Forwards Draft Safety Evaluation Re Assessment of TVA Welding Program.Response to Open Issues Identified in Evaluation Requested within 3 Wks of Ltr Date.Particular Attention Should Be Made to Listed Items
ML20214D840
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 11/14/1986
From: Youngblood B
Office of Nuclear Reactor Regulation
To: White S
TENNESSEE VALLEY AUTHORITY
Shared Package
ML20214D842 List:
References
NUDOCS 8611240271
Download: ML20214D840 (3)


Text

.

7 G .Q 4

fur f, UNITED STATES f.) m i NUCLEAR REGULATORY COM511SSION r, o j WASHINGTON, D. C. 20555

...... /

%, ~

Eccket hos.: 50-327 1 and 50-328 Mr. S. A. White flanager of Nuclear Power Tennessee Valley Authority 6N 38A Lcokcut Place 1101 Market Street Chattanooga, Tennessee 37402-2801

Dear fir. White:

SUBJECT:

Transmittal of Draf t Cocy of the Evaluation on Uelding for Sequoyah Units 1 and 2 l

Enclosed.is a craft copy of the staff safety evaluation on welding for Sequoyah, Units 1 and 2. The staff intends to incorporate this evaluation into the Safety Evaluation Report (SER) en Volurre 2 of Nuclear Perfomance Plan which addresses Sequoyah. The purpose of this letter is to transmit the encloseo evaluation and request that the Tennessee Valley Authority (TVA) respond to the ccen issues identified in the report.

TVA should pay particular attention to the folicwing:

(1) Confirm that the remaining two irregularities identified in Inspection Report Nos. 50-327/86-33 and 50-328/86-33 are encompassed in ycur on-going program for the reconciliation of drawings as discussed in Section III, 3.0 of Volurre 2. (See page 11)

(2) Identify how the TVA welding program will be revised to meet the ao-plicable requirements 10 CFR 50, Appendix 8 and the TVA topical quality assurance program. (See page 12 and 13)

(3) Prior to restart, provide the TVA position on the augmented ten-year inservice inscection program as described in the "Recormendations" section of the report. (See cage 17)

(4) Discuss how TVA plans to address those additional staff recontendations identified on page 18 of the evaluation.

In order for the staff to suppcrt the projected restart date for Sequoyah, TVA should provide the additional informatter within three weeks of the date of this letter. Any items which affect the Sequoyah Nuclear Performance Flen should be provided under oath or a#firmation as revised pages to the Plan.

If you can not meet this date, you should provide your proposed schedule in writing within seven days cf the date of this letter.

8611240271 861114 PDR ADOCK 05000327 p PDR

~

, 14 NOV 1936

-2

  • If you require any additional assistance, please contact the project manager for the Sequoyah SER, Mr. Joseph J. Holonich at FTS 492-7270.

Sincerely, B.J. Ycungblood, Director PWR Project Directorate #4 Division of Pl!R Licensing-A

Enclosure:

As stated cc: See next page JUSTDIBILIR:

(Docket F O flRC PDR Local FDR FRC System NSIC PWR#4 Reading MDuncan BJYounablced Peading TAlexion TVA0P(3)S.RichardsonAR5029 HDenton JTaylor BHayes GZech, RII hGrace LSpessard KBarr SAConnelly DPuller Tf:ovak BJYoungblood JHolonich CStable Tkenyon WLong BKSingh KHooks ACPS (10)

OGC JPartlow BGrimes EJordan TPoindexter MReinhart, AP.

a Pl!R PWR-A g EB/ A P1Nid DPWR-A JH ich/ rad D a1 k BJYo gblood 11/f/86 11 df /86 1)3/86 11/[ 86 DD/IE RLSpessard @ e6 11/h/86.g.

-e J If yev require any additional assistance, please contact the project manager for the Sequoyah SER, Mr. Joseph J. holonich at FTS 492-7270.

Sincerely, ,

/

Col,j r' /

B. . Yq ngblood, Director PWR Pr4 ject Directorate f4 Division of PPR Licensing-A

Enclosure:

As stated cc: See next page