Revised Monthly Operating Rept for May 1995 for San Onofre Nuclear Generating Station Unit 2
ML20095G405
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 05/31/1995
From: Kaplan R
SOUTHERN CALIFORNIA EDISON CO.
To:
Shared Package
ML20095G399 List:
References
NUDOCS 9512210008
Download: ML20095G405 (1)


Text

.

NRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 2 DOCKET NO:

50-361

(

UNIT NAME:

SONGS - 2 i

DATE:

June 14, 1995 COMPLETED BY:

R.

L.

Kaplan TELEPHONE:

(714) 368-6834 OPERATING STATUS 1.

Unit Name:

San Onofre Nuclear Generati..g Station, Unit 2 2.

Reporting Period:

May 1995 3.

Licensed Thermal Power (MWt) :

3390 4.

Nameplate Rating (Gross MWe):

1127 5.

Design Electrical Rating (Net MWe):

1070 6.

Maximum Dependable Capacity (Gross MWe):

1127 7.

Maximum Dependable Capacity (Net MWe):

1070 l

8.

If Changes Occur In Capacity Ratings (Items Number 3 Through 7)

Since Last-Report, Give Reasons:

NA 9.

Power Level To Which Restricted, If Any (Net MWe):

NA 10.

Reasons For Restrictions, If Any:

NA This Month Yr.-to-Date Cumulative 11.

Hours In Reporting Period 744.00 3,623.00 103,320.00 12.

Number Of Hours Reactor Was Critical 464.35 1,503.00 78,277.59 l 13.

Reactor Reserve Shutdown Hours 0.00 0.00 0.00 14.

Hours Generator On-Line 199.28 1,183.60 76,814.94 15.

Unit Reserve Shutdown Hours 0.00 0.00 0.00 16.

Gross Thermal Energy Generated (MWH) 484,128.30 3,576,040.10 250,953,895.94 17.

Gross Electrical Energy Generated (MWH)115,641.50 1,187,001.50 85,038,501.00 18.

Net Electrical Energy Generated (MWH) 86,559.00 1,086,020.04 80,650,114.91 19.

Unit Service Factor 26.78%

32.67%

74.35%

20.

Unit Availability Factor 26.78%

32.67%

74.35%

21.

Unit Capacity Factor (Using MDC Net) 10.87%

28.01%

72.95%

22.

Unit Capacity Factor (Using DER Net) 10.87%

28.01%

72.95%

23.

Unit Forced Outage Rate 0.00%

0.00%

5.42%

24.

Shutdowns ~ Scheduled over Next 6 Months (Type, Date, and Duration of Each):

25.

If Shutdown At End Of Report Period, Estimated Date of Startup:

26.

Units In Test Status (Prior To Commercial Operation): Forecast Achieved INITIAL CRITICALITY NA NA INITIAL ELECTRICITY NA NA COMMERCIAL OPERATION NA NA 1

9512210008 951214 ADOCK0500ggi DR