Monthly Operating Rept for June 1997 for Re Ginna Npp. W/970711 Ltr
ML17264A952
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/30/1997
From: Norton B, Widay J
ROCHESTER GAS & ELECTRIC CORP.
To: Vissing G
NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9707220148
Download: ML17264A952 (11)


Text

CATEGORY 1 REGULATOr INFORMATION DISTRIBUTION oTEM (RIDS)

ACCESSION) %BR.'9707220148 DOC.DATE: 97/06/30 NOTARIZED: NO DOCKET FACI.L*:56-244 Robert Emmet Gihna Nuclear Plant, Unit 1, Rochester G 05000244 AUTH. NAME AUTHOR AFFILIATION NORTON,B.A. Rochester Gas 6 Electric Corp.

WIDAY,J.A. Rochester Gas a Electric Corp.

RECIP.NAME RECIPIENT AFFILIATION VISSING;G.S.

SUBJECT:

Monthly operating rept for June 1997 for RE Ginna NPP.

W/970711 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR L ENCI, i SIZE:

TITLE: Monthly Operating Report (per Tech Specs) T NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72). 05000244 E

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD1-1 PD 1 1 VISSING G. 1 1 INTERNAL: AEOD/SPD/RRAB 1 1 FILE CENTER 01 1 1 NRR/DRPM/PECB 1 1 -GC/DBA/PAD 1 1 RGNl 1 1 EXTERNAL: LITCO BRYCETJ H 1 1 NOAC 1 1 NRC PDR 1 1 D

U N

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESKJ ROOM OWFN SD-5(EXT 415"2083) TO ELIMINATE YOUR NAME

~ FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEEDI TOTAL NUMBER OF COPIES REQUIRED: LTTR 10 ENCL 10

h I

>> nwz szzzzzl I AAHD rzggsx i uiPk'erzi>>

xzzzzzzs StATE ROCHESTER GAS AND ELECTRIC CORPORATION o 89 EAST AVENUE, ROCHESTER, N.K 14649.0001 TELEPHONE ARE* CODE TTTT 546-2700 July 11, 1997 US Nuclear Regulatory Commission Document Control Desk Attn: 'uy S. Vissing Project Directorate I-1 Washington, DC 20555

Subject:

Monthly Report for June, 1997 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Vissing:

Pursuant to Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of June, 1997.

Very truly yours,

a. LI s h A. Widay ant Manager xc: U.S. Nuclear Regulatory Commission Mr. Guy S. Vissing (Mail Stop 14B2)

Project Directorate I-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments 9707220148 970630 P. '

ADOCK 05000244 POR

~~ZBil

.0030

OPERATING DATA REPOR 50-244 Jul 11 1997 COMPLETED BY Benjamin A. Norton TELEPHONE (716) 771-3653

1. Unit Name: R.E. GINNA NUCLEAR POWER PLANT Notes
2. Reporting Period: June 1997
3. Licensed Thermal Power (MWt): 1520
4. Nameplate Rating (Gross MWe): 517

'5. Design Electric Rating (Net MWe): 470

6. Maximum Dependable Capacity (Gross MWe): 490
7. Maximum Dependable Capacity (Net MWe): 480
8. If Changes Occur in Capacity Rating (Items Number 3 Through 7) Since Last Report, Give Reason:
9. Power Level to Which Restricted, If Any (Net MWe:
10. Reason For Restrictions, If An:

This Month Yr.-to-Date Cumulative

11. Hours in Reported Period 720.0 4343.0 241895.0
12. Number of hours Reactor Was Critical 720.0 4343.0 194257.3
13. Reactor Reserve Shutdown Hours 0.0 0.0 1687.6
14. Hours Generator On-line 720.0 4343.0 '91269.5
15. Unit Reserve Shutdown Hours 0.0 0.0 8.5
16. Gross Thermal Energy Generated (MWH) 1091810.0 6549988.0 '72426258.0
17. Gross Electrical Energy Generated (MWH) 372553.0 2240694.0 90351003.0
18. Net Electrical Energy Generated (MWH) 355010.0 2134283.0 85780149.8
19. Unit Service Factor (%) 100.0 100.0 79.1
20. Unit Availability Factor (%) 100.0 100.0 79.1
21. Unit Capacity Factor (using MDC Net) (%) 102.7 102.4 76.4
22. Unit Capacity Factor (using DER Net) (%) 104.9 104.6 76.5
23. Unit Forced Outage Rate (%) 0.0 0.0 5.6
24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):

The refuelin and maintenance outa e is scheduled for October 20 1997. The Ianned duration is 22 da s.

25. Ifhutdown At End of Report Period, Estimate Date of Startup:
26. Units in Test Status (Prior to Commercial Operation): Forcast Achieved INITIALCRITICALITY INITIALELECTRiCITY COMMERCIALOPERATION CUMULATIVETOTAL COMMENCING JANUARY 1, 1975

"" CUMULATIVETOTAL COMMENCING NOVEMBER 8, 1969

I i AVERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50-244 UNIT: R.E. Ginna Nuclear Power Plant DATE: Jul 11 1997 COMPLETED BY:

Benjamin A. Norton TELEPHONE: 716 771-3653 MONTH June 1997 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 498 17. 494

2. 498 18. 494 498 19. 492 498 20. 494
5. 498 21. 492
6. 498 22. 490
7. 498 23. 490
8. 498 24. 490
9. 498 25. 490
10. 496 26. 488 12 13.

'93 493 494 27.

28.

29.

487 488 487

14. 494 30. 486
15. 494 31.
16. 495 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in reporting month. Compute to the nearest whole megawatt.

DOCKET NO:~244 UNIT: R.E. INNA CLEAR P WER PLANT

,D COMPLETED BY:

Be jamin A. Norton, 0:~6>>

UNIT SIIUTDOWN AND POWER REDUCTIONS REPORT MONTH tune~1Q No. Date Type Duration Method of (hours)

Reason reactors'icensee shuting down Event Code'omponent System Code'ause & Corrective Action to Prevent Recurrence Report ¹ 1

F: Forced 2 S Scheduled Reason: 3 4 A-Eciuipment (Explain) Method: Exhibit G - Instructions B-Maintenance or Test 1-Manual for Preparation of Data C-Refueling 2-Manual Scram. Entry Sheets for D-Regulatory 3-Automatic Scram. Licensee Event Report E-Operator Training & 4-Other (Explain) (LER) File (NUREG-Lecensee Examination 0161)

F-Administrative G-Operational Error (Explain)

H-Other (Explain) 5 Exhibit 1- Same Source

'P4 1

H '

NARRATIVE

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO: 50-244 UNIT: R.E. Ginna Nuclear Power Plant DATE: Jul 11 1997 COMPLETED BY: N,g Benjamin A. Norton TELEPHONE: 716 771-3653 MONTH June 1997 The unit operated at full power for the entire month of June. The average power level was 99.8%