ML21161A108

From kanterella
Jump to navigation Jump to search

Summary of Pre-Application Meeting with Exelon Generation Company, LLC on Planned Submittal of License Amendment Request for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, Concerning Spent Fuel Pool Cooling Design Basis Change
ML21161A108
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 06/25/2021
From: Marshall M
Plant Licensing Branch 1
To: Rhoades D
Exelon Generation Co
Marshall M, NRR/DORL/LPLI, 415-2871
References
EPID L-2021-LRM-0051
Download: ML21161A108 (5)


Text

June 25, 2021 LICENSEE: Exelon Generation Company, LLC FACILITY: CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2

SUBJECT:

SUMMARY

OF MAY 24, 2021, PRE-APPLICATION MEETING WITH EXELON GENERATION COMPANY, LLC ON PLANNED SUBMITTAL OF LICENSE AMENDMENT REQUEST FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2, CONCERNING SPENT FUEL POOL COOLING DESIGN BASIS CHANGE (L-2021-LRM-0051)

On May 24, 2021, an observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Exelon Generation Company, LLC (Exelon, the licensee). The purpose of this meeting was for Exelon to provide an overview of its planned license amendment request (LAR) for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Calvert Cliffs), to change the design basis for spent fuel pool (SFP) cooling with a full reactor core offload. The meeting notice and agenda, dated May 13, 2021, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML21144A024. The presentation material used by the licensee is available in ADAMS at Accession No. ML21144A017. A list of attendees is enclosed.

The Exelon representatives stated that in addition to requesting NRCs approval of the design basis change, it would be requesting approval of changes to the decay time section of the Calvert Cliffs Technical Requirements Manual. The proposed design basis change is to no longer require use of shutdown cooling system to support SFP cooling for heat removal when a full reactor core has been off loaded to the SFP. In its presentation, the licensee discussed that the proposed change would result in the SFP temperature rising above the current limit of 130 degrees Fahrenheit (oF) to a maximum of 150 oF.

The Exelon representatives described the regulatory requirements and guidance that they believe were applicable to the proposed change. The licensee identified variations from regulatory guidance that would be included in the proposed LAR and talked about the analyses that would be relied on to support the proposed change that would be described in the proposed LAR. The licensee stated the proposed LAR would have similarities to two previous amendment approvals for Turkey Point (ADAMS Accession No. ML0306207460) and Calvert Cliffs (ADAMS Accession No. ML003773029). The licensee stated that it plans to rely on the existing analysis and methods to demonstrate the proposed change meets applicable regulatory requirements.

The Exelon representatives stated that the licensee would submit the proposed LAR by June 15, 2021, and request that the NRC staff complete the review of the request within six months of the date of submittal.

The NRC staff informed the licensee that in addition to the information discussed during its presentation, the planned LAR needs to include the following:

  • In the proposed LAR, the licensee needs to address that under the possible loss of both trains of SFP cooling, the pool temperature will not exceed 150 oF and the time it will take to reach 150 oF and the time to reaching boiling point temperature. The time to reach boiling temperature is important because it indicates how much time the licensee to put in place alternate cooling methods.
  • In the proposed LAR, the licensee needs to address the maximum or worst-case heat load in the fuel pool and using the maximum service water temperature or maximum ultimate heat sink temperature.
  • In the proposed LAR, the licensee needs to identify all the make-up water sources and identify which ones are safety-related.
  • In the proposed LAR, the licensee needs to address the impact of the higher temperature on the SFP structure.
  • In the proposed LAR, the licensee needs to state the decay heat standard along with the margin used in the fuel pool cooling analysis.

The NRC staff informed the licensee that it would be helpful if the LAR included the following:

  • In the proposed LAR, it would be helpful if the licensee identified the principal design criteria for Calvert Cliffs in addition to the general design criteria (GDC) in the proposed LAR.

During the meeting Exelon identified the GDC that the proposed change would be consistent, however Calvert Cliffs 1 and 2 are non-GDC plants.

Members of the public were in attendance. NRC staff did receive questions from members of the public. The NRC staff were asked the following two questions 1:

  • Is the main change a change to the time of decay heat?
  • If the licensee increases the limit for the spent fuel temperature to 150 oF and the structure of the pool was qualified for 150 oF, would the proposed change zero out the margin for the SFP?

In response to the first question, the NRC staff stated that the SFP should be kept below 150 oF and no boiling should occur in the pool. The NRC staff did not provide a response to the second question during the meeting.

1 The questions are not verbatim as stated by the person asking the question.

No Public Meeting Feedback forms were received. No regulatory decisions were made during the public meeting. Please direct any inquiries to me at (301) 415-2871 or Michael.Marshall@nrc.gov.

Sincerely,

/RA/

Michael L. Marshall, Jr., Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES May 24, 2021, PRE-APPLICATION MEETING WITH EXELON GENERATION COMPANY, LLC ON PLANNED SUBMITTAL OF LICENSING ACTIONS FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2, CONCERNING SPENT FUEL POOL COOLING DESIGN BASIS CHANGE Name Organization John Ma U.S. Nuclear Regulatory Commission (NRC)

Michael Marshall NRC Sean Meighan NRC Sarah Obadina NRC John Parillo NRC Ahsan Sallman NRC Neil Sheehan NRC Hanry Wagage NRC Kurt Bodine Exelon Generation Company, LLC (Exelon)

Cecilie Broussard Exelon Ken Greene Exelon David Helker Exelon Christopher Jackson Exelon Christopher Junge Exelon Francis Mascitelli Exelon John Massari Exelon Larry Smith Exelon Chukai Yin Exelon Janna Jackson ---

Edwin Lyman ---

Shawn Seaman ---

Enclosure

ML21133A291 (Meeting Notice);

ML21161A108 (Summary);

ML21144A017 (Handouts)

OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LAiT NRR/DORL/LPL1/BC NAME MMarshall KEntz JDanna DATE 06/10/2021 06/10/2021 06/24/2021 OFFICE NRR/DORL/LPL1/PM NAME MMarshall DATE 06/25/2021