| | issue date = 10/03/2011 | | | issue date = 10/03/2011 |
| | title = Summary of September 26, 2011, Meeting with Constellation Energy Nuclear Group, LLC on the Proposed Merger Between Constellation Energy Group, Inc. and Exelon Corporation (TAC Nos. ME6234 - ME6238) | | | title = Summary of September 26, 2011, Meeting with Constellation Energy Nuclear Group, LLC on the Proposed Merger Between Constellation Energy Group, Inc. and Exelon Corporation (TAC Nos. ME6234 - ME6238) |
| | author name = Pickett D V | | | author name = Pickett D |
| | author affiliation = NRC/NRR/DORL/LPLI-1 | | | author affiliation = NRC/NRR/DORL/LPLI-1 |
| | addressee name = | | | addressee name = |
Line 9: |
Line 9: |
| | docket = 05000220, 05000244, 05000317, 05000318, 05000410 | | | docket = 05000220, 05000244, 05000317, 05000318, 05000410 |
| | license number = | | | license number = |
| | contact person = Pickett D V, NRR/DORL/LPL1-1, 415-1364 | | | contact person = Pickett D, NRR/DORL/LPL1-1, 415-1364 |
| | case reference number = TAC ME6234, TAC ME6235, TAC ME6236, TAC ME6237, TAC ME6238 | | | case reference number = TAC ME6234, TAC ME6235, TAC ME6236, TAC ME6237, TAC ME6238 |
| | package number = ml11270066 | | | package number = ml11270066 |
| | document type = Meeting Summary, Letter | | | document type = Meeting Summary, Letter |
| | page count = 3 | | | page count = 3 |
| | project = TAC:ME6235, TAC:ME6237, TAC:ME6234, TAC:ME6236, TAC:ME6238 | | | project = TAC:ME6234, TAC:ME6235, TAC:ME6236, TAC:ME6237, TAC:ME6238 |
| | stage = Meeting | | | stage = Meeting |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:'1)-0"ll:P -::. UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 <l 0 \ii : October 3, 2011 "'" ***"", Constellation Energy Nuclear Group, LLC Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 R.E. Ginna Nuclear Power Plant SUMMARY OF SEPTEMBER 26,2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC ON THE PROPOSED MERGER BETWEEN CONSTELLATION ENERGY GROUP, INC. AND EXELON CORPORATION (TAC NOS. ME6234 -ME6238) On September 26, 2011, a Category 1 meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Nuclear Group, LLC (CENG) and Exelon Corporation at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. As stated in the meeting notice dated September 12, 2011 (Agencywide Document Access and Management System (ADAMS) Accession No. ML 112500517), the meeting was closed to the public since the information to be discussed had previously been determined to contain proprietary commercial information and be withheld from public disclosure in accordance with 10 CFR 2.390 as stated in the NRC letter dated August 19, 2011 (ML 112270380). As part of the NRC staff's review of the proposed merger between Exelon Corporation and Constellation Energy Group, Inc. (CEG) (ML 11138A159), the staff has focused on foreign ownership, control or influence (FOCI). CENG's supplemental letter of August 12,2011 (ML 11234A062), led to further staff FOCI concerns that needed to be discussed and resolved. The staff discussed the role and function of the CENG Nuclear Advisory Committee along with FOCI concerns associated with EDF, CENG, and Exelon. A list of attendees is provided in the Enclosure. There were no slides or handouts. Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220, 50-244, 50-317,50-318, and List of cc w/encl: Distribution via LIST OF SEPTEMBER 26, 2011, MEETING CONSTELLATION ENERGY NUCLEAR GROUP, LLC AND EXELON PROPOSED CONSTELLA TION/EXELON Bruce Montgomery Steve Miller Carey Fleming Sean Klein Ned Tyler EXELON Brad Fewell Carol Peterson WINSTON & STRAWN/EDF David Repka Robert Nelson Christopher Regan Michael Markley Jo Ann Simpson Anneliese Simmons Thomas Fredrichs Shawn Harwell Beth Mizuno Jim Whitney Douglas Pickett CENG NUCLEAR ADVISORY COMMITTEE Richard Meserve HOGAN LOVELLS Dan Stenger Enclosure October 3, 2011 Constellation Energy Nuclear Group, LLC Calvert Cliffs Nuclear Power Plant, Unit Nos, 1 and 2 Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 RE. Ginna Nuclear Power Plant SUMMARY OF SEPTEMBER 26, 2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC ON THE PROPOSED MERGER BETWEEN CONSTELLATION ENERGY GROUP, INC, AND EXELON CORPORATION (TAC NOS, ME6234 -ME6238) On September 26,2011, a Category 1 meeting was held between the U,S, Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Nuclear Group, LLC (CENG) and Exelon Corporation at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, As stated in the meeting notice dated September 12, 2011 (Agencywide Document Access and Management System (ADAMS) Accession No, ML 112500517), the meeting was closed to the public since the information to be discussed had previously been determined to contain proprietary commercial information and be withheld from public disclosure in accordance with 10 CFR 2.390 as stated in the NRC letter dated August 19, 2011 (ML 112270380). As part of the NRC staff's review of the proposed merger between Exelon Corporation and Constellation Energy Group, Inc. (CEG) (ML 11138A 159), the staff has focused on foreign ownership, control or influence (FOCI). CENG's supplemental letter of August 12, 2011 (ML 11234A062), led to further staff FOCI concerns that needed to be discussed and resolved. The staff discussed the role and function of the CENG Nuclear Advisory Committee along with FOCI concerns associated with EDF, CENG, and Exelon A list of attendees is provided in the Enclosure. There were no slides or handouts. IRN Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220, 50-244,50-317,50-318, and 50-410 | | {{#Wiki_filter:~f>,1\ REGo~ UNITED STATES |
| | ~.§J\,; '1)-0"ll NUCLEAR REGULATORY COMMISSION |
| | :P |
| | <l |
| | -:0:. WASHINGTON, D.C. 20555*0001 |
| | \ii : |
| | ~,,! October 3, 2011 |
| | ***"", ~o LICENSEE: Constellation Energy Nuclear Group, LLC FACILITY: Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 R.E. Ginna Nuclear Power Plant |
| | |
| | ==SUBJECT:== |
| | |
| | ==SUMMARY== |
| | OF SEPTEMBER 26,2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC ON THE PROPOSED MERGER BETWEEN CONSTELLATION ENERGY GROUP, INC. AND EXELON CORPORATION (TAC NOS. ME6234 - ME6238) |
| | On September 26, 2011, a Category 1 meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Nuclear Group, LLC (CENG) and Exelon Corporation at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. As stated in the meeting notice dated September 12, 2011 (Agencywide Document Access and Management System (ADAMS) Accession No. ML112500517), the meeting was closed to the public since the information to be discussed had previously been determined to contain proprietary commercial information and be withheld from public disclosure in accordance with 10 CFR 2.390 as stated in the NRC letter dated August 19, 2011 (ML112270380). |
| | As part of the NRC staff's review of the proposed merger between Exelon Corporation and Constellation Energy Group, Inc. (CEG) (ML11138A159), the staff has focused on foreign ownership, control or influence (FOCI). CENG's supplemental letter of August 12,2011 (ML11234A062), led to further staff FOCI concerns that needed to be discussed and resolved. |
| | The staff discussed the role and function of the CENG Nuclear Advisory Committee along with FOCI concerns associated with EDF, CENG, and Exelon. A list of attendees is provided in the Enclosure. There were no slides or handouts. |
| | Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220, 50-244, 50-317,50-318, and 50-410 |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
| List of Attendees cc w/encl: Distribution via Listserv DISTRIBUTION: PUBLIC LPL1-1 r/f RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl1-1 Resource RidsNrrPMREGinna Resource RidsNrrLASLittle Resource RidsOgcRp Resource RidsRgn1 MailCenter ResouCSteger. NRR RidsNrrPMNineMilePoint Resource RidsNrrDprPfib RidsNrrDpr JSimpson, NRR TFredrichs, NRR rce ASimmons. NRR JWhitney, NSIR SHarwell, NRR RidsNrrDorlLPL4 Resource JMcHale, EDO Region 1 ADAMS Accession No. PKG ML 112700666 Meetin Notice M L OFFICE LPL1-1/PM LPL1-1/LA PFIB/BC DORLlLPL1-1/BC NAME DPickett NSalgado DATE 9/28/11 CRegan 9/30/11 _ =,-=""=..OFFICIAL RECORD COpy | | |
| }} | | List of Attendees cc w/encl: Distribution via Listserv |
| | |
| | LIST OF ATTENDEES SEPTEMBER 26, 2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC AND EXELON CORPORATION PROPOSED CONSTELLATION/EXELON MERGER CENG Bruce Montgomery Robert Nelson Steve Miller Christopher Regan Carey Fleming Michael Markley Sean Klein Jo Ann Simpson Ned Tyler Anneliese Simmons Thomas Fredrichs Shawn Harwell Beth Mizuno Jim Whitney Douglas Pickett EXELON CENG NUCLEAR ADVISORY COMMITTEE Brad Fewell Richard Meserve Carol Peterson WINSTON & STRAWN/EDF HOGAN LOVELLS David Repka Dan Stenger Enclosure |
| | |
| | October 3, 2011 LICENSEE: Constellation Energy Nuclear Group, LLC FACILITY: Calvert Cliffs Nuclear Power Plant, Unit Nos, 1 and 2 Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 RE. Ginna Nuclear Power Plant |
| | |
| | ==SUBJECT:== |
| | |
| | ==SUMMARY== |
| | OF SEPTEMBER 26, 2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC ON THE PROPOSED MERGER BETWEEN CONSTELLATION ENERGY GROUP, INC, AND EXELON CORPORATION (TAC NOS, ME6234 - ME6238) |
| | On September 26,2011, a Category 1 meeting was held between the U,S, Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Nuclear Group, LLC (CENG) and Exelon Corporation at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, As stated in the meeting notice dated September 12, 2011 (Agencywide Document Access and Management System (ADAMS) Accession No, ML112500517), the meeting was closed to the public since the information to be discussed had previously been determined to contain proprietary commercial information and be withheld from public disclosure in accordance with 10 CFR 2.390 as stated in the NRC letter dated August 19, 2011 (ML112270380). |
| | As part of the NRC staff's review of the proposed merger between Exelon Corporation and Constellation Energy Group, Inc. (CEG) (ML11138A159), the staff has focused on foreign ownership, control or influence (FOCI). CENG's supplemental letter of August 12, 2011 (ML11234A062), led to further staff FOCI concerns that needed to be discussed and resolved. |
| | The staff discussed the role and function of the CENG Nuclear Advisory Committee along with FOCI concerns associated with EDF, CENG, and Exelon A list of attendees is provided in the Enclosure. There were no slides or handouts. |
| | IRN Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220, 50-244,50-317,50-318, and 50-410 |
| | |
| | ==Enclosure:== |
| | |
| | List of Attendees cc w/encl: Distribution via Listserv DISTRIBUTION: |
| | PUBLIC RidsRgn1 MailCenter Resource ASimmons. NRR LPL1-1 r/f CSteger. NRR JWhitney, NSIR RidsAcrsAcnw_MailCTR Resource RidsNrrPMNineMilePoint Resource SHarwell, NRR RidsNrrDorlLpl1-1 Resource RidsNrrDprPfib RidsNrrDorlLPL4 Resource RidsNrrPMREGinna Resource RidsNrrDpr JMcHale, EDO Region 1 RidsNrrLASLittle Resource JSimpson, NRR RidsOgcRp Resource TFredrichs, NRR ADAMS Accession No. PKG ML112700666 Meetin Notice M L 112500517~~eti!:l3l~~~~L1127006.~ 1_~=~~_"==~""~-'~F='-"'<"-'<<~~~-===""'il OFFICE LPL1-1/PM LPL1-1/LA PFIB/BC DORLlLPL 1-1/BC NAME DPickett CRegan NSalgado DATE 9/28/11 9/30/11 |
| | =*"r="'~-*~ _ =,-=""=..=---""'=="==~'" |
| | OFFICIAL RECORD COpy}} |
Letter Sequence Meeting |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
|
MONTHYEARML11109A0352011-04-15015 April 2011 Independent Spent Fuel Storage Installation, Nine Mile Point and Re. Ginna, Notice Regarding Change in Corporate Form of E.D.F. International SA Project stage: Request RS-11-084, Request for Threshold Determination Under 10 CFR 50.802011-05-18018 May 2011 Request for Threshold Determination Under 10 CFR 50.80 Project stage: Request ML1116000442011-06-0909 June 2011 Acceptance Review for Proposed Exelon/Constellation Merger Project stage: Acceptance Review ML11173A0672011-06-17017 June 2011 Independent Spent Fuel Storage Installation, Nine Mile, Units 1 & 2, R. E. Ginna and Independent Spent Fuel Storage Installation - Supplement to Application for Approval of Indirect Transfer of Control of Licenses Project stage: Request RS-11-105, Response to Request for Additional Information Regarding Request for Threshold Determination Under 10 CFR 50.802011-06-24024 June 2011 Response to Request for Additional Information Regarding Request for Threshold Determination Under 10 CFR 50.80 Project stage: Response to RAI ML1115803382011-06-28028 June 2011 Notice of Consideration of Approval of Application Regarding Proposed Corporate Merger and Opportunity for a Hearing - R.E. Ginna Nuclear Power Plant and R.E. Ginna Independent Spent Fuel Storage Installation Project stage: Other ML1115803442011-06-28028 June 2011 Notice of Consideration of Approval of Application Regarding Proposed Corporate Merger and Opportunity for a Hearing - R.E. Ginna Nuclear Power Plant and R.E. Ginna Independent Spent Fuel Storage Installation Project stage: Other ML1115803652011-06-28028 June 2011 Notice of Consideration of Approval of Application Regarding Proposed Corporate Merger and Opportunity for a Hearing - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, and Calvert Cliffs Independent Spent Fuel Storage Installation (TA Project stage: Other ML1115803762011-06-28028 June 2011 Notice of Consideration of Approval of Application Regarding Proposed Corporate Merger and Opportunity for a Hearing - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, and Calvert Cliffs Independent Spent Fuel Storage Installation (TA Project stage: Other ML1115804052011-06-28028 June 2011 Notice of Consideration of Approval of Application Regarding Proposed Corporate Merger and Opportunity for a Hearing - Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 Project stage: Other ML1115804312011-06-28028 June 2011 Notice of Consideration of Approval of Application Regarding Proposed Corporate Merger and Opportunity for a Hearing - Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 Project stage: Other ML1119304532011-07-14014 July 2011 Request for Additional Information - Proposed Merger Between Constellation Energy Group, Inc. and Exelon Corporation Project stage: RAI RS-11-127, Response to Request for Additional Information - Proposed Merger Between Constellation Energy Group, Inc. and Exelon Corporation2011-08-0303 August 2011 Response to Request for Additional Information - Proposed Merger Between Constellation Energy Group, Inc. and Exelon Corporation Project stage: Response to RAI ML11234A0622011-08-12012 August 2011 Response to Nrc'S Request for Additional Information on License Transfer Application Project stage: Request ML1122703802011-08-19019 August 2011 Request for Withholding Information from Public Disclosure for Proposed Merger Between Constellation Energy Group, LLC and Exelon Corporation Project stage: Withholding Request Acceptance ML1127006812011-10-0303 October 2011 Summary of September 26, 2011, Meeting with Constellation Energy Nuclear Group, LLC on the Proposed Merger Between Constellation Energy Group, Inc. and Exelon Corporation (TAC Nos. ME6234 - ME6238) Project stage: Meeting ML1128402172011-10-12012 October 2011 Request for Additional Information(Public) Proposed Merger Between Exelon Corporation and Constellation Energy Group, Inc (TAC Nos ME6234-ME6238) Project stage: RAI ML1128401992011-10-12012 October 2011 Transmittal Letter, Request for Additional Information (NON-PROPRIETARY) Proposed Merger Between Exelon Corporation and Constellation Energy Group, Inc. Project stage: RAI ML11335A0242011-11-10010 November 2011 Units 1 & 2, R. E. Ginna and Independent Spent Fuel Storage Installations - Response to Nrc'S Request for Addtional Information on License Transfer Application Project stage: Request RS-11-181, Submittal of Revised Post-Transaction Organization Related to Application for Approval of Indirect Transfer of Control of Licenses2011-11-11011 November 2011 Submittal of Revised Post-Transaction Organization Related to Application for Approval of Indirect Transfer of Control of Licenses Project stage: Request ML11325A2582011-11-18018 November 2011 Units 1 & 2 and Independent Spent Fuel Storage Installation - Response to Nrc'S Request for Additional Information on License Transfer Application Project stage: Request RS-11-187, ISFSI, Nine Mile Point, Units 1 & 2, and R.E. Ginna & ISFSI, Submittal of Additional Information Exelon Consolidated Financial Statements Related to Application for Approval of Indirect Transfer of Control of Licenses2011-11-22022 November 2011 ISFSI, Nine Mile Point, Units 1 & 2, and R.E. Ginna & ISFSI, Submittal of Additional Information Exelon Consolidated Financial Statements Related to Application for Approval of Indirect Transfer of Control of Licenses Project stage: Request ML12032A1532012-01-25025 January 2012 Independent Spent Fuel Storage Installation, Nine Mile, Units 1 & 2, R. E. Ginna and Independent Spent Fuel Storage Installation - Supplemental Information Project stage: Request ML1203400102012-02-15015 February 2012 FRN: General Notice. Order Approving Application Regarding Proposed Corporate Merger and Indirect Transfer of License Project stage: Request ML1203400312012-02-15015 February 2012 FRN: General Notice. Order Approving Application Regarding Proposed Corporate Merger and Indirect Transfer of Licenses Project stage: Request ML1135603972012-02-15015 February 2012 FRN: General Notice. Order Approving Application Regarding Proposed Corporate Merger and Indirect Transfer of License Project stage: Request ML1135604082012-02-15015 February 2012 Safety Evaluation by the Office of Nuclear Reactor Regulation Indirect Transfer of Control of Facility Operating Licenses Due to the Proposed Merger Between Exelon Corp & Constellation Energy Group, Inc., Calvert Cliffs Nuclear Power Plant, Project stage: Request ML1135603812012-02-15015 February 2012 Order Approving Corporate Merger Between Exelon Corporation and Constellation Energy Group, Inc. and Resultant Indirect Transfer of Renewed Facility Operating Licenses - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, and Independent Project stage: Acceptance Review ML12081A0182012-03-12012 March 2012 Notification of Closing of Corporate Merger of Exelon Corporation and Constellation Energy Group, Inc Project stage: Other ML13037A3802012-12-17017 December 2012 Attachment 1b, 2012 Annual Report of the Ceng Independent Nuclear Advisory Committee Project stage: Other ML13037A3792013-01-30030 January 2013 R. E. Ginna, Submittal of Annual Report of the Nuclear Advisory Committee Project stage: Other ML16011A0032016-01-0707 January 2016 Submittal of Annual Report of the Nuclear Advisory Committee Project stage: Other 2011-06-28
[Table View] |
Summary of September 26, 2011, Meeting with Constellation Energy Nuclear Group, LLC on the Proposed Merger Between Constellation Energy Group, Inc. and Exelon Corporation (TAC Nos. ME6234 - ME6238)ML112700681 |
Person / Time |
---|
Site: |
Calvert Cliffs, Nine Mile Point, Ginna |
---|
Issue date: |
10/03/2011 |
---|
From: |
Pickett D Plant Licensing Branch 1 |
---|
To: |
|
---|
Pickett D, NRR/DORL/LPL1-1, 415-1364 |
Shared Package |
---|
ml11270066 |
List: |
---|
References |
---|
TAC ME6234, TAC ME6235, TAC ME6236, TAC ME6237, TAC ME6238 |
Download: ML112700681 (3) |
|
|
---|
Category:Meeting Summary
MONTHYEARML23352A0592024-01-0909 January 2024 Summary of December 11, 2023, Meeting with Constellation on Alternative Request Involving Carbon Fiber Reinforced Polymer Composite ML23320A2472023-11-17017 November 2023 Constellation - Summary of November 14, 2023, Public Pre-Application Meeting with Constellation Energy Generation, LLC on Adoption of TSTF-591 ML23271A2682023-10-0505 October 2023 September 25, 2023, Summary of with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans ML23263B1062023-09-22022 September 2023 R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23055A0352023-03-24024 March 2023 Summary of February 23, 2023, with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans to Revise Emergency Action Levels ML23033A6662023-02-0909 February 2023 Summary of Public Meeting with Constellation Energy Generation, LLC (Constellation) to Discuss Its Request for Alternatives for Certain Steam Generator Weld Inspections for Calvert Cliffs 1 & 2, Byron 1 & 2, Braidwood 1 & 2, and Ginna ML22346A0002022-12-14014 December 2022 Summary of November 3, 2022, Meeting with Constellation to Discuss Planned License Amendment Requests to Adopt TSTF-505 and 10 CFR 50.69 ML22264A1992022-11-14014 November 2022 Summary of August 22, 2022, Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Steam Generator Welds (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML22159A2272022-06-0808 June 2022 Summary of May 10, 2022, Pre-Application Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, Llc, Regarding a Proposed License Amendament Request (Lar) for Calvert Cliffs Nuclear Power Plant ML22144A0202022-05-26026 May 2022 Summary of Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Proposed Alternative for Examinations of Certain Pressurizer Welds at Calvert Cliffs ML22066A0012022-03-22022 March 2022 Summary, January 10, 2022, Closed Meeting with Exelon Generation Company, Llc, Proposed Relief Request for Alternative Repair of Buried Saltwater Piping with Carbon Fiber Reinforced Polymer Composite System ML21333A1532021-11-30030 November 2021 Summary of November 16, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Extend the Inservice Inspection Interval ML21237A0412021-08-30030 August 2021 Summary of the July 27, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use Case OMN-28, ML21228A0742021-08-27027 August 2021 Summary of July 13, 2021, Meeting with Exelon Generation Company, LLC Concerning License Amendment Request for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, Concerning Spent Fuel Pool Cooling Design Basis Change (L-2021-LLA-0112) ML21176A0822021-07-0606 July 2021 June 15, 2021, Summary of Meeting with Exelon Generation Company, LLC Vessel Nozzle Repair Related to a Planned Request for an Alternative Related to Reactor Pressure ML21161A1082021-06-25025 June 2021 Summary of Pre-Application Meeting with Exelon Generation Company, LLC on Planned Submittal of License Amendment Request for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, Concerning Spent Fuel Pool Cooling Design Basis Change ML21139A1852021-06-22022 June 2021 Summary of Meeting with Exelon Generation Company, LLC Regarding Its Requested Alternative to Eliminate Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting ML21033A6252021-02-16016 February 2021 Summary of January 5, 2021, Meeting with Exelon Generation Company, LLC Regarding License Amendment Request to Adopt Reactor Pressure Vessel Water Inventory Control Enhancements at Nine Mile Point Nuclear Station, Unit 1 ML21011A2822021-01-21021 January 2021 Summary of January 6, 2021, Presubmittal Meeting Between the NRC and Exelon Generation Company, LLC Regarding Licensing Activities to Support the Planned Early Closures of Byron, Unit Nos. 1 and 2 and Dresden, Units 2 and 3 ML20351A2832020-12-18018 December 2020 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20342A3522020-12-10010 December 2020 Summary of November 13, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alterantive to Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting (EPID-L-2020-LRM-0102) ML20323A0332020-12-0101 December 2020 Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20272A0132020-10-0707 October 2020 Summary of September 3, 2020, Meeting with Exelon Generation Company, LLC Concerning Supplemental Position Indication Testing Interval Alternative Request ML20230A0222020-08-20020 August 2020 Summary of August 6, 2020, Meeting with Exelon Generation Company, LLC Planned Submittal of a License Amendment Request and Alternative Request on Excess Check Valve Testing ML20205L3712020-07-23023 July 2020 and R.E. Ginna Nuclear Power Plant Summary of Meeting ML20197A2722020-07-15015 July 2020 2020 Beaver Valley, Calvert Cliffs, Limerick Peach Bottom, Susquehanna Annual Assessment Webinar Summary ML20181A0002020-06-29029 June 2020 Summary of 6/24/20 Meeting with Exelon Generation Company, LLC Regarding Planned Request for Alternative to Supplemental Valve Position Indication Testing Requirements for Braidwood, Calvert Cliffs, Clinton, Limerick, Nine Mile, Peach Botto ML20160A0432020-06-11011 June 2020 Summary of April 9, 2020, Meeting with Exelon Generation Company, LLC Regarding License Amendment Request to Change Allowable Main Steam Isolation Valve Leak Rates at Nine Mile Point Nuclear Station, Unit 2 ML20157A1822020-06-0808 June 2020 Summary of May 8, 2020, Meeting with Exelon Generation Company, LLC, Regarding Proposed Emergency License Amendment Request Involving Control Room Air Treatment System ML20077G9742020-03-18018 March 2020 R. E. Ginna Nuclear Power Plant - Summary of March 2, 2020, Meeting Regarding License Amendment Request to Support Shutdown of Reactor During Upcoming Refueling Outage ML19326C3582019-12-0303 December 2019 Summary of November 20, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Revise the Quality Assurance Program ML19326A3152019-12-0303 December 2019 Summary of November 18, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Supplemental Valve Position Indication Testing Requirements ML19302D3152019-10-28028 October 2019 Annual Assessment Meeting for James A. Fitzpatrick Nuclear Power Plant and Nine Mile Point Nuclear Generating Station - Meeting Summary ML19253C7552019-09-10010 September 2019 Annual Assessment Meeting Summary ML19183A2382019-07-19019 July 2019 Summary of Meeting with Exelon Generation Company, LLC, Planned Concurrent Submittal of Risk-Informed Completion Time and Risk-Informed Categorization ML19162A0272019-06-21021 June 2019 Summary of June 4, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Extend the Test Interval for Safety Relief Valves ML19136A2752019-05-15015 May 2019 Aam 2019 Meeting Summary ML19135A1052019-05-15015 May 2019 Aam Summary Data Sheet of 2018 Plant Performance ML20108F0902019-04-20020 April 2019 April 15, 2020, Meeting Summary with Exelon Generation Company, LLC Regarding Planned Request to Defer Submittal of Owner'S Activity Report (Braidwood 2,Byron 2,Calvert Cliffs 1, LaSalle 1, Limerick 1, Nine Mile Point 2, Quad 2, R. E. Ginna ML19036A8832019-02-0707 February 2019 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use ASME Code Case N-879 ML18354B1712019-01-0202 January 2019 Summary of December 19, 2018, Meeting with Exelon Generation Company, LLC Regarding the Use of Boiling Water Reactor Vessel and Internals Project Guidelines ML18347B4932019-01-0202 January 2019 Summary of Pre-Application Meeting with Exelon Generation Co., LLC (Exelon) Forthcoming License Amendment Requests to Revise Technical Specification Requirements for Main Steam Isolation Valve Leak Rate Tests ML18325A1712018-11-28028 November 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned Fleet License Amendment Request to Revise Technical Specifications for High Radiation Areas ML18297A1722018-10-26026 October 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned License Amendment Request to Adopt TSTF-427 ML18292A8202018-10-24024 October 2018 October 4, 2018, Summary of Pre-Application Meeting with Exelon Generation Co., LLC on Planned Submittal of Licensing Action for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, Risk-Informed Categorization and Treatment ML18283B7992018-10-15015 October 2018 Summary of Telephone Conference with Exelon Generation Company, LLC, Request to Revise Nine Mile Point Nuclear Station, Unit 1, Technical Specifications with New Requirements on Reactor Pressure Vessel Water Inventory Control ML18262A3662018-09-18018 September 2018 August 21, 2018, James A. Fitzpatrick Nuclear Power Plant (Fitzpatrick) and Nine Mile Point Nuclear Generating Station (Nine Mile Point) Summary of Public Meeting ML18222A2852018-09-0404 September 2018 Summary of Telephone Conf. with Exelon Generation Company, LLC Regarding a Request to Revise Nine Mile Point Nuclear Station, Unit 1 Technical Specifications with New Requirements on Reactor Pressure Vessel Water Inventory Control 2024-01-09
[Table view] Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 IR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants NMP1L3564, Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b NMP1L3563, Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208)2023-12-0404 December 2023 Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) IR 05000220/20234022023-11-28028 November 2023 Security Baseline Inspection Report 05000220/2023402 and 05000410/2023402 ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank NMP1L3557, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000220/20234202023-11-0101 November 2023 Security Baseline Inspection Report 05000220/2023420 and 05000410/2023420 ML23305A0052023-11-0101 November 2023 Operator Licensing Examination Approval IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 IR 05000220/20230032023-10-25025 October 2023 Integrated Inspection Report 05000220/2023003 and 05000410/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection IR 05000220/20235012023-10-17017 October 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000220/2023501 and 05000410/2023501 IR 05000220/20230112023-10-16016 October 2023 Comprehensive Engineering Team Inspection Report 05000220/2023011 and 05000410/2023011 2024-02-05
[Table view] |
Text
~f>,1\ REGo~ UNITED STATES
~.§J\,; '1)-0"ll NUCLEAR REGULATORY COMMISSION
- P
<l
-:0:. WASHINGTON, D.C. 20555*0001
\ii :
~,,! October 3, 2011
- "", ~o LICENSEE: Constellation Energy Nuclear Group, LLC FACILITY: Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 R.E. Ginna Nuclear Power Plant
SUBJECT:
SUMMARY
OF SEPTEMBER 26,2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC ON THE PROPOSED MERGER BETWEEN CONSTELLATION ENERGY GROUP, INC. AND EXELON CORPORATION (TAC NOS. ME6234 - ME6238)
On September 26, 2011, a Category 1 meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Nuclear Group, LLC (CENG) and Exelon Corporation at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. As stated in the meeting notice dated September 12, 2011 (Agencywide Document Access and Management System (ADAMS) Accession No. ML112500517), the meeting was closed to the public since the information to be discussed had previously been determined to contain proprietary commercial information and be withheld from public disclosure in accordance with 10 CFR 2.390 as stated in the NRC letter dated August 19, 2011 (ML112270380).
As part of the NRC staff's review of the proposed merger between Exelon Corporation and Constellation Energy Group, Inc. (CEG) (ML11138A159), the staff has focused on foreign ownership, control or influence (FOCI). CENG's supplemental letter of August 12,2011 (ML11234A062), led to further staff FOCI concerns that needed to be discussed and resolved.
The staff discussed the role and function of the CENG Nuclear Advisory Committee along with FOCI concerns associated with EDF, CENG, and Exelon. A list of attendees is provided in the Enclosure. There were no slides or handouts.
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220, 50-244, 50-317,50-318, and 50-410
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF ATTENDEES SEPTEMBER 26, 2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC AND EXELON CORPORATION PROPOSED CONSTELLATION/EXELON MERGER CENG Bruce Montgomery Robert Nelson Steve Miller Christopher Regan Carey Fleming Michael Markley Sean Klein Jo Ann Simpson Ned Tyler Anneliese Simmons Thomas Fredrichs Shawn Harwell Beth Mizuno Jim Whitney Douglas Pickett EXELON CENG NUCLEAR ADVISORY COMMITTEE Brad Fewell Richard Meserve Carol Peterson WINSTON & STRAWN/EDF HOGAN LOVELLS David Repka Dan Stenger Enclosure
October 3, 2011 LICENSEE: Constellation Energy Nuclear Group, LLC FACILITY: Calvert Cliffs Nuclear Power Plant, Unit Nos, 1 and 2 Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 RE. Ginna Nuclear Power Plant
SUBJECT:
SUMMARY
OF SEPTEMBER 26, 2011, MEETING WITH CONSTELLATION ENERGY NUCLEAR GROUP, LLC ON THE PROPOSED MERGER BETWEEN CONSTELLATION ENERGY GROUP, INC, AND EXELON CORPORATION (TAC NOS, ME6234 - ME6238)
On September 26,2011, a Category 1 meeting was held between the U,S, Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Nuclear Group, LLC (CENG) and Exelon Corporation at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, As stated in the meeting notice dated September 12, 2011 (Agencywide Document Access and Management System (ADAMS) Accession No, ML112500517), the meeting was closed to the public since the information to be discussed had previously been determined to contain proprietary commercial information and be withheld from public disclosure in accordance with 10 CFR 2.390 as stated in the NRC letter dated August 19, 2011 (ML112270380).
As part of the NRC staff's review of the proposed merger between Exelon Corporation and Constellation Energy Group, Inc. (CEG) (ML11138A159), the staff has focused on foreign ownership, control or influence (FOCI). CENG's supplemental letter of August 12, 2011 (ML11234A062), led to further staff FOCI concerns that needed to be discussed and resolved.
The staff discussed the role and function of the CENG Nuclear Advisory Committee along with FOCI concerns associated with EDF, CENG, and Exelon A list of attendees is provided in the Enclosure. There were no slides or handouts.
IRN Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220, 50-244,50-317,50-318, and 50-410
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsRgn1 MailCenter Resource ASimmons. NRR LPL1-1 r/f CSteger. NRR JWhitney, NSIR RidsAcrsAcnw_MailCTR Resource RidsNrrPMNineMilePoint Resource SHarwell, NRR RidsNrrDorlLpl1-1 Resource RidsNrrDprPfib RidsNrrDorlLPL4 Resource RidsNrrPMREGinna Resource RidsNrrDpr JMcHale, EDO Region 1 RidsNrrLASLittle Resource JSimpson, NRR RidsOgcRp Resource TFredrichs, NRR ADAMS Accession No. PKG ML112700666 Meetin Notice M L 112500517~~eti!:l3l~~~~L1127006.~ 1_~=~~_"==~""~-'~F='-"'<"-'<<~~~-===""'il OFFICE LPL1-1/PM LPL1-1/LA PFIB/BC DORLlLPL 1-1/BC NAME DPickett CRegan NSalgado DATE 9/28/11 9/30/11
=*"r="'~-*~ _ =,-=""=..=---""'=="==~'"
OFFICIAL RECORD COpy