tests for systems "P" and "I," the electrical

transformer 2-inch drain tests and the hydrant il flow tests and

the " expected pressure and water volume flow characteristics were

achieved with no evidence of line blockage noted." Again, the NRC

does not indicate whether they were observing written reports of

tests done prior to November 4, 1986. While the NRC admits to

some blockage and evidence of sedimentation, the actual test

performed (on some unknown date) was inadequate. The system should

have been achieving several thousand gallons more of water per

minute from the nozzels.

.Raymond Lavoie believes the NRC should have used at least 20 2-

inch nozzels. Also, the fact that " water flowing from the nozzel

was clear" is not indicative of anything if the sedimentation in ~

the pipes was hardened and crusty, as Lavoie observed it to be.

Arrangements should also have been made for producing several

streams of water.

The NRC does not specify what activity it was involved in or what

it observed that caused the NRC to conclude that the Fire Pump

House was always kept locked when not attended. Furthermore, the

.NRC apparently is indicating in paragraph 2 that the inspector

reached his conclusions prior to interviewing Lavoie. Such an

19

- - - ____-_.

.  ;.

.

a : .

interview, therefore, could not be characterized as one conducted

in good faith. The paragraph also states "the stream through a 1

3/4-inch nozzel reached beyond 200 feet." In Lavoie's opinion,

this is inadequate evidence of ability to put out a major fire at

the plant, i.e., there would have to be evidence of the stream

reaching far beyond 200 feet.

Page 26, paragraph 3, the NRC inspector noted that " chlorination

had been in progress," but the reference is to the word

" initiated" in 1983. The report further states the purpose of

chlorination was to prevent microbiological induced corrosion

(MIC). Allegations #6, #49, and ISO do not speak about corrosion,

rather they speak about sedimentation, a completely different

process. Furthermore, the NRC talks about preventing corrosion in

the " unlined pipes," while the pipes in question were not unlined

pipes. The NRC admits this further on in their report where the

inspector indicates that the pipes in question were lined with

cement and therefore could give the impression of being clogged

with sediment. _

Again, the NRC states that the pipes were removed or disassembled

inside the fire pump house to remove MIC deposits, and not

disassembled outside the pump house where workers actually

observed the sediment or clogging. Further, the NRC reports that

the evidence of success of the chlorination project was verified

by the clarity of the water. Again, Lavoie believes clear water

could be achieved if a pipe was filled with hardened sediment.

The real question is: would the amount or volume of water be

20

. ,.

.

.-e .

sufficient to put out a major fire?

' Conclusion: the NRC's inspection did not adequately address the

allegations and it is debatable whether or not an actual onsite

inspection occurred.

-CEMENT COATING' BREAKING OFF INSIDE SERVICE WATER LINES,

(allegation 87, page 28)is dealt with as a cement problem, and is

severed from the cold pulling problem raised in other parts of

the report, although NRC comments on this allegation imply the

cement cracking could have been due to cold pulling.

TRAINING INADEQUACIES (allegations #10, #11, #12, #27, #29, and

  1. 35,-Pages 35, 37, 38, and 63) were dismissed by the NRC which

relied on reports by the licensee and companies it hired. The NRC

also affirmed procedures were adhered too, and they met NRC

requirements. However, other parts of the report (pages 28,

66,74, and 86) show a major failure of those NRC assurances.

Pullman-Higgins, the piping contractor is cited as not knowing,

seven years into the plant's construction that cold pulling is a_

prohibited practice, and with having problems with design control

and construction practices. If the procedures worked so well, why

weren't these problems discovered much earlier?

.

.

HARASSMENT OF WORKERS REPORTING SAFETY PROBLEMS: DRUG AND ALCOHOL

ABUSE (allegations #13, #16, and #21, pages 42 and 49) are

dismissed as "not substantiated." The NRC reasoning? The rules do

not allow that kind of behavior. Such rationale doesn't account

for the fact that rules get broken.

21

_ . _ _ . _ . . . . , . . _ _ _ _ _ _ . _ . . _ . - . _ . .

.. ,.

e. # .

DEBRIS IN AN ELECTRIC GENERATOR, FIRE IN AN ELECTRICAL CONDUIT, A

FILTHY REACTOR, PAINT THINNER SPILLED ON ELECTRICAL CABLES,, WORN

ELECTRICAL ~ CABLES WHICH~GAVE OFF SPARKS (allegations 818, #19,

  1. 38, #39, #43, pages 50, 51, 71, 73, and 80) refer to an overall

housekeeping problem in the Seabrook plant's construction. They

were symptomatic of an ongoing generic problem of poor working

conditions and an uncaring attitude toward building a nuclear

elant. Looking at the issue now has no bearing on the actual

working situation. ,

The fire in the electrical conduit caused by a ci arette

h was

'

dismissed by the NRC with rather speculative language, "if a fire

had occurced..." The alleger rei*terates: a fire very definately

occurred. Is it possible debris or garbage had also fallen into

the conduit and burned hotly enough to burn the cables? That

possibility was not considered by the NRC in addressing this

. allegation.

-

CHECK OFFS FOR STARTUP WERE DONE CARELESSLY (allegation 820, page

53) was decided to be " unsubstantiated" by the NRC. The response,

"if erroneous information was gathered, it would have been

j

detected and corrected" does not take into account that

information not collected cannot be checked. Inspection work

which is not done with first-hand knowlege is sloppy work; it is l

,

not according to procedure. The NRC is willing to concede

!

I erroneous information may have been gathered in the inspection

1

i

procedure; why then assume the follow up procedures function

22

.. - _

- , -

,

. ./

  • f.

'e ; e

correctly if other procedures apparently have failed?

SECURITY problems (allegations #22 and #23, pages 55 and 56) were

'

, dismissed by the NRC'wh'ich cited access control reports. One

alleger-responded that in 1982, security didn't seem as

interested in controlling access as in searching outgoing

. personnel to prevent theft from the site.

,9

1,

The NRC report does not address security during construction so

,

much as it analyzes post-construction security. Essentially the

s

'

NRC accepts the licensee's word that security worked simply

because the licensee's procedure was NRC-approved. Is the

presence of an NRC-approved procedure enough guarantee the

procedure worked?

DEFICIENCIES WITH NONCONFORMANCE REPORTS (allegation #24, page

58) was found to be " unsubstantiated" by the NRC because all the

,

appropriate reporting, engineering, and quality assurance

procedures were NRC-approved. -

l SAFETY RELATED CONSTRUCTION PROCEDURES AMBIGUOUS (allegation #25,

page 60) was dismissed by the NRC because NRC-approved rules and

procedures to prevent such problems were found to be acceptable

by the NRC.

i

,

TRACKING OF BLUEPRINTS AND DRAWING REVISION CONTROL WERE

INEFFECTIVE (allegations #32 and #57, page 64) were found by the

NRC to be true "in isolated cases", but were " unsubstantiated" in

l

23

.--.-- -_- -

. , . . . ,.

. . . - .

.

. .

e. e

,

,

o : . ,

the NRC conclusion. However, the NRC procedures only actually

call'for inspections in isolated cases anyway. If only a small

number of cases were examined by the NRC, and within those were

found " isolated instances" of this problem, might there have been

many more cases never discovered?

Pullman-Higgins, the piping contract,or, lost its document control

responsibilities to UE&C in 1983 (see page 67). That action shows

more of a problem than the NRC acknowleges in the " isolated

cases" cited.

. BATTLING AND SABOTAGE BETWEEN CONTRACTORS (allegations #33,#34,

859, and.t 60, page 66, "could not be fully substantiated by the

NRC, but no safety related equipment deficiencies could be

identified..." No contractors from P-H, one of the contractors

mentioned in the allegation, remained on site at the time of the

-NRC's investigation, and the NRC ms .e no apparent effort to h

contact any of the P-H employees who had worked on seabrook. No

4

safety problems were found because the NRC didn't talk to anyone .

who would know about the problems referred to in the allegations.

.

PRIMARY AND BACKUP FEEDWATER SYSTEMS SUPPORTED BY A SINGLE

STRUCTURE AND NOT ADEQUATLEY SEPARATED (NO FIREWALL BETWEEN THEM)

(allegation #48, page 85) was dismissed as "not substantiated" by l'

the NRC, but the allegation, made by Douglas Richardson, was

misinterpreted. The alleger was concerned an accident,

specifically a fire or a seismic event, could destroy both

systems at once; the NRC only analyzed a situation where a

) l

-

24 t -

l

' l:-

.

.. . .

_ _ _ _ _ _ _ _ _

r-

s. .

. - i .-

nissile from the turbine driven pump wrecking the system "is not

a' credible event." That was not the concern raised by Richardson.

THERE IS NO FIRE BARRIER OR OTHER SEPARATION BETWEEN' CONTROL

BUILDING AIR CONDITIONING SYSTEM REFRIGERANT LINES (allegation #

51, page 86) refers to no separation of power sources and no fire

barriers between primary and backup systems. The NRC agrees that

is the case, but says the " design...does not degrade plant

safety." But is the design truely adequate for protecting public

safety? The alleger, Douglas Richardson, was told by NRC staff

the lack of separation was based on the proper functioning of the

fire protection system. But that system has been called into

question (see page 25).

EMERGENCY FEEDWATER SYSTEM FED FROM THE SAME TANK WHICH SERVES AS

CONDENSATE STORAGE FOR THE MAIN STEAM FEEDWATER SYSTEM

(allegation 852, page 87) was found to be " unsubstantiated" by

the NRC. However, the rationale assumes a minimum requirement,

.

that the heat removal system will work. Does this follow the

defense-in-depth requirement? -

.

Both the primary and backup system are connected to the same

I

water tank. This tank is backt' -Jp by the concrete enclosure

'which will catch water from the tank if it ruptures. However,

does this rationale take into account a rupture high up in the

tank preventing water from flowing into the concrete containment?

Wouldn't water inside the ruptured tank then be inaccessible?

,

f

,,  ; '

25

,:

A

4

-____-_____-_ _ __ _____ _______ _

e .

o- , .

Also, if the tank ruptures, is potential clogging from debris

from the rupture, or failure of alarm and level gauges taken into

account? The system is also defended by citing administrative

controls which rely on operators taking correct actions. Does

this analysis look at the fact that human error is the cause of

many nuclear plant accidents?

The tank has six nozzle penetrations; other systems are hooked up

to it. Will there always be a full tank? Is design adequate?

Wouldn't two tanks in different locations be safer?

The feedwater system is an extremely important part of the

I

nuclear plant, and its safe design and construction is crucial to

the plant's safety. It should be noted that this system failed in

the Three Mile Island nuclear plant, and this systems's failure

caused an accident more recently at the Davis Besse nuclear

plant in Toledo, Ohio.

UNEVEN SUPPORT LOADING UNDER HEAT EXCHANGERS: LINES RUN IN WRONG

SLOPE; WELD IDENTIFICATION PROBLEMS; COLD PULLING IN THE

CONDENSER PIPING, PROBLEMS IN THE TURBINE EXHAUST SYSTEM AND

CONDENSER PIPING (allegation ISS, page 91) was found

unsubstantiated because the NRC misconstrued the alleger's

(Douglas Pichardson) concerns and looked at an entirely different

system. The NRC examined the feed water heaters, not the heat

exchangers, even though the alleger showed the NRC on their own

drawings the exact system to which he was referring.

.

26

' -

.

. - _ _ _ _ _ _ _ _ _ _ _ _ _ -_ \

. -_

,

. -.-

o e ,

but

The-NRC says the sloping of the pipes was part of the design,

the alleger, a former as-built piping inspector, would not

confuse.a designed slope for a construction error.

The weld identification problems were dismissed because according

to the NRC, that information was "not a regulatory requirement."

The_ alleger was told by P-H that weld identification was a

requirement, and part of his job. That program was cancelled at

the same time there was a major restructuring of P-H's role in

the Seabrook plant construction. Is there a relationship between

,

the decision to cancel the program and the discovery that P-H was

suffering from reports of poor job performance (see page 67)?

The alleger addressed a problem of cold pulling in the condenser

piping. The NRC looked at an entirely different system and cited

~ s

a cold pulling incident which had already been documented and

dismissed as an isolated incident (see page 74).

4 The NRC inspected the main steam and feedwater lines instead of_

the turbine exhaust system and condenser piping, even though the

alleger was very specific on the location and function of the

system he was concerned about. In inspecting the wrong system,

.

.the NRC found it had no problems and dismissed the allegation.

Photos numbers 11 and 12 are not the heat exchangers described by

Douglas Richardson to the NRC. There is no question of mistaken

terminology: the NRC examined the wrong system.

27

r -- w a v+~v ,--e

n~rr-- e, -em----m----d.9-v- e s *www* --

-tv--

. .. . . . . . _

.

o

'

. e2

e o ,

TRAINING WAS OF UNEVEN QUALITY (allegation #58, page 95) was

misinterpreted by the NRC, thus was "not substantiated." Allegers

referred to specific technical training; the NRC sidestepped this

concern and addressed only general orientation procedures.

.

CONCLUSION

From random indications that something was not right here and

there, the information in the NRC report shows the feeling on the

allegers' parts that something was wrong is justified. Cold

pulling was not known to be a prohibited practice by the piping

contractor who also.had job performance problems. Those problems

!

weren't discovered until long after construction was begun,

calling into question effectiveness of training, of quality

,

assurance and quality control programs (if the contractor didn't

,

know about prohibited practices, neither did their inspectors),

and of NRC inspection and general _ oversight of the Seabrook plant _

construction.

Some NRC decisions are questionable. For instance, the fire

protections system is not classified as safety related. However,

the NRC relies on the_ fire protection system in calculations on

how well safety related systems and their backups should be

separated. For that reason, shouldn't fire protection systems be

considered safety related?

,

28

-

,. - - - - _ _ _ - . . - . - . _ _ _ _ _

,_ _ _ . , _ , , _

_ _

L

- . o

b

o oe

Douglas Richardson, former piping inspector, was told by NRC

engineer Jacque Durr, and on-site NRC inspector Anthony Cerne,

that the NRC was not concerned if non-safety related systems

don't. work. However, on page 92, the NRC states it is concerned

about the general quality of all plant systems to avoid failures

and challenges to safety systems.

<

The' quality of the report itself is poor. The NRC sidestepped

allegations, misconstrued allegations, which had been made very

-

clear. The NRC accepted licensee analyses and reports, and quoted

-

rules and procedures prohibiting certain actions as proof those

actions could not have taken place. Yet there are indications,

those rules have been broken repeatedly. The NRC arguement that

the existence of certain procedures means those procedures

couldn't have been violated seems to be a way for the NRC to

insulate itself from questions of how well the agency protects

public safety.

Even though the NRC inspection team for this report was -

specifically asked to look at the individual allegations as

examples of generic problems, the NRC made every effort to avoid

doing so. Larger questions, beyond the allegations and the NRC

response to them are raised by this report. How valid is the

framework within which the NRC operates? Is it enough for the NRC

to say there are procedures to prevent certain prohibited

activities? Rules aren't always obeyed. Is it enough for the NRC

to approve a nuclear plant's safety based on audits of a very

small percentage of licensee reports on self-inspections?

-29

1,,.. -

- - _ . - _ _ _ - _ .

- - - - - - - - - _ - - - - - - . - - - - - - - - - - _ _ - - - _ - - - - - - - - - _

.

,

.. o ,

e cm

Additional questions to be addressed are how were similar

allegations and problems at other nuclear plants around the

country treated by the NRC? It seems there was a serious quality

assurance breakdown with at least one contractor at the Seabrook

nuclear plant. Several companies which worked at the Seabrook

I

plant were cited for serious quality assurance breakdowns at

(

other nuclear plants. For example, the Byron nuclear plant was.

denied an operating license in 1984 because Johnson Controls and

Pittsburg Testing Labs (both contractors at the Seabrook plant)

f

had quality assurance breakdowns there.

!

l

l

t

The NRC response to'the allegations in many instances widely

missed the issues allegers brought up. First hand information was

not gathered. If this NRC report is-an example of how well that

agency carries out its responsibilities, it is not encouraging.

' Fail safe" is a concept whose meaning has changed since _

Chernobyl.and the Challenger accidents. The NRC assurances the

~

Seabrook nuclear plant is fail safe are undercut by information

provided in the very report meant to substantiate them. Shouldn't

assurances the Seabrook plant is safe be put in the hands of an

independent investigator, who, with considerable public

oversight, can comprehensively examine the plant?

.

30

~

~~~~ ~

. . . .. . . -. - _ - _ - - _ _