Monthly Operating Repts for Aug 1998 for St Lucie,Units 1 & 2.With 980911 Ltr
ML17229A861
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 08/31/1998
From: Rogers J, Stall J
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
L-98-235, NUDOCS 9809170224
Download: ML17229A861 (10)


Text

CATEGORY 1 REGULATORY INFORMATXON DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:9809170224 DOC.DATE: 98/08/31 NOTARIZED: NO DOCKET I FACIL:50-335 St. Lucie Plant, Unit 1, Florida Power & Light Co. -05000335 50-389 St. Lucie Plant, Unit 2, Florida Power &. Light Co. 05000389 AUTH. NAME AUTHOR AFFILIATION ROGERS,J.A. Florida Power & Light Co.

STALL,J.A. Florida Power & Light Co.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating repts for Aug 1998 for St Lucie,Units 1 &

2.With 980911 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:.

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-3 PD 1 1 GLEAVES,W 1 1 INTERNAL: 1 1 AEOD/SPD/RRAB 1 1 E CENTER 01 1 1 OC/DBA/PAD 1 1 1 1 EXTERNAL: LITCO BRYCE,J H 1 1 NOAC 1 1 NRC PDR 1 1 D

0 N

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP. US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 10 ENCL 10

Florida Power 5 Light Company, 6501 South Ocean Drive, Jensen Beach. FL 34957 September 1 1, 1998 L-98-235 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Monthl 0 eratin Re ort Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the August 1998 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units 1 and 2.

Please contact us should there be any questions regarding this information.

Very truly yours, J. A. Stall Vice President St. Lucie Plant JAS/spt Attachments cc: Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, St. Lucie Plant fg~ pQ (

9809i70224 98083i poR Aoocx osooosss R PDR an FPL Group company

~ ~

DOCKET NO 50 - 335 UNIT NAME ST. LUCIE UNIT 1 DATE 09/08/98 COMPLETED BY J. A. ROGERS TELEPHONE 561/467/7296 REPORTING PERIOD: AUGUST 1998

1. Design Electrical Rating (Mwe-Net) 830
2. Maximum Dependable Capacity (Mwe-Net) 839 MONTH -YTD- CUMULATIVE
3. Number of Hours Reactor Critical ,744 5514.2 149040.5
4. Number of Hours Generator On Line 744 5464.5 147404.7
5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWH) 631185 4575846 119460905

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-335 UNIT: St. Lucie Pl DATE: Sep. 7, 1998 COMPLETED BY: S.A.ROGERS TELEPHONE: (561) 467-7296 tupoRTMONTH Unit 1 operated at essentially full power for the entire month of August.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-335 UNIT: St. Lucie 01 DATE Sep. 7, 1998 COMPLETED BY: J.A.ROGERS TELEPHONE: (561) 467-7296 REPORT MONTH ~Au st1998 Number Date TYPe Duration Reason Method of Cause & Corrective 1 (Hours) 2 Shutting Action to Down Prevent Recurrence Reactor3 Unit 1 operated at essentially full poem for the entire month of August F Forced Reason Method S Scheduled A - Equipment Failure texplain) l - Manual B - Maintenance or Test 2 - Manual Scram C Refueling 3 - Automatic Scram t) - Regulatory Restriction 4 - Continued E - Operator Training 4 License Examination S - Load Reduction F

G - Administrative Operational Error (Explain) 9 Other (Explain)

H Other t Explain) 091587 ppr

DOCKET NO 50 - 389 UNIT NAME ST. LUCIE UNIT 2 DATE 09/08/98 COMPLETED BY J. A. ROGERS TELEPHONE 561/467/7296 REPORTING PERIOD: AUGUST 1998

1. Design Electrical Rating (Mwe-Net) 830
2. Maximum Dependable Capacity (Mwe-Net) 839 MONTH -YTD- CUMULATIVE
3. Number of Hours Reactor Critical 744 5831 113072.5
4. Number of Hours Generator On Line 744 5801.9 111442.5
5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWH) 625985 4949264 91215657

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-3S9 UNIT: St. Lucie ¹2 DATE: Sep. 7, 1998 COMPLETED BY: J.A.ROGERS TELEPHONE: (561) 467-7296 HN ONT MONTH Unit 2 operated at essentially full power for the entire month of August.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

I UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-389 UNIT: St. Lucie 02 DATE: Sep. 7, 1998 COMPLETED BY: J.A.ROGERS TELEPHONE: (561) 467-7296 REPORT MONTH ~Au t 1998 Number Date TYPe Duration Reason Method of Cause & Corrective 1 (Hours) 2 Shutting Action to Down Prevent Recurrence Reactor3 Unit 2 operated at essentially full popover for the entire month of August.

F Forced Reason Method S Scheduled A - Equipment Failure texplain) 1 - Manual B Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 Other t Explain)

G - Operational Error tExplain)

H - Other tExplain) 091599 PPL