ML20237G905

From kanterella
Revision as of 22:03, 24 January 2021 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Forwards Action Plan for Restart,Rept for Month of May 1987
ML20237G905
Person / Time
Site: Rancho Seco
Issue date: 06/29/1987
From: Andognini G
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GCA-87-321, NUDOCS 8708240291
Download: ML20237G905 (2)


Text

i

$)suun

~

SACRAMENTO MUNICIPAL UT UTY DISTRICT C P. o. Box 15830, Sar.ramento CA flECgED 95852-1830.(916) 452-321[:

AN ELECTRIC SYSTEM SERVING THE HEARMO{CA(lFOAJia 31 flEGICH '!

June 29, 1987 GCA 87-321 Mr. J. B. Martin, Regional Administrator Regional V Office Inspection and Enforcement ,

U. S. Nuclear Regulatory Commission '

1450 Maria Lane, Suite 210 Walnut Creek, California 94596

Dear Mr. Martin:

SUBJECT:

ACTION PLAN MONTHLY PROGRESS REPORT - MAY 1987 This monthly report on the status of the Action Plan for Performance Improvement at Rancho Seco covers activities during the month of May 1987.

As of May 31, 1987, 2199 employees and contractors were implementing the program action items which cover a wide spectrum of modification, maintenance, inspection, training, procedures development, administrative and management improvement issues. The goal is improved safety, reliable operation, increased productivity and a planned reduction in contractor dependency.

The attached report is intended to keep you, as holders of our Action Plan, current on our progress.

Sincerely, G. Carl Andognini h b.

Chief Executive Officer, Nuclear Enclosure cc: NRC - Rancho Seco RIC Files 4th Floor Files B708240291 DR ADDCK %PDRhi2 7'"- C f RANCHO SECO NUCLEAR GENERATING STATION O 14440 Twin Cities Road, Herald, CA 95638-9799;(209) 333 2935

$: ACTION PLAN MONTHLY PROGRESS REPORT

^

CONTENTS I. Highlights II. Introduction III. Action Plan Progress

.1 Changes and Revisions to the Action Plan

.2 New Issues Affecting Restart

.3 Systematic Assessment Program

.4 Management. Operations, and Administration

.5 Plant Modifications and Maintenance Improvements

.6 Systems Review and Testing Program

.7 Non-Action Plan Related Activities

.8 Resource Commitments and Utilization

.9 Schedule

. s

J

f-p RANCHO SECO.

ACTION PLAN FOR RESTART REPORT FOR THE MONTH OF MAY, 1987 Prepared By:

Rancho Seco Staff J

@ 707, l C[A

- -m 1-c I i c"o ,

I. HIGHLIGHTS

  • Completion of the 'A' Decay Heat Outage represents one of the most significant Restart Milestones attained to date. The

' outage was completed on May 27, 1987, whenithe 'A' Train of the Decay Heat System was ceclared operable foliowing nearly two months of maintenance /and modifications wort

  • An outage of the >3' Train 9f the Decay Heat System was started in May. Modifications work completed under the outage.during May includes modification of pipe supports and installation of a Post Accident Sampling System sampling line. Maintenance work started in May includes 'B' Train Motor Operated Valve refurbishment, Nuclear Raw Hater pump motor refurbishment, Nuclear Service Electrical Bus maintenance and Emergency Diesel Generator maintenance and upgrades.
  • Eight snubbers and five motor operated valves were refurbished in a short " Common" Train Decay Heat Outage.
  • The System Review and Test Program made additional ' testing progress this month with completion of the following tests; Control Room HVAC (STP-779, 1059, 1061 and M-lll), 'BB' Battery Discharge Test and Load Shedding Control Switch Testing (STP 980).
  • Site staffing levels have been dropped to 2199. ,

SUMMARY

Restart is progressing in accordance with the Action Plan. The NRC and other industry agencies are working closely with us to insure that our commitments meet their needs and will support a safe Restart.

II. INTRODUCTION This report highlights the progress in implementing the " Action Plan for Performance Improvement" at the Rancho Seco Nuclear Generating, Station. This report covers the month of May, 1987.

m

0 III. ACTION PLAN PROGRESS

1. Chances and Revision to the Action Plan The expanded System Review and Test Program (SRTP) is l functioning with assigned Systems Engineers for each system.

The SRTP consolidates the input from the Plant Performance and l Management Improvement Program (PP&MIP) with the system reviews performed by the Systems Engineer and develops a systems testing ,

i program to demonstrate plant material readiness.

The entire Quality Tracking System (QTS) database is being overhauled by a task force under an assigned project manager.

When this is complete, the aggregate of identified QTS items to be accomplished before restart will comprise the " Scope" of the restart effort. This.information will be issued as a portion of the Restart Action Plan Report.

2. New Issues Affectina Restart e An additional 30 cables were added to the list of 241 cables which were " walked down" to determine proper design location. The increase in sample size to 271 cables was a result of discrepancies found in the 240th cable inspected.
  • The reliability of l'03 motor operated (MOVs) valves in safety related systems continues to be an important issue. There are 107 MOVs that require refurbishment and 64 are complete. The MOV program is ahead of schedule.
3. Systematic Assessment Proaram This program provides the input to the QCI-12 " Plant Performance and Management Improvement Program" (PP&MIP). The program is-essentially complete, as shown in the following discussion of each input area.
a. December 26. 1985 Event Analysis i

A total of 150 analyses, studies, repairs. and l modifications were initiated to investigate and recover from the overcooling event. These resulted in approximately 400 recommendations, which have been identified by the respective managers and system engineers for closure.

b. Precursor Review f A total of 1396 documents, applicable to Rancho Seco, have been reviewed to determine the appropriateness of previous reviews and implementing actions. These also are reflected in management and system-related work lists.

10 111. ACTION PLAN PROGRESS (Continued)

Deterministic Failure Consequence Analysis l c.

i 'l This portion of the program generated a series of items l

which will be closed before Restart. These analyses I documented the effect of component failure on system operation, as well as the synergistic effects upon other systems. A total of 1232 recommendations resulted from this analysis program.

d. Personnel Interviews Interviews with plant personnel resulted in 1631 recommendations and generated actions to be completed prior to Restart.
e. SHQG The program inputs thus far total 154 recommendations out of 174 currently listed. The remaining inputs will be evaluated according to the QCI-12 process when they are officially received.
4. Manaaement. Ooeretions and Administration.
a. Changes in Supervisory and Management Staff:

Efforts are continuing to identify permanent SHUD management individuals for every key position. Both NRC and SHUD realize the importance of employing these managers prior to Restart so that they may function as a cohesive team. The four SHUD Directors reporting to the Assistant General Managers have been named.

b. Changes in Organizational Structure:

Efforts are in full stride to implement the " Ultimate" or permiinent nuclear organization by staffing of all nuclear management positions with SHUD people.

5. Plant Modifications and Maintenance Improvements Actual work is underway on most of the identified modification and maintenance projects. Many items have been completed to support schedule milestones.
6. Systems Review and Test Procram Implementation of the programmatic structure has been initiated with several system related tests completed. Detailed test procedures are being developed.

~

r

- g- -. ..

p III. ACTION PLAN PROGRESS (Continued)

~

7. Non-Action Plan Related Activities The second phase of the Foothills Fault Seismic Design Study contract has been let to Bechtel Corporation to perfonn additional trenching. Expected completion is August, 1987.
8. Resource Commitments and Utilization As a part of the expansion necessary to support the Action Plan, implementation programs have been strengthened or put in place to provide improved management information and control of activities and resources. These efforts allow for the budgeting and allocation of resources, where necessary, to accomplish the commitments of the Action Plan.

During the month of May, 1987, the total staff assigned to the Nuclear Organization decreased by about 10%. On May 30, 1987, there were 855 SMUD employees and 1344 consultant /other

- contractors assigned to the nuclear organization with a small number of SMUD and consultant personnel assigned to various locations other than Rancho Seco.

Approximate overtime utilization of the staff during the month of April as a percentage of straight time hours worked is as follows:

SMUD 11%

Craft Labor 15%

Consultants /Other Contractors 11%

(located at Rancho Seco and submitting site timesheets)

As of May 31, 1987, a total of 2199 people were directly supporting Rancho Seco and the restart effort. On a typical day-shift, approximately 1,800 people are physically present within the security fence.

9. Schedule There exists potential for schedule delay due to:
a. Decay Heat System repairs
b. Cable routing discrepancies
c. Failures during system tests i
d. Delays in the regulatory process l

l e. MOV problems.

1