Advises That Util Will Submit Entire Plant Performance & Mgt Improvement Program Action List on 870518,per Telcon W/Jb Martin & Listing of Asrtp Insp Items Scheduled for Resolution Before Restart on 870515,per J Callan Request
ML20214L831
Person / Time
Site: Rancho Seco
Issue date: 05/11/1987
From: Andognini G
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Martin J
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GCA-87-004, GCA-87-4, NUDOCS 8706010092
Download: ML20214L831 (2)


Text

l

. ,a w

  • esuun SACRAMENTO MUNICIPAL UTIUTY DISTRICT O P. O. Box 1583o, Sacramento CA 95852-1830,(910) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CAllFORNIA GCA 87-004 MAY 11 1987 J. B. Martin, Regional Administrator Region V Office of Inspection and Enforcement Attn: Document Control Desk U. S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596 DOCKET NO. 50-312 RANCllO SECO NUCLEAR GENERATING STATION LICENSE NO. DPR-54 DISTRICT RESTART COMMITMENTS AND ASRTP RESOLUTION SCIIEDULE As part of our discussions at your office on April 28, 1987, you and your staff requested specific information as to what the District has committed to complete prior to the restart of Rancho Seco. The District submitted Revision 0 of its Restart Scope List on April 17, 1987 and will submit subsequent revisions to the list as appropriate. To clarify its position further, the District considers the Restart Scope List as the specific listing of items the District will complete prior to restart. Furthermore, the April 17 submittal provides a basis for discussion and concurrence by your staff on the District's plan for restart of the unit.

Also, in a subsequent telephone conversation, you suggested that the District submit its entire list of Plant Performance and Management Improvement Program (PP&MIP) actions. The District will submit the entire PP&MIP Action List on May 18, 1987.

Likewise, in our discussions, Mr. Joe Callan, NRC ASRTP Team Leader, requested a verification of District commitments relative to the 44 items in the ASRTP Inspection Report by May 1, 1987. As subsequently discussed with Mr. Callan, the l

8706010092 870511 PDR ADOCK 05000312 O PDR DISTRICT HEADQUARTERS O 62o1 S Street, Sacramento CA 95817-1899 lO S .Ab

GCA 87-004 J. B. Martin District is carefully evaluating in detail all 44 items.

Thus, the District will transmit to the NRC on May 15, 1987, a listing of the ASRTP items scheduled for resolution before restart. This listing will include.the District's review of items it verbally committed during the ASRTP exit, to resolve and those items stated in the ASRTP report the NRC believes the District had committed to complete prior to restart. The District's re-evaluation of these items may require further negotiations of those items where a difference in interpretation of the commitment exists. It is important to note, many of the items in the ASRTP report have already been processed through PP&MIP (QCI-12) and assigned an appropriate date for completion.

If you have any questions, please contact J. Vinquist of my staff at extension 4244.

Sincerely, YYb A

.CarlAbdognini

-Chief Executive Officer, Nuclear Attachment cc: G.- Kalman, NRC, Bethesda (2)