Issue date | Title | Topic | |
---|---|---|---|
ML20217D836 | 11 October 1999 | Provides NRC with Summary of Activities at TMI-2 During 3rd Quarter of 1999 | |
ML20217F827 | 7 October 1999 | Forwards Pmpr 99-13, CNWRA Program Manager Periodic Rept on Activities of CNWRA, for Fiscal Reporting Period 990828- 0924.Diskette Containing Pmpr in Wordperfect 8 Is Encl. All Variances Are Expressed with Regard to Current Plans | |
ML20216J658 | 28 September 1999 | Provides Info as Requested of Licensees by NRC in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams | Generic Fundamentals Examination |
ML20212E197 | 16 September 1999 | Forwards Rev 11 of Gpu Nuclear Operational QAP, Reflecting Organizational Change in Which Functions & Responsibilities of Nuclear Safety & Technical Support Div Were Assigned to Other Divisions | |
ML20212A210 | 13 September 1999 | Forwards Rev 3 of Gpu Nuclear Post-Defueling Monitored Storage QAP for Three Mile Island Unit 2, Including Changes Made During 1998.Description of Changes Provided on Page 2 | |
ML20216G415 | 9 September 1999 | Forwards Pmpr 99-12, CNWRA Program Manager Periodic Rept on Activities of CNWRA, for Fiscal Reporting Period 990731- 0827.All Variances Expressed with Regard to Current Operations Plans | |
ML20211M586 | 2 September 1999 | Forwards non-proprietary & Proprietary Response to NRC 990708 RAI Re TS Change Request 272,reactor Coolant Sys Coolant Activity.Proprietary Encl Withheld | Affidavit |
ML20211M659 | 1 September 1999 | Forwards Errata Page to 990729 Suppl to TS Change Request 274,to Reflect Proposed Changes Requested by . Page Transmitted by Submitted in Error | |
ML20211L240 | 1 September 1999 | Submits Response to NRC AL 99-02, Operator Reactor Licensing Action Estimates | |
ML20211H373 | 27 August 1999 | Responds to NRC 990810 RAI Re TMI LAR 285 & TMI-2 LAR 77 Re Changes Reflecting Storage of TMI-1 Radioactive Matls in TMI-2 Facility.Revised License Page mark-up,incorporating Response,Encl | Scaffolding |
ML20211H400 | 27 August 1999 | Responds to NRC 990810 RAI Re TMI-1 LAR 285 & TMI-2 LAR 77 Re Changes to Clarify Authority to Possess Radioactive Matls Without Unit Distinction.Revised License Page mark-up, Incorporating Response Encl | Scaffolding |
ML20211K239 | 23 August 1999 | Forwards fitness-for-duty Performance Data Repts for TMI, Oyster Creek & Corporate Headquarters Located in Parsippany, Nj | Fitness for Duty |
05000289/LER-1999-007, Forwards LER 99-007-01 Re Increasing Failure Rate of ESAS Relays.Rept Supplements Preliminary Info Re Determination of Root Cause & Long Term Corrective Actions.Changes Made for Supplement Are Indicated in Bold Typeface | 20 August 1999 | Forwards LER 99-007-01 Re Increasing Failure Rate of ESAS Relays.Rept Supplements Preliminary Info Re Determination of Root Cause & Long Term Corrective Actions.Changes Made for Supplement Are Indicated in Bold Typeface | |
ML20211H504 | 20 August 1999 | Forwards Proprietary & non-proprietary Rept MPR-1820,rev 1, TMI Nuclear Generating Station OTSG Kinetic Expansion Insp Criteria Analysis. Affidavit Encl.Proprietary Rept Wihheld | Affidavit |
ML20211H357 | 19 August 1999 | Forwards Itemized Response to NRC 990712 RAI Re TS Change Request 248 Re Remote Shutdown Sys,Submitted on 981019 | Safe Shutdown |
ML20211A393 | 12 August 1999 | Requests NRC Concurrence with Ongoing Analytical Approach as Described in Attachment,Which Is Being Utilized by Gpu Nuclear to Support Detailed License Amend Request to Revise Design Basis for TMI-1 Pressurizer Supports | Earthquake |
ML20210R469 | 11 August 1999 | Forwards Update 3 to Post-Defueling Monitored Storage SAR, for TMI-2.Update 3 Revises SAR to Reflect Current Plant Configuration & Includes Minor Editorial Changes & Corrections.Revised Pages on List of Effective Pages | |
ML20210L383 | 30 July 1999 | Responds to NRC 990617 RAI Re OTSG Kinetic Expansion Region Insp Acceptance Criteria That Was Used for Dispositioning Indications During Cycle 12 Refueling (12R) Outage | Stress corrosion cracking Eddy Current Test |
ML20210K737 | 30 July 1999 | Forwards Rev 2 to 86-5002073-02, Summary Rept for Bwog 20% Tp LOCA, Which Corrects Evaluation Model for Mk-B9 non- Mixing Vane Grid Previously Reported in Util to Nrc,Per 10CFR50.46 | |
ML20210L115 | 28 July 1999 | Confirms Two Senior Management Changes Made within Amergen Energy Co,Per Proposed License Transfer & Conforming Administrative License Amends for TMI-1 | |
05000289/LER-1999-009, Forwards LER 99-009-00 Re 990626 Event Involving Partial Loss of Offsite Power & Subsequent Automatic Start of EDG 1A.Commitments Made by Util Are Contained in long-term Corrective Actions Section | 22 July 1999 | Forwards LER 99-009-00 Re 990626 Event Involving Partial Loss of Offsite Power & Subsequent Automatic Start of EDG 1A.Commitments Made by Util Are Contained in long-term Corrective Actions Section | |
ML20216D400 | 22 July 1999 | Provides Summary of Activities at TMI-2 During 2nd Quarter of 1999 | |
ML20210G947 | 15 July 1999 | Forwards Pmpr 99-10, CNWRA Program Manager Periodic Rept on Activities of CNWRA, for Fiscal Reporting period,990605- 0702.Diskette Containing Pmpr in Wordperfect 8 Format Is Also Encl | |
ML20212K170 | 13 July 1999 | Submits Concerns Re Millstone & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Should Provide Adequate Emergency Planning in Case of Radiological Accident | Chernobyl |
05000289/LER-1999-008, Forwards LER 99-008-00 Re Discovery of Degraded But Operable Condition of RB Emergency Cooling Sys.Condition Did Not Adversely Affect Health & Safety of Public | 2 July 1999 | Forwards LER 99-008-00 Re Discovery of Degraded But Operable Condition of RB Emergency Cooling Sys.Condition Did Not Adversely Affect Health & Safety of Public | Boric Acid |
ML20196J398 | 1 July 1999 | Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Y2K Readiness Disclosure for TMI-1 Encl | |
ML20209C113 | 1 July 1999 | Forwards Signed Agreement as Proposed in NRC Requesting Gpu Nuclear Consent in Incorporate TMI-1 Thermo Lag Fire Barrier Final Corrective Action Completion Schedule Commitment of 000630 Into Co Modifying License | Fire Barrier |
ML20196J765 | 29 June 1999 | Provides Updated Info Re Loss of Feedwater & Loss of Electric Power Accident Analyses to Support TS Change Request 279 Re Core Protection Safety Limit,As Discussed at 990616 Meeting | Shutdown Margin Fuel cladding |
ML20196J770 | 29 June 1999 | Forwards LAR 285 for License DPR-50,clarifying Authority to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matls May Continue to Be Moved Between TMI-1 & TMI-2 Units | |
ML20209C039 | 29 June 1999 | Forwards LAR 77 to License DPR-73,clarifying Authority to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-2 License to Amergen,Radioactive Matl May Continue to Be Moved Between TMI-1 & TMI-2 Units | |
ML20196G206 | 23 June 1999 | Requests That NRC Update Current Service Lists to Reflect Listed Personnel Changes That Occurred at TMI | |
05000289/LER-1999-006, Forwards LER 99-006-00,providing Complete Description,Extent of Condition & Actions Taken in Association with Determination of Inability of Pressurizer Support Bolts to Meet FSAR Requirements | 23 June 1999 | Forwards LER 99-006-00,providing Complete Description,Extent of Condition & Actions Taken in Association with Determination of Inability of Pressurizer Support Bolts to Meet FSAR Requirements | |
ML20196D217 | 17 June 1999 | Forwards Pmpr 99-9, CNWRA Program Manager Periodic Rept on Activities of CNWRA, for Fiscal Reporting period,990508- 0604.New Summary Personnel Table Was Added to Rept Period.Matl Scientist Joined Staff Period | |
ML20196A043 | 15 June 1999 | Providess Notification That Design Verification Activities Related to Calculations Supporting Analytical Values Identified in Gpu Nuclear Ltr to NRC Has Been Completed | |
05000289/LER-1999-004, Forwards LER 99-004-00,re Discovery of Emergency FW Pump Bearing Failure During Performance of Oil Change on 990510. Event Was Determined Reportable IAW 10CFR50.73,since Pump Was Determined to Be Inoperable Longer than TS AOT | 9 June 1999 | Forwards LER 99-004-00,re Discovery of Emergency FW Pump Bearing Failure During Performance of Oil Change on 990510. Event Was Determined Reportable IAW 10CFR50.73,since Pump Was Determined to Be Inoperable Longer than TS AOT | |
ML20212K254 | 8 June 1999 | Submits Concerns Re Millstone NPP & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Requests That NRC Provide Adequate Emergency Planning in Case of Radiological Accident | Chernobyl |
ML20212K267 | 8 June 1999 | Submits Concerns Re Millstone NPP & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Requests That NRC Provide Adequate Emergency Planning in Case of Radiological Accident | Chernobyl |
ML20195E275 | 4 June 1999 | Informs That PCTs & LOCA Lhr Limits Submitted in Util Ltr for LOCA Reanalysis Performed in Support of TMI-1 20% Tube Plugging Amend Request Have Been Revised.Revised PCT & LOCA Lhr Limit Values Are Provided on Encl Table 1 | |
ML20195E328 | 4 June 1999 | Forwards Application for Amend to License DPR-50,modifying Conditions Which Allow Reduction in Number of Means for Maintaining Decay Heat Removal Capability During Shutdown Conditions | |
ML20195C572 | 2 June 1999 | Forwards Description of Gpu Nuclear Plans for Corrective Actions for 1 H Fire Barriers in Fire Zones AB-FZ-3,AB-FZ-5, AB-FZ-7,FH-FZ-2 & Previous Commitments for Fire Zones CB-FA-1 & FH-FZ-6 | Fire Barrier |
ML20207E256 | 25 May 1999 | Submits 30-day Written Rept on Significant PCT Change in ECCS Analyses at TMI-1 | |
ML20195B246 | 21 May 1999 | Forwards Itemized Response to NRC 990506 RAI for TS Change Request 279 Re Core Protection Safety Limit | High Energy Line Break |
ML20206R646 | 13 May 1999 | Forwards Rev 39 of Modified Amended Physical Security Plan for TMI | |
05000289/LER-1999-003, Forwards LER 99-003-00, Discovery of Condition Outside UFSAR Design Basis for CR Habitability, Which Was Determined Reportable on 990310.Rept Is Being Submitted Four Weeks Later than Required,Per Discussion with NRC | 7 May 1999 | Forwards LER 99-003-00, Discovery of Condition Outside UFSAR Design Basis for CR Habitability, Which Was Determined Reportable on 990310.Rept Is Being Submitted Four Weeks Later than Required,Per Discussion with NRC | Control Room Habitability |
ML20206K630 | 7 May 1999 | Provides Addl Info Re TMI-1 LOFW Accident re-analysis Assumptions for 20% Average SG Tube Plugging as Discussed on 990421 | |
ML20206H078 | 30 April 1999 | Forwards Rev 0 to 1092, TMI Emergency Plan. Summary of Changes Encl | Safe Shutdown Health Physics Network Shutdown Margin High Radiation Area Emergency Lighting Earthquake Fire Protection Program Inadvertent Siren Activation Siren Exclusive Use |
ML20206J481 | 30 April 1999 | Provides Summary of Activities at TMI-2 During First Quarter of 1999.TMI-2 RB Was Not Inspected During Quarter.Routine Radiological Surveys of Auxiliary & Fuel Handling Bldgs Did Not Identify Any Significant Adverse Trends | |
ML20206E412 | 27 April 1999 | Requests That TS Change Request 257 Be Withdrawn | |
ML20206C521 | 23 April 1999 | Requests Mod to Encl Indemnity Agreement Number B-64,on Behalf of Gpu & Affiliates,Meed,Jcpl,Penelec & Amergen Energy Co,Llc.Ltr Supersedes & Withdraws 990405 Request Submitted to NRC | |
ML20206C826 | 22 April 1999 | Submits Financial Info IAW Requirements of 10CFR50.71(b) & 10CFR140.21 | Incorporated by reference Uranium Hexafluoride |