Notifies That Application to Amend License NPF-3,authorizing post-transient Insp of Hydraulic & Mechanical Snubbers Will Be Submitted by 860228.Understanding That 850130 Application Will Be Approved by 860215 Confirmed
ML20137M870
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 01/22/1986
From: Williams J
TOLEDO EDISON CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
1239, GL-84-13, TAC-11311, TAC-11312, TAC-65069, NUDOCS 8601290091
Download: ML20137M870 (1)


Text

TOLEDO

%s EDISON Docket No. 50-346 JOE WILUAMs. JA_

sa ve.neum- m License No. NPF-3 Q$$

Serial No. 1239 January 22, 1986 Mr. John F. Stolz, Director PWR Project Directorate No. 6 Division of PWR Licensing - B United States Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Stolz:

On January 30, 1985, Toledo Edison submitted an application (Scrial No. 1113) for an amendment to Facility Operating License No. NPF-3, Appendix A Technical Spccifications, for the Davis-Besse Nuclear Power Station Unit No. 1. This application requested that Technical Specific-ation 3/4.7.7, Hydraulic Snubbers, be revised to include hydraulic and mechanical snubbers, and delete the snubber listing of Table 3.7-3 pursuant to Generic Letter 84-13. In its review of this application, the Nuclear Regulatory Commission (NRC) Staff has requested that Toledo Edison also add a surveillance requirement which requires the performance of a post-transient inspection of all hydraulic and mechanical snubbers attached to sections of systems that have experienced an unexpected, potentially damaging transient. Toledo Edison is presently preparing such a surveillance requirement and will submit this under a separate amendment application to your office by February 28, 1986.

As discussed with Mr. A. W. DeAgazio of your staff, it is Toledo Edison's understanding that the NRC Staff will complete its processing of the application contained in Serial No. 1113 and issue a license amendment by February 15, 1986 which addresses both hydraulic and mechanical snubbers and deletes Table 3.7-3. The issuance of this amendment is necessary prior to the plant entering Mode 4 of restart from the current outage.

Very truly yours, W:DRWilah cc: DB-1 NRC Resident Inspector 00 L