Requests Prompt Approval of Proposed Amend 125,Rev 1,to License DPR-54 to Facilitate Startup.Request Made Due to Early Completion of Listed Work Scheduled for 90-day Outage
ML20125A784
Person / Time
Site: Rancho Seco
Issue date: 05/29/1985
From: Reinaldo Rodriguez
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Thompson H
Office of Nuclear Reactor Regulation
References
RJR-275, TAC-55468, TAC-56973, NUDOCS 8506110196
Download: ML20125A784 (1)


Text

asuun SACRAMENTO MUNICIPAL UT1uTY DISTRICT O 6201 s Street, P.O. Box 15830, sacramento 2A 95852-1830, (916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA RJR-275 May 29, 1985 DIRECTOR OF NUCLEAR REACTOR REGULATION ATTN: HUGH L THOMPSON JR. DIRECTOR DIVISION OF LICENSING V S NUCLEAR REGULATORY COMMISSION WASHINGTON DC 20555 DOCKET N0. 50-312 LICENSE NO. DPR-54

SUBJECT:

PROPOSED AMENDMENT 125, REVISION 1 Rancho Seco Unit 1 shutdown March 15, 1985 for a scheduled 90 day outage. The work performed included refueling for Cycle 7, major overhaul of the turbine generator system, feedwater heater repairs, once through steam generator in-spections, feedwater flow nozzle repairs, numerous TMI modifications, Appendix R modifications, upgrading equipment for the EQ program, and several other minor plant repairs and modifications.

Due to the exceptional performance of plant personnel, a very effective schedul-ing program and the ability to resolve problems quickly, the outage schedule progressed ahead of the planned duration.

The original startup schedule was planned for June 15, 1985. The present schedule has plant heatup on June 5th and core criticality on June 7th. This is slightly one week ahead of the schedule planned prior to shutdown on March 15, 1985.

With the impending summer heat load and economics to prevent purchases of oil generated capacity, Rancho Seco should be put on-line as soon as possible.

Since the plant has been modified and the modification involved Technical Speci-fication changes, the approval of Proposed Amendment No. 125, Revision 1 is required prior to criticality, ourpromp$responsewillbemostappreciatedinthismatter.

\

s  %+

R. J. odrJuez (

Assistant Eeneral M'a ager, Nuclear s 0! 0 Subscribed and sworn to before me j k

this G Act day of ( e xc , , 1985.

C[

, . . bb 5

_ ( W a r) $ . &suu h-l/yy;oran&t?c.'cbonush k Notary Public SQ W

fxnwtuto co'miY My comm. mres m 13. ns7 0506110196 850529 -- "~

PDR ADOCK 05000312 p PDR