Monthly Operating Rept for Mar 1996 for Re Ginna Nuclear Power Plant
ML17264A442
Person / Time
Site: Ginna Constellation icon.png
Issue date: 03/31/1996
From: Walden J, Widay J
ROCHESTER GAS & ELECTRIC CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9604110077
Download: ML17264A442 (6)


Text

CATEGORY 1 REGUDRTOk -

INFORMATION DISTRIBUTION%STEM (RIDE)

E

'l ~

DOCKET FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G

05000244 AUTH.NAME AUTHOR AFFILIATION WALDEN,J.V.

Rochester Gas

& Electric Corp.

WIDAY,J.A.

Rochester Gas a Electric Corp.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Mo rating rept for Mar 1996 for Gina Station.

/960405 1

DISTRIBUTION CODE:

IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:License Exp date in accordance with 10CFR2,2;109(9/19/72).

'05000244 E

RECIPIENT ID CODE/NAME PD1-1 PD INTERNAL: AEOD/SPD/RRAB NRR/DRPM/PECB EXTERNAL LITCO BRYCE iJ H

NRC PDR COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

RECIPIENT ID CODE/NAME JOHNSON,A LE C TER

.0 RGNl NOAC COPIES LTTR ENCL 1

1 1

1 1

1 1

1 D

N NOTE TO ALL "R1DS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTEl CONTACT THE DOCUMENT CONTROL DESKI ROOM OWPN SD-S(EXT, 415"2083)

TO ELIMINATE YOUR NAME PROM DISTRIBUTION LISTS POR DOCUMENTS YOU DON'T NEEDl TOTAL NUMBER OF COPIES REQUIRED:

LTTR 9

ENCL 9

76RK

/

HATE ROCHESTER GAS AND ELECTRIC CORPORATION o 89 EAST AVENUE, ROCHESTER, N.Y. 14649-0001 TELt'PHONC ARcA cooc 710 546.2700 GINNA STATION April 5, 1996 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Subject:

Monthly Report for March, 1996 Operating Status Information R.

E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Sir:

Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of March, 1996.

Very truly yours, s

h A. Wida lant Manager li.00"8 JAW:tjn Attachments c:

Mr. Thomas T. Martin NRC (1)

Vwoea<0077 960SSX PDR ADQCK 05000244',

R PDR

OPERATING DATAREPORT COMPLETED BY:

ri 5 1996 50-244 John V. Walden TELEPHO (716) 771 3588 Notes

1. Unit Name:

R.E. GINNANUCLEAR POWER PLANT

2. Reporting Period:

March 1996 3.

Licensed Thermal Power (MWI):

1520 4.

Nameplate Rating (Gross MWe):

517 5.

Design Electric Rating (Net MWe):

470 6.

Maximum Dependabte Capacity (Gross MWe):

490 7.

Maximum Dependabte Capacity (Net MWe):

470 8.

It Changes Occur in Capadty Rating (Items Number 3 Through 7) Since Last Report, Give Reason:

9.

Power Level to Which Restricted, IfAny (Net MWe:

10. Reason For Restrtctions, IfAn.

This Month Yr.-to.Date Cumulative-

11. Hours in Reported Period
12. Number of hours Reactor Was Critica
13. Reactor Reserve Shutdovm Hours
14. Hours Generator On-line
15. Unit Reserve Shutdown Hours
16. Gross Thermal Energy Generated (MWH)
17. Gross Electrical Energy Generated (MWH)
18. Net Electrical Energy Generated (MWH)
19. Unit Service Factor (%)
20. UnitAvailabilityFactor (%)
21. Unit Capacity Factor (using MDC Net) (%)
22. Unit Capacity Factor (using DER Net) (%)
23. Unit Forced Outage Rate (%)

744.0 662.5 0.0 659.8 0.0 947615.0 322337.0 306413.0 88.7 88.7 87.6 87.6 11.3 2184.0 2102.5 0.0 2099.8 0.0 3068799.0 1044176.0 992756.0 96.1 96.1 96.7 96.7 3.9 230952.0 185769.6 1687.6

'82848.5 8.5 259932107.0 86106676.0 81740568.0 79.2 79.2 76.4 76.4 5.5

24. Shutdovms Scheduled Over Next 6 Months (Type, Date and Duration of Each):

Refuelin and Maintenance Start 4/01/96 Duration 58 da

25. ItShutdown At End of Report Period, Estimate Date of Startup:
26. Units in Test Status (Prior to Commercial OperaVon):

Force st Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

'UMULATIVETOTALCOMMENCINGJANUARY1, 1975

    • CUMULATIVETOTALCOMMENCINGNOVEMBER8, 1969

G.

~

~

'VERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50-244 UNIT: R.E.

Ginna Nuclear Power Plant DATE:

ril 5 1996 COMPLETED BY:

John Walden TELEPHONE:

7 6

771-3588 MONTH March 1996 DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 477 17.

473 477 18.

474 3.

477 19.

473 4

~

476 20.

474 5.

477 21.

473 6

~

476 22.

7.

362 23.

24'75 25.

10.

26.

475 12.

13.

100 426 472 27.

28.

29.

476 475 475 14

~

15.

473 473 30.

31.

476 473 16.

473 INSTRUCTIONS On this format, list the average daily unit power.level in MWe-Net for each day in reporting month.

Compute to the nearest whole megawatt.

DOCKI:.T NO.

UNll NAhfl: R E. CilNNA NUCLEAR POWER PLANT UNIT SHUTDOWN AND POWER REDUCTIONS I)A Il'-

CohfPLI'.1 I'.D BY ohn V. Walden REPORT hfONTH +arch ql:LIIPIIO

. (716) 771-3588 r

Ho.

Date 0 0 O~

Pl C0 00 Pl 0

c 000 0 4rl C

0 Ct Licensee Event Report II Ew 0

0 0

Vl Q C0 ul 0C Q

D E

0 O

Cause L Corrective Action to Prevent Recurrence 3-7-96 84.2 96-002 KE "B" Condenser Circulating Water ump tripoed causing a

Secondary system transient.

The Reactor was manually scramed due to Turbine Operatin Limits being exceeded.

See LER 96-002 for more details.

l F: Forced S:

Scheduled Rtv. 4/85 4949 2

Reason:

A-Equipment Failure (Explain)

I3-hfaintenancc or Test C-Refueling D-Regulatory Restriction E-Operator Training Bc Liccnsc Examination F-Administrative G-Operational Error (Explain)

II-Other (Explain) 3 hfcthod:

I-hfanual 2-hfanual Scram.

3-Automatic Scram.

4-Other {Explain)

Exhibit G - Instructions for Preparation of Data Entry Sheets for Liccnscc Event Rcport (LER) File (NUREG-0161)

Exhibit I - Same Source

NARRATIVE

SUMMARY

OP OPERATING EXPERIENCE DOCKET NO: 50-244 UNIT: R.E. Qinna Nuclear Power Plant DATE: A 'l 5 19 COMPLETED BY:

John Walden TELEPHONE:

716 1-3588 MONTH March 1996 A forced outage occurred on March 7, 1996 due to the trip of the "B" Condenser Circulating Water Pump.

A manual reactor scram was initiated to prevent potential damage to the main turbine (see LER 96-002).

The unit was placed on-line on March 11, 1996 and ran at full power for the remainder of the month.

The average power for the month excluding the forced outage was 96%