NLS8400254, Forwards Schedule for Submittal of Addl Safety Parameter Display Sys Info,Per 840803 Request

From kanterella
Jump to navigation Jump to search

Forwards Schedule for Submittal of Addl Safety Parameter Display Sys Info,Per 840803 Request
ML20093E360
Person / Time
Site: Cooper Entergy icon.png
Issue date: 10/05/1984
From: Pilant J
NEBRASKA PUBLIC POWER DISTRICT
To: Vassallo D
Office of Nuclear Reactor Regulation
References
NLS8400254, TAC-51232, NUDOCS 8410120072
Download: ML20093E360 (2)


Text

o .

Nebraska Public Power District " ""d$kS ffbS0""*"

NLS8400254 October 5,1984 Office of Nuclear Reactor Regulation Operating Reactors Branch No. 2 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Mr. Domenic B. Vassallo, Chief

Reference:

1) Letter from D. B. Vassallo to J. M. Pilant dated August 3,1984, " Safety Parameter Display System (SPDS) - Preimplementation Audit"

Dear Mr. Vassallo:

Subject:

Schedule for Submittal of Additional SPDS Information Cooper Nudear Station NRC Docket No. 50-298, DPR-46 This letter is in response to Reference 1 and transmits the requested subject schedule for submittal of additional SPDS information (attached).

Should you have any questions or require additional information, please contact me.

Sincerely, LM Ja M. Pflant Technical Staff Manager Nuclear Power Group JMP/Irb:emz8/2 Attachment Q0 t I

(

8410120072 841005 PDR ADOCK 05000298PDR p

Nebraska Public Power District Schedule for Submittal of Additional SPDS Information n

Item Scheduled Submittal

1. . Finalized list of SPDS parameters as well as a February 28,~ 1985 discussion of the rationale for any deletions and/

or additions to the parameter set proposed in Table.7-1 of the SPDS Safety Analysis.

2.. Commitment to provide a highly reliabic power February 28, 1985 supply system for the SPDS and a description of

-the power supply system in terms of its impact on total SPDS reliability (flow charts or diagrams may be helpful).

3. Summary of the reliability report being prepared February 28, 1985 by SAIC; this summary should describe both methodology and results.
4. Certification report being prepared by CPI that February 28, 1985 discusses the acceptance criteria, testing procedures used to certify proper isolation, and

.the results of that testing.

5. Large format color photographs or reproductions February 28, 1985 and all PMIS display pages that are defined as SPDS displays and all unique display / control hardware interfaces.
6. A written description for SPDF displays that are February 28, 1985 not'self-evident.
7. The results of the "1.000-hot.r test" af ter- SPDS November 15, 1985 implementation for confirmatary review.
8. Documentation providing evidt.nce that the November. 15, 1985 information displayed on the Cooper SPDS is-readily perceived and does not mislead the operator (s) (e.g. , results of man-in-the-loop

' testing, data from BWROG prototype experiments, operational experience with similar systems such as the SAIC design at Fermi, etc.).

9. Validation test plans and results. November 15, 1985
10. . Summary of verification and validation November 15, 1985 discrepancies and resolutions addressed in the following four reports:

.a. Requirements Verification Report

b. Software Design Verification Report
c. Validation Report
d. Field Installation Verification Report