ML17265A429: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 09/30/1998
| issue date = 09/30/1998
| title = Monthly Operating Rept for Sept 1998 for Re Ginna Nuclear Power Plant.With 981009 Ltr
| title = Monthly Operating Rept for Sept 1998 for Re Ginna Nuclear Power Plant.With 981009 Ltr
| author name = WALDEN J V, WIDAY J A
| author name = Walden J, Widay J
| author affiliation = ROCHESTER GAS & ELECTRIC CORP.
| author affiliation = ROCHESTER GAS & ELECTRIC CORP.
| addressee name = VISSING G S
| addressee name = Vissing G
| addressee affiliation = NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
| addressee affiliation = NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
| docket = 05000244
| docket = 05000244

Revision as of 02:04, 19 June 2019

Monthly Operating Rept for Sept 1998 for Re Ginna Nuclear Power Plant.With 981009 Ltr
ML17265A429
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/30/1998
From: Walden J, Widay J
ROCHESTER GAS & ELECTRIC CORP.
To: Vissing G
NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9810190325
Download: ML17265A429 (8)


Text

CATEGORY 1 REGULA'I RY INFORMATIONDISTRIBUTION SYSTEM (RIDS)ACCESSION NBR,:9810190325 DOC.DATE: 98/09/30 NOTARIZED:

NO DOCKET I FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G 05000244 AUTH.NAME AUTHOR AFFILIATION WALDEN;J.p.'ochester Gas&Electric Corp.WIDAY,J.A.

Rochester Gas 6 Electric Corp.RECIP.NAME RECIPIENT AFFILIATION VISSING,G.S.

~

SUBJECT:

Monthly operating rept for Sept 1998 for RE Ginna Nuclear Power Plant.With 981009 ltr.DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE: TITLE: Monthly Operating Report (per Tech Specs)NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72).

E 05000244 RECIPIENT ID CODE/NAME PD1-1 PD COPIES RECIPIENT LTTR ENCL-.ID CODE/NAME 1 1 VISSING,G.

COPIES LTTR ENCL 1 1 INTERNAL: AEOD/SPD/RRAB OC/DBA/PAD EXTERNAL: LITCO BRYCE,J H NRC PDR 1 1 1 1 1 1 1 1 RGN1 NOAC 1 1 1 1 1 1 D N NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE.TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 9 ENCL 9 0~S

~~ROCHESTER GAS AND ELECTRIC CORPORATION 89EASTAVENIJE, ROCHESTER, N.Y.14649-000'REA CODE 716-546-2700 October 9, 1998 US Nuclear Regulatory Commission Document Control Desk Attn: Guy S.Vissing Project, Directorate I-1 Washington, DC 20555

Subject:

Monthly Report for September, 1998 Operating Status Information R.E: Ginna Nuclear Power Plant Docket No.50-244

Dear Mr.Vissing:

Pursuant to Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of September, 1998.xc: U.S.Nuclear Regulatory Commission Mr.Guy S.Vissing (Mail Stop 14B2)Project Directorate l-1 Washington, D.C.20555.Very truly yours, Q..d se h A.Widay Plant Manager U.S.Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S.NRC Ginna Senior Resident Inspector Attachments 98i0190325 980930 PDR ADOCK 05000244 R PDR

~~T OPERPlNG DATA REPORTCOMPLETED BY: 50-244 October 9, 1998 f.U John V.Walden TELEPHONE (716)771-3588 OPERATING STATUS 480 1.Unit Name: R.E.GINNA NUCLEAR POWER PLANT 2.Reporting Period: Se tember, 1998 3.Design Electric Rating (Net MWe): 470 4.Maximum Dependable Capacity (Net MWe): Notes: This Month Yr.-to-Date Cumulative**

5.Number of hours Reactor Was Critical 6.Hours Generator On-line 7.Unit Reserve Shutdown Hours 8.Net Electrical Energy Generated (MWH)720.0 720.0 0.0 345907.0 6551.0 6551.0 0.0 3219003.0 204510.2 201489.7 8.5*90760519.4

    • CUMULATIVE TOTAL COMMENCING NOVEMBER 8, 1969 7 C F Q Jl DOCKET NO: 50-244 UNIT NAME: R.E.GINNA NUCLEAR POWER PLANT DATE: October 9 1998 COMPLETED BY: John V.Walden UNIT SHUTDOWN REPORTING PERIOD: Se tember 1998 (Month/Year)

NO.DATE TYPE F: FORCED S: SCHEDULED DURATION (HOURS)REASON"'ETHOD OF SHUTTING DOWN'" CAUSE/CORRECTIVE ACTIONS COMMENTS

SUMMARY

A power reduction occurred on September 5, 1998 at 2120.Power was reduced to 45%for off-site circuit repairs and turbine control maintenance.

Full power operation resumed on September 6, 1998 at 1410.The unit operated at full power for the remainder of the month of September.

(1)Reason (2)Method A-Equipment Failure (Explain)B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training/License Examination F-Administrative G-Operational Error (Explain)H-Other (Explain)1-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4-Continuation 5-Other (Explain) 0