Monthly Operating Rept for Feb 1996 for Re Ginna Nuclear Power Plant.W/960307 Ltr
ML17264A397
Person / Time
Site: Ginna Constellation icon.png
Issue date: 02/29/1996
From: Walden J, Widay J
ROCHESTER GAS & ELECTRIC CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9603140099
Download: ML17264A397 (8)


Text

CATEGORY 1 REGULATOR INFORMATION DISTRIBUTIONOISTEM (RIDE)

I DOCKET FACIL:-50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G 05000244 AUTH. NAME AUTHOR AFFILIATION WALDEN,J.U. Rochester Gas a Electric Corp.--

WIDAY,J.A. Rochester Gas  !'lectric Corp.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly opera for Feb 1996 for RE Ginna Nuclear Power Plan 960307 r.

DISTRIBUT;ON CODE: IE24D COPIES RECEIVED:LTR TITLE: Monthly Operating Report (per Tech Specs) 1 ENCL J SIZE:

NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72). 05000244 E RECIPIENT ID CODE/NAME COPIES 1'ECIPIENT LTTR ENCL ID CODE/NAME COPIES LTTR ENCL 0 PD1-1 PD 1 JOHNSONFA 1 1 INTERNAL: AEOD/SPD/RRAB 1 1 FIL R 1 1 1 NRR/DRPM/PECB 1 1 1 1 EXTERNAL: LITCO BRYCE,J H 1 1 NOAC 1 1 NRC PDR 1 1 I

D NOTE TO ALL MRIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM OWFN 5D-5(EXT. 415-2083) TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 9 ENCL . 9

l' ffffffifif liiiffilf t

/

ffffI7ff~lineiiif f, ffffffffl'ifffffff ROCHESTER GAS AND ELECTRIC CORPORATION o 89 EAST AVENUE, ROCHESTER, N.K 14649-0001 TELEPHONE AREA COOE 7IO 546.2700 GINNA STATION March 7, 1996 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Subject:

Monthly Report for February, 1996 Operating Status Information R. E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Sir:

Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of February, 1996.

Very truly yours, s A. Widay an Manager JAW:tjn Attachments c: Mr. Thomas T. Martin NRC (1)

M03l40099 960229 PI PDR ADOCK 05000244I R PDRL ~

~4'Oo~~

OPERATING DATA REPORT 50-244 a 71 COMPLETED BY:

John V. Walden TELEPHO (716) 7714588

1. Unit Name: RE. GINNA NUCLEAR POWER PLANT Notes
2. Reporting Period: Fobrua 1996
3. Licensed Thermal Power (MWI): 1520
4. Nameplate Rating (Gross MWo): 517
5. Design Electric Rating (Net MWo): 470
6. Maximum Dependable Capacity (Gross MWe): 490
7. Maximum Dependable Capacity (Not MWo): 470
8. If Changes Occur in Capacity Rating (Items Number 3 Through 7) Since Last Report, Give Reason:

RoviewofName lateRatin definitionrovealodthatthovaluois517MWeinsteadof490MWoas roviousl re Ited.

Name late Ratin = urbino Generator MVA x Power Factor 608.4 MVA x .85 P -"517.14 MWo

9. Power Level to Which Restricted, If Any (Net MWo):
10. Reason For Restrictions, If An .

This Month Yr:to.Dato Cumulative"

11. Hours in Reported Porlod 696.0 1440.0 230208.0
12. Number of hours Reactor Was Critical 696.0 1440.0 185107.1
13. Reactor Reserve Shutdown Hours 0.0 0.0 1687.6
14. Hours Generator On-line 696.0 1440.0 182188.7
15. Unit Reserve Shutdown Hours 0.0 0.0 8.5
16. Gross Thermal Energy Generated (MWH) 1024993.0 2121184.0 258984492.0
17. Gross Electrical Energy Gonoratod (MWH) 348735.0 721839.0 85784339.0
18. Net Electrical Energy Generated (MWH) 331602.0 686343.0 81434155.0
19. Unit Service Factor (%) 100.0 100.0 79.1
20. Unit AvailabilityFactor (%) 100.0 if 100.0 79.1
21. Unit Capacity Factor (using MDC Not) (%) 101.4 101.4 76.3
22. Unit Capacity Factor (using DER Not) (%) 101.4 101.4
23. Unit Forced Outago Rate (%) 0.0 0.0 5.5
24. Shutdowns Scheduled Ovor Next 6 Months (Typo, Date and Duration of Each):

Rofuelin and Maintenance Start 4/01/96 Duration 62 da

25. If Shutdown At End of Report Period, Estimate Date of Startup:
26. Units in Test Status (Prior to Commercial Operation): Force st Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

'UMULATIVETOTAL COMMENCING JANUARY 1 1975 ~

"CUMULATIVETOTAL COMMENCING NOVEMBER 8, 1969

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50-244 UNIT: R.E. Ginna Nuclear Power Plant DATE: March 7 1996 COMPLETED BY: UakL John Walden TELEPHONE: 6 771-3588 MONTH Februar 1996 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 476 17. 476 476 18. 476

3. 476 19. 476 476 20. 476
5. 475 21. 476
6. 476 22. 476
7. 476 23. 476
8. 476 24. 476
9. 476 25. 476
10. 476 26. 476 476 27. 476
12. 476 28. 476
13. 476 29. 476
14. 476 30.
15. 476 31.
16. 476 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in reporting month. Compute to the nearest whole megawatt.

no( Kl. T NO 50 244 IINITNAMI:R.E. GINNA NUCLEAR POWER. PLANT DATE UNIT SHUTDOWN AND POWER REDUCTIONS (:OhIPLI:.O'I:.D BY o n V. Wa1den REPORT hlONTH Tl:.LI:PIIO 716 771-3588 Pl 0 C C

0 C 0 cOI o0 I.icensee Em 0 Irl Cause gI Corrective III 0 0 C 0 L 0 Event 0 Action to No. Date 0 0 VI 0 5 cc III 0 0 0 I- QX O~ 0 0 N C Report tf I/l 0 E Prevent Recurrence 0

O F: Forced hlethod: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) I-hlanual for Preparation of Data 4'%eason:B-Maintenance or Test C-Refueling 2-hlanual Scram.

3-A utoma tie Scram.

Entry Sheets for Licensee Event Rcport (LER) File (NIJRE(-

D-Regulatory Restriction 4-Other (Explain) 0161)

E-Operator Training & License Examination F-Administrative G.Operational Error (Explain)

IIEV. 4/WS II-Other (Explain) Exhibit - Same Source I

NARRATIVE

SUMMARY

OF OPERATING'XPERIENCE DOCKET NO: 50-244 UNIT: R.E. Ginna Nuclear Power Plant DATE: M h 7 19 6 COMPLETED BY:

John Walden TELEPHONE: 716 771-3588 MONTH Februar 1996 Average power for the month was 97%