Forwards Requested Changes to Final Draft Tech Specs, Including Rev 2 to Procedure Toprp, Turbine Overspeed Protection... & Proprietary RCS Flow Measurement Uncertainty.Measurements Withheld (Ref 10CFR2.790)
ML20088A269
Person / Time
Site: Wolf Creek, Callaway, 05000000
Issue date: 04/06/1984
From: Petrick N
STANDARDIZED NUCLEAR UNIT POWER PLANT SYSTEM
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML19268E760 List:
References
SLNRC-84-0059, SLNRC-84-59, NUDOCS 8404110299
Download: ML20088A269 (2)


Text

r i

1 - . o, a.

SNUPPS Stensierdeaed Nuclear Unit Power Mont Systoni 5 sic csierry **d Nicholas A.Petrick Executive Director (301) 80H310 April 6, 1984 SLNRC 84-0059 FILE: 0543 SUBJ: SNUPPS Technical Specifications Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Docket Nos. STN 50-482 and STN 50-483 Ref: SLNRC 84-046, 3/20/84, Same Subject

Dear Mr. Denton:

The purpose of this letter is to forward requested changes to the final draft version of the SNUPPS Technical Specifications. These changes are to be considered in addition to those forwarded in the referenced letter.

The following documentation has been enclosed with this letter:

Attachment 1 - Status of Technical Specification Open Issues Attachment 2 - Proposed Technical Specification Changes and Justifications Attachment 3 - Background Information on the Change Requested to Specifi-cation 3.2.3 (RCS Flowrate and Nuclear Enthalpy Rise Hot i Channel. Factor)

Attachment 4 - Callaway's Turbine Overspeed Protection Reliability Program Please note that the information provided in Attachment 3 is proprietary to Westinghouse. As this submittal contains information proprietary to Westinghouse Electric Corporation, it is supported by an affidavit signed by Westinghouse, the owners of the information. The affidavit sets forth the basis on which the information may be withheld from public disclosure by the Commission and addresses with specificity the considerations listed in paragraph (b) (4) of Section 2.790 of the Commission's regula-tions.

Accordingly, it is respectfully requested that the information which is proprietary to Westinghouse be -withheld from public disclosure in accord-ance with 10CFR Section 2.790 of the Commission's regulations. Co rre-spondence with respect to either the proprietary aspects of this application

.for withholding or the supporting Westinghouse affidavit should reference CAW-84-28 and should be addressed to R. A. Weisemann, Manager, Regulatory and Legislative Affairs, Westinghouse Electric Corporation, P. O. Box 355, Pittsburgh, Pennsylvania 15230. pg

{ b p DSS &

g 8 8404110299 840406 l

" ^"" ""va hN (g J&1

- SLNRC 84-0059 :

Page Two Attachne' n t 4 is provided 'to formally submit a complete copy of Callaway's Turbine Overspeed Protection Reliability Program since pages 1 through 8 of Callaway's program were inadvertently omitted from the referenced letter.

Very(truly yours, Ar4 NC Nicholas A.'Petrick~

'JHR/dtk'/2al Attachment

~

h cc: J. Neisler/B. Little, USNRC/ CAL

- W. Schum/A. Smith, USNRC/WC J. Konklin, USNRC Region III

'- G..L. Koester, KGE D. T. McPhee, KCPL

.D. F. Schnell, UE

~

f ,

- +

Rm *L -