PRXORXTY (ACCELERATED RZDS PROCESSING)
REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
DOCKET FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G
05000244 AUTH.NAME AUTHOR AFFILIATION WALDEN,J.V.
Rochester Gas
& Electric Corp.
WIDAY,J.A.
Rochester Gas
& Electric Corp.
RECIP.NAME RECIPIENT AFFILIATION
SUBJECT:
Monthly operatin t for Oct 1995 for RE Ginna Nuclear Power Plant.
51109 r.
DISTRIBUTION CODE:
IE24D COPIES RECEIVED:LTR ENCL SIZE:
TITLE: Monthly Operating Report (per Tech Specs d
NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72).
05000244 RECIPIENT ID CODE/NAME PD1-1 PD INTERNAL: AEOD/SPD/RRAB NRR/DRPM/PECB EXTERNAL: LITCO BRYCE,J H
NRC PDR COPXES LTTR ENCL 1
1 1
1 1
1 1
1 1
1 RECIPIENT ID CODE/NAME JOHNSON,A FILE CENTER G
NOAC COPXES LTTR ENCL 1
1 1
1 1
1 1
1 NOTE,TO ALL "RZDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE!
CONTACT THE DOCUMENT CONTROL DESKi ROOM OWFN 5DS (415-2083)
TO ELIMINATE YOUR NAME.FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED(
TOTAL NUMBER OF COPIES REQUIRED:
LTTR 9
ENCL 9
0
~,t
-'ÃE f/ tEF
~~/
augj~i/j/eire 8P:::
ROCHESTER GAS AND ELECTRIC CORPORATION o 89 EAST AVENUE, ROCHESTER, N.K 14649-0001 EEEEPHONE AREA CODE 7ld 546.2700 GINNA,STATION November 9,
1995 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555
Subject:
Monthly Report for October, 1995 Operating Status Information R.
E. Ginna Nuclear Power Plant Docket No. 50-244
Dear Sir:
Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of October, 1995.
Very truly yours,
- p. LJ s
h A. Wida lant Manager JAW:tjn Attachments c:
Mr. Thomas T; Martin NRC,'(1)
V O
95iii50098 95i03i PDR ADOCK 05000244 R
0 I
t DOCKET NO: 50-244 November 9, 1995 f.'ohn V. Walden TELEPHONE (716) 7714588 COMPLETED BY OPERATING DATAREPORT OPERATING STATUS Notes
- 1. Unit Name:
R.E. GINNANUCLEAR POWER PLANT
- 2. Reporting Period:
October, 1995 3.
Licensed Thermal Power (MWt):
1520 4.
Nameplate Rating (Gross MWe):
490 5.
Design Electric Rating (Net MWe):
470 6.
Maximum Dependable Capacity (Gross MWe):
490 7.
Maximum Dependable Capacity (Net MWe):
470 8.
IfChanges Occur in Capacity Rating (Items Number 3 Through 7) Since Last Report, Give Reason:
9.
Power Level to Which Restricted, IfAny (Net MWe):
- 10. Reason For Restrictions, IfAny:
This Month Yr.-to-Date Cumulative-
- 11. Hours in Reported Period
- 12. Number of hours Reactor Was Critical
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On-line
- 15. Unit Reserve Shutdown Hours
- 16. Gross Thermal Energy Generated (MWH)
- 17. Gross Electrical Energy Generated (MWH)
- 18. Net Electrical Energy Generated (MWH)
- 19. Unit Service Factor (%)
- 20. Unit AvailabilityFactor (%)
- 21. Unit Capacity Factor (using MDC Net) (%)
- 22. Unit Capacity Factor (using DER Net) (%)
- 23. Unit Forced Outage Rate (%)
745.0 745.0 0.0 745,0 0.0 1093897.0 371561.0 353447.0 100.0 100.0 100.9 100.9 0.0 7296.0 6387.3 0.0 6312.4 0.0 9194598.0 3094852.0 2940822.0 86.5 86.5 85.8 85.8 0.7 227304.0 182203.1 1687.6 179284.7 8.5
'54709835.0 84328904.0 80050052.0 78.9 78.9 76.0 76.0 5.5
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):
Refueling and Maintenance, Start 4/01N6, Duration 60 days
- 25. IfShutdown At End of Report Period, Estimate Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forcast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION
'UMULATIVETOTALCOMMENCINGJANUARY1, 1975 CUMULATIVETOTALCOMMENCINGNOVEMBER8, 1969
t t
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50-244 UNIT: R.E. Ginna Nuclear Power Plant DATE: November 9
1995 COMPLETED BY:
John Walden TELEPHONE:
7 6
771-3588 MONTH October '995 DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 470 17.
475 2
~
470 18.
475 3.
470 19.
474 4
~
471 20.
474 5.
472 21.
474 6.
476 22.
475 7.
476 23.
475 24.
9.
475 25.
474 10.
474 26.
474 474 27.
474 12.
475 28.
475 13.
474 29.
475 14.
474 30.
475 15.
475 31.
475 16.
475 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in reporting month.
Compute to the nearest whole megawatt.
DOCKI:.T NO.
VNll'NAhll:.R E-GINNA NUCLEAR POWER PLANT UNIT SHUTDOWN AND POWER REDUCTIONS T
COhIPLI:.1 ED BY t
C'nVV.
Walden REPORT hlONTH l'I'.LI'.P IIONI'.
Ho.
Date 0
4 oP 0
C0
///o0 IZ cn ~0 C
M 4/
3 g 0 l/l C 0
CL Licensee Event Report lI Ew 0
O Vl o0 Vl (J CO lA o
C Q
0 Cause 8 Corrective Action to Prevent Recurrence 1
F: Forced S:
Scheduled Rtv. 4/ss 4549 Reason:
A-Etluipment Failure (Explain)
B-hlaintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)
II-Other (Explain) 3 hfethod:
1-hlanual 2-hfanual Scram.
3-Automatic Scram.
4-Other (Explain) 5 Exhibit G - Instructions for Preparation of Data Entry Sheets for Liccnscc Event Rcport (LER) File (NVREG-OI6I)
Exhibit I - Same Source
0 4'
NARRATIVE
SUMMARY
OP OPERATING EXPERIENCE DOCKET NO: 50-244 UNIT: R.E.
Ginna Nuclear Power Plant DATE: Nov mber 9
1995 COMPLETED BY:
John Walden TELEPHONE:
716 71-3588 MONTH October 1995 Average power for the month was 97%