Letter Sequence Request |
---|
|
|
MONTHYEARML20067C4071982-11-24024 November 1982 Responds to Re Tech Specs for Snubber Surveillance.All Snubbers Defined in Ansi/Asme OM-4 Std Will Be Listed in Tech Spec Tables in Manner Similar to Current Table on Hydraulic Snubbers Project stage: Other ML20105B9341983-06-28028 June 1983 Requests Extension Until 830801 to Submit Revised Tech Specs for Snubbers,Due to Extensive Internal Review Project stage: Other ML20077G8181983-08-0101 August 1983 Extends Submittal Date for Proposed Tech Specs on Snubber Surveillance to 830901,to Allow for Resolution of Util Nuclear Review Board Comments Project stage: Other ML20077M1361983-09-0101 September 1983 Proposed Changes to Tech Specs 3.7.7 & Table 3.7-3 Re Snubber Surveillance to Include Mechanical Snubbers W/ Schedules,Actions & Acceptance Criteria for Sample Testing Project stage: Request ML20077M1341983-09-0101 September 1983 Application for Amend to License NPF-3,revising Tech Specs 3.7.7 & Table 3.7-3 Re Snubber Surveillance to Include Mechanical Snubbers W/Schedules,Actions & Acceptance Criteria for Sample Testing.Safety Evaluation Encl Project stage: Request ML20077M1301983-09-0101 September 1983 Forwards Application for Amend to License NPF-3,revising Tech Specs 3.7.7 & Table 3.7-3 Re Snubber Surveillance to Include Mechanical Snubbers W/Schedules,Actions & Acceptance Criteria for Sample Testing.Class III Fee Encl Project stage: Request ML20101T4441985-01-30030 January 1985 Proposed Tech Specs,Revising Hydraulic & Mechanical Snubber Surveillance Program,Including Changes to Visual & Functional Tests of safety-related Snubbers & Maint of Equipment & Surveillance Records Project stage: Other ML20101T4241985-01-30030 January 1985 Application for Amend to License NPF-3,revising Tech Specs 3.7.7,4.7.7 & 6.10.2.m Re Mechanical & Hydraulic Nuclear safety-related Snubbers Project stage: Request ML20137M8701986-01-22022 January 1986 Notifies That Application to Amend License NPF-3,authorizing post-transient Insp of Hydraulic & Mechanical Snubbers Will Be Submitted by 860228.Understanding That 850130 Application Will Be Approved by 860215 Confirmed Project stage: Request ML20140F9071986-03-26026 March 1986 Informs That Deletion of Footnote 6 & Addition of within Specified Range to Proposed Surveillance Requirements 4.7.7.2b & 4.7.7.2c.2,respectively,will Be Incorporated Into Apr 1986 Amend Application,Per NRC 860324 Request Project stage: Other 1983-09-01
[Table View] |
|
---|
Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] |
Text
.
,9- 1
.g TOLEDO
%sm EDISON ACHAAo P. CROUSE vce prem NW%F Docket No. 50-346 wim asvuai License No. NPF-3 Serial No. 1113 January 30, 1985 Director ,f Nuclear Reactor Regulation Attention: Mr. John F. Stolz Operating Re ctor Branch No. 4 Division of Licensing United States Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Stolz:
Under separate cover, we are transmitting three (3) original and forty
.(40) conformed copies of an application for Amendment to Facility Operating License No. NPF-3 for the Davis-Besse Nuclear Power Station Unit No. 1.
This. application requests that the Davis-Besse Nuclear Power Station Unit 1 Technical Specifications, Appendix A, be revised to reflect the changes attached. The proposed changes involve Section 3.7.7, 4.7.7, 6.10.2.m and Bases.
The attachment identifies the changes, Safety Evaluation and Significant Hazard Consideration. The proposed change concerns _ Technical Specifications for mechanical and hydraulic nuclear safety related snubbers.
This amendment request is a revision to a previous submittal, therefore,
~ no fee is incurred.
Very truly yours, RPC: GAB Attachment lec: DB-1 NRC Resident Inspector ,
State of Ohio 8502060160 850130 k ej d/7 PDR ADOCK 05000346 OO P pm f )\
THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 l v
APPLICATION FOR AMENDMENT TO .
FACILITY OPERATING LICENSE NO. NPF-3 FOR DAVIS-BESSE NUCLEAR POWER STATION UNIT NO. 1 Enclosed are forty-three (43) copies of the requested changes to the Davis-Besse Nuclear Power Station Unit No. 1 Facility Operating License No. NPF-3, together with the Safety Evaluation for the requested change.
The proposed changes include Section 3.7.7, 4.7.7, 6.10.2.m and Bases.
By /s/ R. P. Crouse Vice President, Nuclear Sworn and subscribed before me this 30th day of January, _1985. t
/s/ Laurie A. Hinkle, nee (Brudzinski)
Notary Public State of Ohio _
My Commission Expires May 16, 1986 SEAL
r
~c. :. . .
Docket No. 50-346
' License No'. NPF-3
-Serial-No. 1113 Janua ry 30,-1985 Attachment-I. Changes to Davis-Besse Nuclear Power Station Unit 1, Appendix A Technical-Specifications 3.7.7, 4.7.7, 6.10.2.m and Bases.
A. -Time required to Implement. This change is to be effective upon NRC approval.
,. .B. Reason for Change (Facility Change Request 83-080 Rev. D). In response to NRC request of November 20,.1980 (Log No. 638) and revised request dated August 15, 1984 (Log No. 1581) for mechanical'and hydraulic snubbers.
~
C. -Safety Evaluation (See Attached)
L w D. Significant Hazard' Consideration (See Attached) t.
t 3
/
n-.
%+
t-4 I
4 A
1
{' 'l L.
Safety Evaluation Title Technical Specification amendment for hydraulic and mechanical snubbers surveillance. This amendment applies to Sections 3/4.7.7, B3/4.7.7 and 6.10. 2.~
' Introduction l'
The revised surveillance program includes changes to visual and functional tests'of both hydraulic and mechanical safety-related snubbers as well as
. maintenance of equipment and surveillance records. All safety related snubbers at Davis-Besse Unit #1 are installed for seismic event loads.
Some non-safety related snubbers may be designed for other dynamic loads such as relief valve thrust in combination with the seismic loads.
References NUREG-0103 Rev. 4 Standard Technical Specifications, ANSI /ASME OM4 and Drawing'12501-M-618.
Discussion
~
The safety function of all affected snubbers is to ensure the-integrity of
. safety-r' elated systems is maintained during and following seismic loads (definition of safety related snubbers). The' safety function of the Technical Specification as a license document is to provide technical' requirements for plant- operation.
The change proposed is to change _the functional test' sample size in the-Er Technical Specification from "at least 10 hydraulic snubbers or.at least 10% of all snubbers listed in Table 3.7-3, whichever is.less" to "at'least 10' percent (rounded off to next highest integer) of each group of . ,
snubbers". Thereby all safety-related snubbers, both mechanical'and
- hydraulic will be tested. Also'at least a 10% representative sample will' be tested. Changes to the functional test acceptance criteria assure the
-required function of the snubber will be documented' as acceptable prior to -
snubber-reuse. Also tables listing safety related snubbers have been deleted from the Technical Specification and placed in plant drawin'gs and e : surveillance test procedures.
'The additional' inspections required (both hydraulic and mechanical) may
-increase the total man-rem exposure at Davis-Besse. In order to maintainL .
radiation exposure ALARA, visual inspection of snubbers in high. radiation-
~
zones will be performed during-plant shutdowns. Personnel _may use visual'
' inspection aids such as binoculars or other visual . support devices. Also,
.in order to maintain exposure ALARA,~ functional inspections may be
. 'Lperformed on snubbers ~just prior to preventive maintenance 7 Snubbers
? located in low: radiation areas may be inspected and. tested preferentially.
~
foyer those in high radiation areas. ,.
S.
The snubber functional testing program must be conducted such that the system or train operability conform to Technical Specifications.
Functional testing will require unpinning of at least -one end, which in turn renders the snubber temporarily inoperable. However, to conform with Technical Specifications, the action required of station operators is to within 72. hours:
- 1. Restore to operable, or
- 2. ' Verify operability by engineering evaluation or
- 3. Declare the supported subsystem inoperable and follow the appropriate action statement, and perform an engineering evaluation within 90 days to document degradation or adverse effects.
Functional testing of 10 percent-of the snubbers is required every 18 months, which means testing can be performed during refueling outages for inaccessible snubbers. Functional testing may also be performed just prior to preventive maintenance being done on snubbers in order to reduce the time when safety-related systems are unavailable. In this manner, through the use of proper administrative controls, functional testing of the snubbers can be accomplished without violating the existing Technical Specifications.
Conclusion:
The proposed change upgrades the surveillance inspection and testing of snubbers and therefore will increase the confidence level that snubbers on safety-related systems will perform as required to restrain movements during earthquakes and still allow normal movements due to thermal expansion. 'This confidence level will be offset slightly due to the fact 7 that portions of safety-related systems may be inoperable during functional' testing of the snubbers. However the proposed change will not introduce any'new or affect the consequences of previously-analyzed accidents. Therefore, this change does not. constitute an unreviewed safety question.
cj d/7
-f f
,' A sf .)
+ Y 4
m Significant Hazard Consideration
.The proposed amendment request for mechanical and hydraulic snubbers does not. represent a Significant Hazard.
The amendment would revise the testing requirements for hydraulic shock suppressors (snubbers) and add requirements for mechanical snubber operability and testing. The proposed changes were made in response to an NRC request to upgrade the testing requirements for all safety-related snubbers to ensure a higher degree of operability. The changes involve:
clarifying the frequency for visual-inspections, stating the requirements
.for' functional testing of snubbers which visually appear inoperable, adding a formula for the selection of representative sample sizes,
_ clarifying the testing acceptance criteria, and revising the method of snubber listing to incorporate more information.
The Commission has provided guidance concerning the application of the standards in 10CFR50.92 by providing certain examples (48FR14870). The examples of actions involving no significant hazards considerations include changes that' constitute additional limitations or restrictions.in the Technical Specifications. The proposed changes revise sections of the
' Technical Specifications related to hydraulic snubbers to clarify requirements and_ include additional testing, and incorporate both operability and testing requirements for mechanical snubbers.
Based on the-above information, this amendment request would not (1)-involve a significant increase in the probability or consequences of
~
- an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated;_ or (3) involve a significant re' duction in a margin of safety.
~Therefore, based on the above, the requested license amendment does not present a-Significant Hazard.
%