IR 05000220/2023011
| ML23289A017 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point (DRP-063, NPF-069) |
| Issue date: | 10/16/2023 |
| From: | Mel Gray Division of Operating Reactors |
| To: | Rhoades D Constellation Energy Generation, Constellation Nuclear |
| References | |
| IR 2023011 | |
| Download: ML23289A017 (1) | |
Text
October 16, 2023
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000220/2023011 AND 05000410/2023011
Dear David Rhoades:
On September 29, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Nine Mile Point Nuclear Station, Units 1 and 2. The NRC inspectors discussed the results of this inspection with Peter Orphanos, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety
Docket Nos. 05000220 and 05000410 License Nos. DPR-63 and NPF-69
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000220 and 05000410
License Numbers:
Report Numbers:
05000220/2023011 and 05000410/2023011
Enterprise Identifier: I-2023-011-0011
Licensee:
Constellation Energy Generation, LLC
Facility:
Nine Mile Point Nuclear Station
Location:
Oswego, NY
Inspection Dates:
September 11, 2023 to September 29, 2023
Inspectors:
P. Cataldo, Senior Reactor Inspector
N. Floyd, Senior Reactor Inspector
D. Kern, Senior Reactor Inspector
J. Kulp, Senior Reactor Inspector
N. Mentzer, Reactor Inspector
E. Miller, Reactor Inspector
J. Schoppy, Senior Reactor Inspector
A. Turilin, Reactor Inspector
Approved By:
Mel Gray, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Nine Mile Point Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Comprehensive Engineering Team Inspection
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Structures, Systems, and Components (SSCs) (IP section 03.01)===
For each component sample listed below, the team reviewed licensing and design basis documents and a sampling of applicable operator actions, periodic testing results, corrective action program documents, internal and external operating experience, preventive and corrective maintenance work orders, modifications, and aging management programs.
Additionally, the team performed walkdowns of the component or procedure and conducted interviews with licensee personnel.
The team used the attributes contained in IP 71111.21M, Appendix A, Component Review Attributes, such as those listed below as guidance. Specifically, the team evaluated these attributes in the course of applying 71111.21M, Appendix B, Component Design Review Considerations and 71111.21M, Appendix C, Component Walkdown Considerations.
- (1) Unit 1 Loss of Main Feedwater Initiating Event
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (2) Unit 1 High Pressure Coolant Injection Pump No. 12 (PMP-29-03)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (3) Unit 1 Electromatic Relief Valve 123
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
The team used Appendix B guidance for Valves, Instrumentation, and As-Built System.
- (4) Unit 1 Emergency Condenser Loop 11
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (5) Unit 2 Loss of 4 KV Division II Emergency Bus (2ENS*SWG103) Initiating Event
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electrical Loads, Motor Control Centers, and As-Built System.
- (6) Unit 2 A Residual Heat Removal Heat Exchanger Service Water Supply Isolation Valve (2SWP*MOV90A)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (7) Unit 2 A Residual Heat Removal Pump (2RHS*P1A)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (8) Unit 2 A Residual Heat Removal Pump Motor
- Energy sources (electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electrical Loads, Motor Control Centers, and As-Built System.
- (9) Unit 2 Suppression Pool Purge Nitrogen Supply Outboard Outlet Isolation Valve (2CPS*AOV111)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
Modifications (IP section 03.02) (5 Samples)
- (1) ECP-16-000339: Replace the EDG 102 and EDG103 Timing Relays
- (2) ECP-18-000398: Add Redundant Valve in Series with 2EGS*AOV2011A /
2EGS*AOV2011B (Post Lube Pilot Valves)
- (3) ECP-20-000570: NMP1 Emergency Diesel Generator Tank Cathodic Protection System Modification
- (4) ECP-21-000361: Modify NMP2 Service Water Pump Interlock Logic
- (5) ECP-22-000282: Replace PT Fuses for DIV I & II located in 2EGS*PNL11 and 2EGS*PNL31 10 CFR 50.59 Evaluations/Screening (IP section 03.03) (17 Samples)
(1)5059-2020-168, Disable Moisture Separator High Level Turbine Trip in the Steam Admission Trip Circuit fed from Battery Board 11 (Steam Leak Created Battery Ground), dated September 18, 2020 (2)5059-2020-172, Modification to Install High Point Vents in U1 Control Room Chilled Water Piping, dated September 24, 2020 (3)5059-2020-194, Shielding for the DFR Line From 2DFR*MOV120 to the Containment Penetration, dated November 18, 2020 (4)5059-2020-205, Long Standing Tagout U2X-CCP-0046, dated December 7, 2020 (5)5059-2020-210, Modify Snubbers 2ISC-21PSSP003C1 and 2WCS-PSSP886A1, dated July 12, 2023 (6)5059-2021-016, Control Room Panel F1, dated April 12, 2021 (7)5059-2021-019, NMP1 EOP Support Procedure, dated March 27, 2021 (8)5059-2021-024, Unit 2 Refuel Bridge TRM 3.9.4 Change Evaluation, dated March 11, 2021 (9)5059-2021-043, Install Capacitors on Detector Strings and Fire/Smoke Dampers in Unit 1 Local Fire Panels, dated October 15, 2021 (10)5059-2021-053, Operators Rounds Guide, dated February 25, 2021 (11)5059-2021-059, Change Frequency of N1-IPM-036-017, Reactor Hi Water Level - 13 Feedwater Pump Trip Verification per PMC-20-126425, dated March 4, 2021 (12)5059-2021-065, Main Power Transformer Deluge System Replacement, dated March 18, 2021 (13)5059-2021-068, Add UT as an Inspection Method That Gives Credit to the Top Guide Inspection and Reset Inspection Interval, dated March 16, 2021 (14)5059-2021-110, Residual Heat Removal Reject Line to Reactor Water Cleanup System Cross-tie, dated January 19, 2021 (15)5059-2022-014, NMP1 NERC PRC-026 Compliance: Generator Protection Relays, dated May 16, 2022 (16)5059-2022-105, Standby Diesel Generators, dated September 28, 2022 (17)5059-2022-120, Tech Eval to Defeat Annunciator Input from U1 Refuel Bridge High Range Rad Monitor Input via S-ARP-001, dated October 31, 2022
Operating Experience Samples (IP section 03.04) (3 Samples)
- (1) NRC Information Notice 2019-01: Inadequate Evaluation of Temporary Alterations
- (2) Part 21 Report - Nonconforming Relay Led to Failures of Battery Chargers (EN 55453)
- (3) Part 21 Communication - Failure of Safety-Related Spring Charging Motor (AR 4401753)
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On September 29, 2023, the inspectors presented the Comprehensive Engineering Team Inspection results to Peter Orphanos, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
1701253.301
Structural Integrity Associates, Inc., NMP-1 Top Guide Grid
Beam Flaw Assessment Update
Revision 0
Nine Mile Point Unit 2 Diesel Generator Loading
Revision 13
25VDC Breakers Coordination
Revision 0
RHR Heat Exchanger Performance - K Values used in
Containment Analyses and Recommended HX Performance
Testing Acceptance Criteria
dated 5/6/09
S0-FLOOD-F001
Internal Flooding Hazard Analysis
Revision 1
Corrective Action
Documents
01974089
2429598
2524898
2629695
2664561
04130528
04169109
230952
245321
249798
04327479
04346002
04372692
04401753
04408464
04420027
04428667
04451825
04485431
04486137
04521302
04535217
04668582
04668639
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
04674179
04703564
Corrective Action
Documents
Resulting from
Inspection
4697228
04698169
04701751
04701865
04701902
04701979
04702075
04702077
04702078
04702179
04702247
04702260
04702269
04702502
04702513
04702527
04702530
04702535
04702582
04702791
04702825
04702854
04702855
04703532
04703535
04703554
04704067
04704269
04704311
04704897
04704971
04705153
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
04705291
04705310
04705311
04705312
04705352
04705400
04705408
04705507
04705508
04705539
04705605
04705679
04705696
04705775
04705794
Drawings
B-42346-C, Sh. 6
Unit 1 Fire Barrier Penetration Seal Details for FS-5
Revision 1
C-35970-C, Sh. 1
Unit 1 General Floor Plan Reactor Building El. 237 &
Turbine Building El. 250
Revision 6
Engineering
Evaluations
ADC-11-000685
Minute Operator Action Time for Circulating Water Line
Break
Revision 0
CNF-TGUT-01
Hitachi Ultrasonic Exam Results
dated 4/4/21
ECP-20-000504
Disable Moisture Separator Hight Level Turbine Trip in the
Steam Admission Trip Circuit fed from Battery Board 11
(Steam Leak Created Battery Ground)
Revision 0
ECP-20-000605
NMP1 Reactor Pressure Instrument Channel Surveillance
Frequency Extension from 24 Months to 48 Months
Revision 0
ECP-21-000016
Cross-tie between Residual Heat Removal Reject Line to
Reactor Water Cleanup System Discharge to Condenser
Revision 1
ECP-22-000366
Technical Evaluation to Defeat Annunciator Input from Unit 1
Refuel Bridge High Range Radiation Monitor
Revision 0
N2-MISC-001
Internal Events NMP2 Time Sensitive Operator Actions PRA
Input from the 2019 Model Update
Revision 2
Miscellaneous
Mersen 9F60 Series Potential Transformer Medium Voltage
Fuses
dated 2018
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Shielding Approval Form, 2-SHIELDIN-RB-215-031
dated
9/18/23
Fuse, 0.5E, 5.5KV,
- P.T. PR-1 (PO# 01356413, Catalog ID#
0011801524-2, DP# LIM-05495, CG)
Revision 1
N1-EPM-082-801
Emergency Generator Diesel Fuel Storage Buried Tanks
and Piping Cathodic Protection System Potential Survey
performed
9/23/22
N1-EPM-GEN-
24
Electromatic Solenoid Inspection
performed
3/27/23
N1-ISP-066-003
Auto Depressurization System Operability Test
performed
3/26/23
N1-PRA-012
Internal Flooding Analysis Notebook
Revision 3
N1-ST-Q3
High Pressure Coolant Injection Pump and Check Valve
Operability Test
performed
4/22/23
N2-OSP-RHS-
Q@004
RHR System Loop A Pump & Valve Operability Test and
System Integrity Test and ASME XI Pressure Test
performed
7/19/23
N2-RSP-RMS-
M003
Monthly Source Check of DRMS Tech Spec Radiation
Monitors
performed
8/23/23
Recent Issues Related to the Commercial Grade Dedication
of Allen Bradley 700-RTC Relays
dated
2/17/16
PCR-22-02698
Add Step to Reset Panel to Standby Checks Using Switch to
Reset Logic
dated
9/21/22
S-MMP-SDM-001
Quarterly PM Inspection of Gates and Doors
dated
7/28/23
Procedures
ER-NM-331-1001
Nine Mile Point Unit 1 Reactor Internals Program Basis
Document
Revision 4
N1-EPM-GEN-
150
4.16KV Breaker Inspection P.M.
Revision 20
N2-EOP-6.21
Containment Venting
Revision 7
N2-EPM-GEN-
550
GE 4.16KV Magne-Blast Breaker P.M.
Revision 13
N2-OSP-SWP-
M001
Service Water Valve Position Verification
Revision 5
N2-PM-082
RPV Flood Up/Draindown
Revision 21
N2-SOP-03
Loss of AC Power
Revision 22
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
OP-NM-102-106
Operator Response Time Program at Nine Mile Point
Revision 17
Work Orders
C92180736
C92180870
C92562700
C92562702
C93226857
C93480108
C93718001
C93771790
C93777205
C93777210
C93784028
C93847507
C93886674
06-02118-00
06-02119-00