PNO-II-85-122:on 851228,surveillance Test Determined That Unit 1 RCS Unidentified Leak Rate to Be Approx 0.28 Gpm in Excess of 1.0 Gpm TS Limit.Leakage Suspected to Be Coming from in-core Thermocouple Electrical Connection Seal
ML20212F789
Person / Time
Site: North Anna Dominion icon.png
Issue date: 12/30/1985
From: Brownlee V, Elrod S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
References
PNO-II-85-122, NUDOCS 9711050090
Download: ML20212F789 (1)


_ _ _ _ - _ _ _ _ _ _ _ _

$)/L dt /i/uce 6/ uj **[.y /

December 30, 1985

\r LIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE PN0-II-85-122 Cds preliminary notification constitutes EARLY notice of events of POSSIBLE safety 'or public interest significance. The information is as initially received without verifi-cation or evaluation, and is basically all that is known by the Region 11 staff on this date.

FACILITY: Virginia Electric & Power Company Licensee Emergency Classification:

North Anna Unit 1 X Notification of Unusual Event Docket No. 50-338 Alert Mineral, Virginia Site Area Emergency General Emergency Not Applicable

SUBJECT:

SHUTOOWN IN EXCESS OF 48 HOURS At 9:30 p.m. on December 28 a survei' lance test determined the Unit I reactor coolant system (RCS) unidentified leak rate to be approximately 0.28 gailons per minute (gpm) in excess of the 1.0 gpm Technical Spet.ification (TS) limit.

The Unit was at 30% power conducting an ascent to full power following a refueling outage.

In compliance with the TS action statement, a power decrease was commenced at 5:55 a.m. on December 29; the Unit entered Mode 3 at 7:24 a.m. and Mode 4 at 8:49 p.m. A Unit cooldown is continuing with RCS temperature at 300*F at 8:00 a.m. on December 30. The leakage is ,

suspected to be coming from an in-core thermocouple electrical connection seal. Virginia ectric and Power Company (VEPCO) is planning a nine-day outage to repair the leak and an

'C' loop cold leg temperature element / manifold which had failed on December 24.

xegion II is monitoring VEFCO's repair efforts.

North Anna Unit 2 is operating at 100 percent power, ,

VEPC0 is prepared to respond to media inquiries.

The licensee informed the NRC headquarters incident response center of this occurrence by telephone at 6:08 a.m. on December 29.

This information is current as of 2:00 p.m.

Contact:

S. A. Elrod, 242-5536 V. Brownlee, 242-5583 ,

fW

()ll 4 61

,e< # e#

fk B 4

C/R Distribut  : Chm, Cmrs, PE, GC, CA, A S. 4fstorian, SECY, Records.

b9 _;di

~4 9711050090 851230 PDR I&E PNO-II-85-122 PDR l i

=_ _ _ - _ -___ _ _ _ - _ _ _ - _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __________________-_____-_________________A