Forwards post-defueling Plan, TMI-2 Cleanup Program,Post- Defueling Monitoring Storage, Per 860114 Commitment.Environ Evaluation of Plan Will Be Submitted in Jan 1987
ML20214S394
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 12/02/1986
From: Standerfer F
GENERAL PUBLIC UTILITIES CORP.
To: Travers W
Office of Nuclear Reactor Regulation
Shared Package
ML20214S397 List:
References
4410-86-L-0201, 4410-86-L-201, NUDOCS 8612080274
Download: ML20214S394 (2)


Text

.

GPU Nuclear Corporation g g{ Post Office Box 480 Route 441 South Middletown, Pennsylvania 17057-0191 717 944 7621 TELEX 84 2386 Writer's Direct Dial Nurnber:

(717) 948-8461 4410-86-L-0201 Document ID 0138P December 2, 1986 TMI-2 Cleanup Project Directorate Attn: Dr. W. D. Travers Director US Nuclear Regulatory Commission c/o Three Mile Island Nuclear Station Middletown, PA 17057

Dear Dr. Travers:

Three Mile Island Nuclear Station, Unit 2 (TMI-2)

Operating License No. DPR-73 Docket No. 50-320 TMI-2 Cleanup Program - Post-Defueling Monitored Storage (PDMS)

During the meeting between GPU Nuclear senior management and the Nuclear Regulatory Commission on January 14, 1986, post-defueling plans for the damaged Three Mile Island Unit 2 reactor were discussed. At that time, we committed to provide a plan for plant conditions following completion of the Cleanup Program. Attached is a copy of that plan entitled "TMI-2 Cleanup Program - Post-Defueling Monitored Storage."

The planned PDMS configuration described in the attached document is a safe, stable, and secure plant condition which poses no risk to the health and safety of the public. The plant will be secured, monitored and maintained.

The remaining amount and location of nuclear fuel will preclude nuclear criticality. Potential off-site exposures will be well below 10 CFR 50, Appendix I guidelines.

As previously discussed with you, this plan will be a principal topic at the upcoming meeting of the Advisory Panel for the Decontamination of the Three l Mile Island Unit 2 on December 10, 1986, at Harrisburg, PA.

8612090274 861202 l PDR ADOCK 05000320 06a7 F PDR 8 e L

GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation i

Dr. Tr;v;rs- December 2, 1986

. 4410-86-L-0201 An " Environmental Evaluation of TMI-2 Post-Defueling Monitored Storage" will be submitted for your consideration in January 1987 as input to your planned supplement to the Programmatic Environmental Impact Statement. Appropriate License and Technical Specification Change Requests in support of the PDMS plan will be submitted for your approval beginning in the First Quarter of 1987.

Sincerely, y-

. R. Standerfe Vice President / Director, TMI-2 FRS/RER/eml Attachment I