Monthly Operating Rept for Feb 1999 for Ginna Nuclear Power Plant.With 990310 Ltr
ML17265A596
Person / Time
Site: Ginna Constellation icon.png
Issue date: 02/28/1999
From: Walden J, Widay J
ROCHESTER GAS & ELECTRIC CORP.
To: Vissing G
NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9903170065
Download: ML17265A596 (5)


Text

CATEGORY 1 c

REGULA RY INFORMATION DISTRIBUTIO SYSTEM (RIDS)

ACCESSION NBR:9903170065 DOC.DATE: 99/02/28 NOTARIZED: NO DOCKET FACIL:50.-.24~+ Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G 05000244 AUTH.NAciir".' AUTHOR AFFILIATION WALDEN,J.V. Rochester Gas & Electric Corp.

WIDAY,J.A. Rochester Gas & Electric Corp.

RECIP.NAME RECIPIENT AFFILIATION VISSING,G.S.

SUBJECT:

Monthly operating rept for Feb 1999 for Ginna Nuclear Power Plant. With 990310 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs) E NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72). 0500024+

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL R PD1-1 PD 1 1 VISSING,G. 1 1 INTERNAL: AEOD/SPD/RRAB 1 1 FILE CENTER 1 1 OC/DBA/PAD 1 1 1 1 EXTERNAL: LMITCO MARSHALL 1 1 NOAC 1 1.

NRC PDR 1 1 U

E NOTE TO ALL "RZDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPZES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-20B3 TOTAL NUMBER OF COPIES REQUIRED: LTTR 9 ENCL 9

AeO K1%

I J ROCHESTER GAS AND ELECTRIC CORPORATION.69EASTAVENUE, ROCHESTER, N.Y. 14649-0001 AREA CODE 716-546-2700 March 10, 1999 US Nuclear Regulatory Commission Document Control Desk Attn: Guy S. Vissing Project Directorate I-1 Washington, DC 20555

Subject:

Monthly Report for February, 1999 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Vissing:

Pursuant to Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of February, 1999.

Very truly yours, a.d.

se h A. Widay Plant Manager xc: U.S. Nuclear Regulatory Commission Mr. Guy S. Vissing (Mail Stop 14B2)

Project Directorate I-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments PDR ADQCK OSOggpgy),k R 'Pa@

OPERON ING DATA REPORT 50-244 C. March 10, 1999 COMPLETED BY:

John V. Walden TELEPHONE (716) 771-3588 OPERATING STATUS

1. Unit Name: R.E. GINNA NUCLEAR POWER PLANT Notes:
2. Reporting Period: Februa, 1999
3. Design Electric Rating (Net MWe): 470
4. Maximum Dependable Capacity (Net MWe): 480 This Month Yr.-to-Date Cumulative**
5. Number of hours Reactor Was Critical 672.0 1416.0 208135.2
6. Hours Generator On-line 672.0 1416.0 205114.7
7. Unit Reserve Shutdown Hours 0.0 0.0 85 *
8. Net Electrical Energy Generated (MWH) 281445.0 651087.0 92502167.4
    • CUMULATIVETOTAL COMMENCING NOVEMBER 8, 1969

4 DOCKET NO: 50-244 UNIT NAME: R.E. GINNA NUCLEAR POWER PLANT DATE: March 10 1~~99 COMPLETED BY: John V. Walden UNIT SHUTDOWN REPORTING PERIOD: Februar 1999 (Month/Year)

NO. DATE TYPE DURATION REASON"'ETHOD OF DOWN"'AUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED COMMENTS

SUMMARY

The unit was in end of fuel cycle coastdown for the entire month of February. Power was reduced from 100% to 70%.

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other (Explain)