'4 GPU Nuclear Corporation I
Nuclear miom,,s*
1 o
- Middletown, Pennsylvania 17057 0191 j
717 944 7621.
TELEX % 2386 1
Writer 1 Direct Olal Number:
d
. Febnary 23,-1990 4
C311-90-2021 U. S. Nuclear. Regulatory Commission Attn: Document Control. Desk -
Washington, DC 20555
Dear Sir:
Three Mile Island Nuclear Station, Unit 1. (TMI-1)-
Operating License No. DPR-50 Docket No. 50-289 OTSG Tubes' Post Inservice' Inspection Report For Refueling Interval BR Technical Specification section 4.19.5.a requires reporting to the NRC, within-15 days following the completion of each inservice inspection of steam.
generator tubes, the number of tubes repaired or removed from service in each steam generator.
During the current refueling interval _8R eddy current inspection,- a total of _
4 eight.(8) tubes' were removed from service by plugging. - Specifically, five.-(5) i tubes were plugged in' steam generator "A", and three-(3) tubes were plugged in-steam generator "B".
The. plugging was completed on February 16, 1990.
Since fabrication, a total of 1265 tubes have.been removed from service in steam generator "A", and 3?O tubes in steam generator"B".
This letter fulfills the requirements of 'the above cited Technical Specification Section.
Sincerely
/
ki 1
Vice President & Director, TMI HDH/EP/lt:2021 l
cc:
F. Young (NRC) 0 R. Hernan (NRC)
Ii L
W. Russell (NRC) g0 g
l GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation '