Monthly Operating Repts for Jan 1980
ML17208A454
Person / Time
Site: Saint Lucie, Turkey Point  NextEra Energy icon.png
Issue date: 02/09/1980
From: CHILSON V T
FLORIDA POWER & LIGHT CO.
To:
Shared Package
ML17208A453 List:
References
NUDOCS 8004180528
Download: ML17208A454 (5)


Text

SUMMARY

OF OPERATING EXPERiENCE DOCKET NO~50-250 Turkey Point UNIT Unit No.3 DATE Feb.9 1980 COMPLETED BY'.T.Chilson TELEPHONE (305)552-3824 REPORT MONTH JANUARY, 1980 Unit No.3 scheduled refueling, maintenance, and inspections continued during month.Outage was extended to repair, failed mechanical seal on reactor coolant pump No.3C.Refer to"Unit.Shutdowns and Power Reductions" section of the January, 1980, Operating Status Report.for additional information.

jor Safety-related maintenance activities performed during the month included: Per formed periodic integrated Sa f eguards Surveil-lance Test.Repaired failed mechanical seal on reactor coolant pump No.3C.Inspections and requirements of IE Bulletins and NUREG-0578 continued.

Florida Power&Light Company commitments for NUREG-0578 implementation

's continuing.

Refer to correspondence between FPL and NRC for ad-ditional information.

Completed performance of Steam Generator Tube Inspection Program.

SUMMARY

OF OPERATING EXPERIENCE DOCKET'NO-50-251 UNIT Turkey Point Unit No.4 DATE Feb.9 1980 COMPLETED BY V.T.Chilson REPORT MONTH JANUARY, 1980 TELEPHONE (305)552-3824 Unit No.4 operated at approximately 100%R.P., except for outages of Jan.19 and 26-27, 1980, and load reduction of Jan..23-24, 1980.Refer to"Unit Shutdowns and Power Reductions" section of the January, 1980, Operating Status Report for additional information.

Major Safety-related maintenance activities performed during the month included: Inspections and requirements of IE Bulletins and NUREG-0578 were performed during the month.Florida Power&Light Company commitments for NUREG-0578 implementation is continuing.

Refer to correspondence between.FP&L and NRC for additional information.

0 1

SUMMARY

OF OPERATiNG EXPERiENCE DOCKET NO 50>>335 UNiT St.Lucie Unit No.1 DATE Feb.9 1980 COMPLETED BY V.T.Chilson REPORT MONTH JANUARY, 1980 TELEPHOVj.

E 305)552-3824 Unit operated at approximately 100%R.P., except for outage of Jan.17, 1980, and load reductions of Jan.9-10, and 30-31, 1980.Refer to"Unit Shutdowns and Power Reductions"'ection of the January, 1980;Operating Status Report for additional information.

Major Safety-related maintenance activities performed during the month included: Florida Powe&Light Company commitments for NUREG-0578 implementation is continuing.

Refer to correspondence between FPGL and NRC for additional information.