Revised Monthly Operating Rept for June 1995 for San Onofre Nuclear Generating Station Unit 2
ML20095G410
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 06/30/1995
From: Kaplan R
SOUTHERN CALIFORNIA EDISON CO.
To:
Shared Package
ML20095G399 List:
References
NUDOCS 9512210009
Download: ML20095G410 (1)


Text

_.

. NRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 2 DOCKET NO: 50-361 UNIT NAME: SONGS -2 DATE: July 14,1995 COMPLETED BY: R. L. Kaplan TELEPHONE: (714) 368-6834 OPERATING STATUS

1. Unit Name: San Onofre Nuclear Generating Station, Unit 2
2. Reporting Period: June 1995
3. Licensed Thermal Power (MWt) : 3390
4. Nameplate Rating (Gross MWe): 1127
5. Design Electrical Rating (Net MWe): 1070
6. Maximum Dependable Capacity (Gross MWe): 1127
7. Maximum Dependable Capacity (Net MWe) : 1070
8. If Changes Occur In Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons: NA

9. Power Level To Which Restricted, If Any (Net MWe): NA
10. Reasons For Restrictions, If Any: NA This Month Yr.-to-Date Cumulative
11. Hours In Reporting Period 720.00 4,343.00 104,040.00
12. Number of Hours Reactor Was Critical 720.00 2,223.00 78,997.59 l
13. Reactor Reserve Shutdown Hours 0.00 0.00 0.00
14. Hours Generator On-Line 631.72 1,815.32 77,446.66
15. Unit Reserve Shutdown Hours 0.00 0.00 0.00
16. Gross Thermal Energy Generated (MWH) 2,013,810.98 5,589,851.07 252,967,706.92
17. Gross Electrical Energy Generated (MWH) 67 9,18 8. 50 1,866,190.00 85,717,689.50
18. Net Electrical Energy Generated (MWH) 643,083.00 1,729,103.04 81,293,197.91
19. Unit Service Factor 87.74% 41.80% 74.44%
20. Unit Availability Factor 87.74% 41.80% 74.44%
21. Unit Capacity Factor (Using MDC Net) 83.47% 37.21% 73.02%
22. Unit Capacity Factor (Using DER Net) 83.47% 37.21% 73.02%
23. Unit Forced Outage Rate 12.26% 4.64% 5.48%
24. Shutdowns Scheduled Over Next 6 Months (T ype , Date, and Duration of Each):

> 25. If Shutdown At End Of Report Period, Estimated Date of Startup:

26. Units In Test Status (Prior To Commercial Operation): Forecast Achieved INITIAL CRITICALITY NA NA INITIAL ELECTRICITY NA NA COMMERCIAL OPERATION NA NA

)

l 1

1 i

1 l 9512210009 951214 1 PDR ADOCK 05000361 i R PDR 1

. - - - -_ . - _ - _ _ _ __ _ - . .\