MONTHYEARML20217N1931999-10-22022 October 1999 Forwards Insp Rept 50-298/99-12 on 990927-30.No Violations Noted.Insp Exam of Activities Under License as They Relate to Emergency Preparedness & to Compliance with Commission Rules & Regulations & with Conditions of License ML20217G8771999-10-14014 October 1999 Forwards Insp Rept 50-298/99-10 on 990920-24.No Violations Noted ML20217G7401999-10-14014 October 1999 Forwards MOR for Sept 1999 for Cooper Nuclear Station. Rept Includes Documentation of Challenges to Safety/Relief Valves,Iaw TS 5.6.4 ML20217C2671999-10-0808 October 1999 Forwards Insp Rept 50-298/99-03 on 990823-27 & 0907-10.No Violations Noted.Purpose of Insp to Ensure That Licensee Had Effective Programs for Identifying,Evaluating & Correcting Problems Which Could Impact Safe Plant Operations ML20212K9661999-09-30030 September 1999 Forwards Safety Evaluation Accepting plant-specific Safety Evaluation Rept for USI A-46 Program Implementation at Cooper Nuclear Station ML20216J1081999-09-28028 September 1999 Ltr Contract:Task Order 048, Cooper Safety Sys Design & Performance Capability Insp, Under Contract NRC-03-98-021 ML20212J5061999-09-27027 September 1999 Forwards Insp Rept 50-298/99-07 on 990718-0828.No Violations Noted.Inspectors Focused on Implementation of Licensee Reactor Safety & Emergency Preparedness Programs ML20212F3641999-09-22022 September 1999 Forwards Insp Rept 50-298/99-09 on 990823-26.No Violations Noted ML20216J8061999-09-20020 September 1999 Forwards Rev 37 to Safeguards Plan,Iaw Provisions of 10CFR50.(p).Rev Withheld,Per 10CFR73.21 ML20212C4921999-09-15015 September 1999 Forwards Monthly Operating Rept for Aug 1999 for Cooper Nuclear Station.Rept Includes Operating Data Rept,Unit SD Rept & Documentation of Challenges to Safety/Relief Valves ML20212A6061999-09-14014 September 1999 Forwards Insp Rept 50-298/99-08 on 9900816-20.No Violations Noted.Insp Focused on Implementation & Effective Performance of Access Authorization/Fitness-for-Duty (Behavior Observation) Program & Access Control of Personnel ML20211N5271999-09-0202 September 1999 Responds to NRC 990823 RAI Re Y2K Readiness at Cooper Nuclear Station,Per GL 98-01,Suppl 1 05000298/LER-1999-006, Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl1999-08-26026 August 1999 Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl ML20211F1311999-08-24024 August 1999 Forwards Rev 1 to Calculation Nedc 97-044, NPSH Margins for RHR & CS Pumps, in Support of 990615 Proposed Amend to DPR-46 Re Containment Overpressure Contribution to ECCS Pumps NPSH Requirements 05000298/LER-1999-003, Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support Personnel1999-08-23023 August 1999 Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support Personnel ML20211F4661999-08-23023 August 1999 Discusses GL 98-01 Issued by NRC on 980511 & NPPD Responses for Cooper Nuclear Station & 990628 & Results of Visit to Plant on 990811-12.Staff Determined That Integrated Contigency Plan Incomplete & CNS Not Y2K Ready ML20210R0301999-08-12012 August 1999 Forwards Monthly Operating Rept for July 1999 for Cooper Nuclear Station,Iaw Guidance Provided by GL 97-02.Rept Also Includes Documentation of Challenges to Srvs,Per TS 5.6.4 ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210P6761999-08-10010 August 1999 Requests That Following Changes Be Made to Distribution on NRC Correspondence ML20210P6861999-08-0909 August 1999 Forwards Insp Rept 50-298/99-06 on 990530-0717.No Violations Noted.During Insp,Inspectors Identified Two Issues Categorized as Being Low Risk Significance & within Licensee Response Band ML20210N1331999-08-0606 August 1999 Forwards Notice of Withdrawal of Application for Amend to FOL DPR-46.By Ltr Licensee Withdrew Amend Request Which Would Have Revised Usfar to Reflect as-built Configuration of Reactor Bldg Isolation Dampers ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210K6071999-08-0202 August 1999 Submits Withdrawal of Proposed License Amend Re Secondary Containment Isolation Description & Refueling Accident Analysis Results ML20210K3811999-08-0202 August 1999 Forwards Listed Info,Which NPPD Believes Demonstrates Ability to Obtain Funds in Amount of $10 Million for Payment of Such Premiums within Specified Three Month Period,Iaw 10CFR140.21 ML20210G5101999-07-28028 July 1999 Forwards fitness-for-duty Program semi-annual Performance Rept for Period of 990101-0630,per Provisions of 10CFR26.71(d) ML20210D2541999-07-21021 July 1999 Forwards Insp Rept 50-298/99-02 on 990628-0702.Purpose of Insp Was Primarily to Evaluate Effectiveness of Licensed Operator Requalification Program.No Violations Were Identified ML20210C2041999-07-20020 July 1999 Discusses 990715 Mgt Meeting with Midamerican Energy Co Re risk-informed Baseline Insp Program Recently Implemented at Cooper & Fort Calhoun Stations ML20209H8191999-07-15015 July 1999 Forwards Safety Evaluation on GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20209E6951999-07-12012 July 1999 Discusses Response to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Recommends Review of New Database Diskettes on Listed Website.Comments Due by 990901 or Data Entered Into Rvid for Plant Will Be Acceptable ML20209D8731999-07-0808 July 1999 Refers to 990707 Meeting Re Licensee Recent Maintenance Program self-assessment.Also Discussed How Licensee Incorporated Assessment Findings Into Rev of Maintenance Performance Improvement Plan.List of Attendees Encl ML20209B7851999-07-0101 July 1999 Forwards Corrected Occupational Radiation Exposure Repts, for Cys 1996 & 1997.Util Stated That Repts Did Not Properly Tabulate Number of Personnel Receiving Exposures Less than 100 Mrem by Work & Job Functions in CY96 & CY97 05000298/LER-1999-005, Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl1999-07-0101 July 1999 Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl ML20196J2471999-06-29029 June 1999 Discusses Completion of Licensing Action for GL 97-04, Assurance of Sufficient Net Positive Suction Head for ECC & Containment Heat Removal Pumps, 05000298/LER-1999-004, Forwards LER 99-004-01.Commitments Made by Util Are Encl1999-06-28028 June 1999 Forwards LER 99-004-01.Commitments Made by Util Are Encl ML20209B5451999-06-28028 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Disclosure Encl ML20196H0331999-06-24024 June 1999 Informs NRC of Deletion of 1991 Commitment Contained in Ltr Re Feedwater Nozzle Bypass Leakage Monitoring at Plant ML20196F7511999-06-24024 June 1999 Discusses 990622 Meeting with Public at Arbor Manor, Alburn,Ne to Provide Overview of Pilot Insp Program ML20209A7221999-06-23023 June 1999 Submits Revised Pages to Proposed Change to Plant TS Previously Submitted in ,Per 990615 Telcon with NRC ML20196F5331999-06-22022 June 1999 Forwards Examination Summary Rept for FW Nozzle Examinations Performed During 1998 Fall Refueling Outage at Cooper Nuclear Station.Rept Covers Past Examinations Up to & Including 1998 Fall Refueling Outage ML20196B4681999-06-17017 June 1999 Forwards TS Bases Changes Made at Plant Subsequent to Receipt of License Amend 178,dtd 980731,for Conversion to Its,Through 990610.List of Effective Pages for TS Bases, Encl ML20196E1411999-06-16016 June 1999 Forwards Insp Rept 50-298/99-05 on 990502-29.Noncited Violations Identified ML20195H8891999-06-14014 June 1999 Forwards Response to NRC 990315 RAI Re GL 95-07, Pressure Locking & Thermal-Binding of SR Power-Operated Gate Valves, 180-day Response Submitted by District on 960213 ML20195F6171999-06-0909 June 1999 Informs That GE Rept, Matl Presented by GE 970709 Meeting at Cooper Nuclear Power Station Re Replacement of ECCS Pump Suction Strainers Between Nppd,Ge & NRC Staff, Will Be Withheld from Public Disclosure as Requested ML20207G3031999-06-0808 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure EPIP 5.7.1, Emergency Classification,Rev 24,under 10CFR50,App E,Section V Provisions.No Violations Identified ML20195E2351999-06-0808 June 1999 Forwards Response to NRC 990517 RAI Re Util Proposed Change to TS Re Calibr Frequency of Reactor Recirculation Flow Transmitters Associated with APRM ML20207G4481999-06-0808 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure,Epip 5.7.1, Emergency Classification,Rev 23 C2,under Provisions of 10CFR50,App E,Section V ML20207G3001999-06-0707 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station Ep,Rev 33,under Provisions of 10CFR50,App E,Section V.No NRC Approval Required Based on Determination That EP Effectiveness Not Affected by Changes ML20207G4531999-06-0707 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure EPIP 5.7.1, Emergency Classification,Revision 25,under Provisions of 10CFR50,App E,Section V ML20207D3811999-05-27027 May 1999 Informs That During Next 6 to 12 Months,Starting 990530,NRC Plans to Conduct Insps Shown in Attached Insp Plan.Insps Include Both Planned Baseline & Supplemental Insps (Formerly Core & Regional Initiative Insps) ML20207A5191999-05-19019 May 1999 Forwards Insp Rept 50-298/99-04 on 990321-0501.Four Violations Identified & Being Treated as non-cited Violations 1999-09-30
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217G7401999-10-14014 October 1999 Forwards MOR for Sept 1999 for Cooper Nuclear Station. Rept Includes Documentation of Challenges to Safety/Relief Valves,Iaw TS 5.6.4 ML20216J8061999-09-20020 September 1999 Forwards Rev 37 to Safeguards Plan,Iaw Provisions of 10CFR50.(p).Rev Withheld,Per 10CFR73.21 ML20212C4921999-09-15015 September 1999 Forwards Monthly Operating Rept for Aug 1999 for Cooper Nuclear Station.Rept Includes Operating Data Rept,Unit SD Rept & Documentation of Challenges to Safety/Relief Valves ML20211N5271999-09-0202 September 1999 Responds to NRC 990823 RAI Re Y2K Readiness at Cooper Nuclear Station,Per GL 98-01,Suppl 1 05000298/LER-1999-006, Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl1999-08-26026 August 1999 Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl ML20211F1311999-08-24024 August 1999 Forwards Rev 1 to Calculation Nedc 97-044, NPSH Margins for RHR & CS Pumps, in Support of 990615 Proposed Amend to DPR-46 Re Containment Overpressure Contribution to ECCS Pumps NPSH Requirements 05000298/LER-1999-003, Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support Personnel1999-08-23023 August 1999 Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support Personnel ML20210R0301999-08-12012 August 1999 Forwards Monthly Operating Rept for July 1999 for Cooper Nuclear Station,Iaw Guidance Provided by GL 97-02.Rept Also Includes Documentation of Challenges to Srvs,Per TS 5.6.4 ML20210P6761999-08-10010 August 1999 Requests That Following Changes Be Made to Distribution on NRC Correspondence ML20210K6071999-08-0202 August 1999 Submits Withdrawal of Proposed License Amend Re Secondary Containment Isolation Description & Refueling Accident Analysis Results ML20210K3811999-08-0202 August 1999 Forwards Listed Info,Which NPPD Believes Demonstrates Ability to Obtain Funds in Amount of $10 Million for Payment of Such Premiums within Specified Three Month Period,Iaw 10CFR140.21 ML20210G5101999-07-28028 July 1999 Forwards fitness-for-duty Program semi-annual Performance Rept for Period of 990101-0630,per Provisions of 10CFR26.71(d) 05000298/LER-1999-005, Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl1999-07-0101 July 1999 Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl ML20209B7851999-07-0101 July 1999 Forwards Corrected Occupational Radiation Exposure Repts, for Cys 1996 & 1997.Util Stated That Repts Did Not Properly Tabulate Number of Personnel Receiving Exposures Less than 100 Mrem by Work & Job Functions in CY96 & CY97 05000298/LER-1999-004, Forwards LER 99-004-01.Commitments Made by Util Are Encl1999-06-28028 June 1999 Forwards LER 99-004-01.Commitments Made by Util Are Encl ML20209B5451999-06-28028 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Disclosure Encl ML20196H0331999-06-24024 June 1999 Informs NRC of Deletion of 1991 Commitment Contained in Ltr Re Feedwater Nozzle Bypass Leakage Monitoring at Plant ML20209A7221999-06-23023 June 1999 Submits Revised Pages to Proposed Change to Plant TS Previously Submitted in ,Per 990615 Telcon with NRC ML20196F5331999-06-22022 June 1999 Forwards Examination Summary Rept for FW Nozzle Examinations Performed During 1998 Fall Refueling Outage at Cooper Nuclear Station.Rept Covers Past Examinations Up to & Including 1998 Fall Refueling Outage ML20196B4681999-06-17017 June 1999 Forwards TS Bases Changes Made at Plant Subsequent to Receipt of License Amend 178,dtd 980731,for Conversion to Its,Through 990610.List of Effective Pages for TS Bases, Encl ML20195H8891999-06-14014 June 1999 Forwards Response to NRC 990315 RAI Re GL 95-07, Pressure Locking & Thermal-Binding of SR Power-Operated Gate Valves, 180-day Response Submitted by District on 960213 ML20195E2351999-06-0808 June 1999 Forwards Response to NRC 990517 RAI Re Util Proposed Change to TS Re Calibr Frequency of Reactor Recirculation Flow Transmitters Associated with APRM ML20207A0701999-05-19019 May 1999 Forwards Rev 3 to CNS Strategy for Achieving Engineering Excellence, Which Provides Effective Tool for Overall Engineering Work Mgt.Commitments Made by Util,Encl ML20206R7601999-05-17017 May 1999 Forwards Annual Radiological Environ Rept,Radiological Environ Monitoring Program,Jan-Dec 1998,per TS 5.6.2 ML20206P9681999-05-13013 May 1999 Forwards Monthly Operating Rept for Apr 1999 for Cooper Nuclear Station.Rept Includes Documentation of Challenges to Safety/Relief Valves ML20206J0741999-05-0404 May 1999 Forwards Rev 14 to CNS QA Program for Operation, Per 10CFR50.54(p) & 10CFR50.71.None of Changes Represent Reduction of Commitments.Summary of Changes,Encl ML20206J2331999-05-0303 May 1999 Forwards CNS Annual Radioactive Effluent Release Rept for 1998 & Offsite Dose Assessment Manual ML20206F2021999-04-30030 April 1999 Informs That NPPD Now Anticipates LAR Committed in Will Be Submitted by 990615.Operability Evaluations Presently in Effect Ensure That ECCS Pumps Are Operable But Nonconforming & Are Capable of Fulfilling Safety Functions ML20206E5461999-04-29029 April 1999 Forwards Cooper Nuclear Station Occupational Radiation Exposure Rept for 1998. Numbers Reported Reflected Tabulation of All Personnel on Site by Work & Job Function. Repts Will Be Corrected & Resubmitted by 990701 ML20205K1151999-04-0101 April 1999 Submits Extension of Commitment Date for Rev to Plant Strategy for Achieving Engineering Excellence from 990331 to 990519.Licensee Requires Addl Time to Finalize & Approve Rev 3 to Plant Strategy for Achieving Engineering Excellence ML20205E4331999-03-31031 March 1999 Forwards First Biennial Rept of Financial Assurance for Decommissioning for Cns,Per 10CFR50.75(f)(1) ML20205A0561999-03-23023 March 1999 Provides Info Detailing Property Insurance Coverage Maintained by NPPD & Midamerican Energy Co for Cns,In Compliance with 10CFR50.54(w)(3) 05000298/LER-1999-001, Forwards LER 99-001-00,including List of NRC Commitments Made by Util1999-03-22022 March 1999 Forwards LER 99-001-00,including List of NRC Commitments Made by Util ML20204G8811999-03-22022 March 1999 Forwards CNS Inservice Insp Summary Rept,Fall 1998 Refueling Outage (RFO-18), IAW Provisions of 10CFR50.55a. Analytical Evaluation for RPV Shell Weld Indications & Augmented Exam Results of RPV Also Included ML20204J4841999-03-19019 March 1999 Requests NRC Review & Approval of CNS ISI Relief Request (RR) PR-04,rev 1.ISI RR PR-04,rev 0 Required CNS to Perform Visual Insp of RPV Head Flange Seal Leak Detection Line. Approval Is Required Because Test Methodology Was Changed 05000298/LER-1998-013, Forwards LER 98-013-01 Re Missed Surveillance of Secondary Containment Isolation Valve.List of NRC Commitments Encl1999-03-16016 March 1999 Forwards LER 98-013-01 Re Missed Surveillance of Secondary Containment Isolation Valve.List of NRC Commitments Encl ML20204C9641999-03-15015 March 1999 Forwards Monthly Operating Rept for Feb 1999 for Cooper Nuclear Station.Rept Includes Documentation of Challenges to Srvs,Per TS 5.6.4 ML20207J5811999-03-10010 March 1999 Forwards Rev 1 to Calculation Nedc 98-024, APRM - RBM Setpoint Calculation ML20207F9661999-03-0101 March 1999 Responds to NRC Re Violations Noted in Insp Rept 50-298/98-08.Corrective Actions:Circumstances Surrounding Four Examples Have Been Discussed with Individuals Involved & Counseled,Where Appropriate ML20203C6961999-02-0808 February 1999 Forwards fitness-for-duty Program semi-annual Performance Rept for Period of 980701-1231,per 10CFR26.71(d) ML20202H6721999-02-0202 February 1999 Informs of Changes in Schedule Affecting Four Commitments in ,By Greater than One Month & Notifies of Plans to Issue Rev 3 to Strategy for Achieving Engineering Excellence ML20202E2231999-01-28028 January 1999 Forwards Response to NRC 980603 RAI Re NRC Ongoing Review of IPEEE for Cooper Nuclear Station,Submitted 961030 ML20199K6721999-01-19019 January 1999 Requests Extension of Present Due Date to 980202,as Addl Time Is Required to Resolve Issues Raised on Corrective Actions During Senior Mgt Review of Insp Rept 50-298/98-15 05000298/LER-1998-011, Forwards LER 98-011-00,per 10CFR50.73(a)(2)(v).Commitments Made by Util,Encl1999-01-19019 January 1999 Forwards LER 98-011-00,per 10CFR50.73(a)(2)(v).Commitments Made by Util,Encl ML20199E6281999-01-14014 January 1999 Forwards Monthly Operating Rept for Dec 1998 for Cooper Nuclear Station.Rept Also Includes Documentation of Challenges to Safety/Relief Valves,Iaw TS 5.6.4 ML20206P4171998-12-31031 December 1998 Informs of Extended Completion Due Date of Third Commitment Re EOP Calculations,Per Licensee 980723 Response to Violations Noted in Insp Rept 50-298/98-02.Date Has Been Extended to 990228 ML20199D2251998-12-30030 December 1998 Forwards 1998 CNS Simulator Certification Rept,As Required by 10CFR55.45.Rept Describes Performance Tests Conducted from 1995-98,discusses Performance Test Discrepancies from 1995-98 & Provides Revised Test Plan for 1999-2002 ML20198K2491998-12-23023 December 1998 Discusses RAI Re Response to NRC GL 97-04, Assurance of Sufficient Net Positive Suction Head for ECC & Containment Heat Removal Pumps ML20205A4411998-12-17017 December 1998 Forwards Initial Exam Outline for RO Written Exam to Be Given Week of 990208.Preliminary Copies of License Applications for Candidates Encl ML20196C4011998-11-20020 November 1998 Forwards Rev 1 to Cooper Nuclear Station COLR Cycle 19. Licensee Discovered That COLR Submitted with Contained Incorrect Max Average Planar Linear Heat Generation Rate Curves Specified in Figures 1 to 4 1999-09-20
[Table view] |
Text
1 l
l N
Nebraska Public Power District Nebraska's Energy Leader NLS990045 May 4,1999 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 l
Subject:
Cooper Nuclear Station Quality Assurance Program NRC Docket No. 50-298, DPR-46 Gentlemen:
This letter transmits Revision 14 of the Cooper Nuclear Station Quality Assurance Program per 10CFR50.54(a) and 10CFR50.71.
Attachment "A"is a summary of the changes made and submitted herein. None of the changes represent a reduction of commitment in the CNS Quality Assurance Program.
Should you have any ques ons or comments concerning this revision, please contact me.
. H. Swaiies -
-P dent of i ear nergy
/nr
' 1:' 00 cc: Regional Administrator w/ attachments USNRC - Region IV Senior Project Manager w/ attachments USNRC - NRR Project Directorate IV-1 1 I
Senior Resident Inspector w/ attachments USNRC NPG Distribution (w/o attachments)
Cooper Nuclear Station Po. Box 98/ Brownville. NE 683210098 Tel*nhane.' (402) 825-3811/ Fax: (402) 825-s211 9905120108 990504 .- http//ww nppd com PDR ADOCK 05000299 P PDR
3 l
1 Attachment A l to NLS990045 i Page 1 of 7 l l Cooper Nuclear Station )
Quality Assurance Program For Operation l Policy Document Revision 14 l
I l This listing describes changes to the Policy Document since the last (revision 13) submittal to the I Nuclear Regulatory Commission. Inconsequential changes (e.g,.; page numbers, Table of l
Contents references, and typographical errors) have also been appropriately changed; however, those particular changes are not described in detail. Each Change Description is followed by a
" bolded" explanation or phrase depicting why that specific change is not considered a reduction in QA Program commitment.
l Section/ Change Description / Explanation Commitment Paragraph Reduction
! Page Assessment Cornorate Policy Changed title of Division Manager of Quality Assurance No Statement, to Senior Manager of Quality Assurance and Vice President-page vi Nuclear to Senior Vice President of Energy Supply l Organizational title changes.
1.5, Deleted definitions of" Assessment" and " Evaluation", and No page 1-8 thru l-10 added new term / definition for Conditions Adverse to Ouality Previous activities " assessment" and " evaluation" are now performed as a part of QA audits and surveillances. New I guidance is provided for issues referenced as " Conditions Adverse to Quality".
1.5, Changed Vice President-Nuclear to Senior Vice President No page 1-12,13 of Energy Supply, changed Site Manager to Vice President of Nuclear Energy, and changed Division Manager of Quality l Assurance to Senior Manager of Quality Assurance in l Section titled Nuclear Power Groun Management)
Organizational title changes.
1.5, Deleted " assessment / evaluation" and reworded final sentence No page 1-13 in section titled Nuclear Ouality Procedures (NQPs)
Previous activities " assessment" and " evaluation" are now performed as a part of QA audits and surveillances.
i
Attachment A to NLS990045 l Page 2 of 7 1.5, Changed Vice President-Nuclear to Senior Vice President No page 1-16 of Energy Supply in Section titled Review l Organizational title change.
j 1.5, Deleted section titled Significant Conditions Adverse to No page 1-16 Ouality Definition was more applicable to Conditions Adverse to Quality, therefore, SCAQ definition was deleted and used as the definition for CAQ.
1.5, Revised the definition of Surveillance No page 1-17 Definition was refined to more clearly describe this QA activity without deleting any overview commitment.
l 2.1, para 1, Changed Senior Vice President of Energy Supply to Vice No page 2-1 President of Nuclear Energy as the delegated NPPD Nuclear I Officer, changed Vice President-Nuclear to Senior Vice President of Energy Supply, removed the terms
" assessments, evaluations", replaced the wording " audits, surveillances, inspections, verifications" with "all QA overview functions" Organizational title changes; assessments and evaluations are i
now included with QA audits and surveillances; general wording l used to depict QA overview rather than specific terminology.
l 2.2,1., Added new paragraph detailing commitment to Regulatory No l l page 2-3 Guide 1.8, revision 2 Added commitment per NPPD correspondence NLS980129 from J.H. Swailes to the U.S. NRC, dated August 24,1998.
l 2.2, para 6, Changed Division Manager of Quality Assurance to Senior No page 2-4 Manager ofQuality Assurance Organizational title change.
2.5, para 2, Relocated from Technical Specifications-entire paragraph No page 2-13 Information not altered, only relocated.
2.5, para 3 Relocated from Technical Specifications-items
- Technical No page 2-14 Requirements Manual and *Offsite Dose Assessment Manual Information not altered, only relocated.
2.7, para 5, Changed Site Menager to Vice President of Nuclear Energy No page 2-17 Organizational title change.
Attachment A to NLS990045 l Page 3 of 7 2.10, para 2, Removed the term " Assessments / Evaluations" No page 2-19 Assessments / Evaluations now a part of QA audits /surveillances.
2.11, para 2, Removed the term " Assessments / Evaluations" No page 2-21 Assessments / Evaluations now a part of QA audits /surveillances.
i 2.13(c), Removed the term " Assessments / Evaluations" No page 2-24 Assessments / Evaluations now a part of QA audits /surveillances.
2.16, para 3 & 5, Changed Vice President-Nuclear to Vice President of No ;
page 2-27 Nuclear Energy and to Senior Vice President of Energy l
Supply, respectively Organizational title changes.
2.17, para 1, Relocated from Technical Specifications-the wording No page 2-28 "Section 6.0 of this standard" Information not altered, only relocated.
2.18, para 1, Changed Division Manager of Quality Assurance to No ,
page 2-29 Senior Manager of Quality Assurance Organizational title change.
2.18, para 2 Relocated from Technical Specifications-entire paragraph No and a.-g., Information not altered, only relocated.
page 2-29 & 2-30 2.19.1.(a)(6), Removed the term " Assessments / Evaluations" No page 2-32 Assessments / Evaluations now a part of QA audits /surveillances.
3.1, para 1, Removed the term " Assessments" No page 3-1 Assessments now a part of QA audits / sun eillances.
3.2, para 2 Changed Vice President-Nuclear to Senior Vice President No page 3-2 of Energy Supply, subsequently changed responsibility and authority for the Safety Review and Audit Board (SRAB) l from the Senior Vice President of Energy Supply to the Vice President of Nuclear Energy l Organizational title changes. Responsibility as NPPD's nuclear officer changed so that it would be assigned to the Vice President located at CNS. Similarly, the responsibility for the Safety Review and Audit Board (SRAB) was also then reassigned.
Attachment A to NLS990045 Page 4 of 7 3.2.1, Changed Vice President-Nuclear to Senior Vice President No page 3-2 of Energy Supply Organizational title change.
3.2.2, para 1 thru 5, Changed Vice President-Nuclear to Senior Vice President No page 3-2,-3 & -4 of Energy Supply and changed Division Manager of Quality Assurance to Senior Manager of Quality Assurance Organizational title changes.
I 3.2.3, para 1 & 8, Changed Division Manager of Quality Assurance to Senior No I page 3-4 & 3-5 Manager of Quality Assurance and changed Site Manager to Vice President of Nuclear Energy, respectively Organizational title changes.
3.2.3, para 11, Changed the wording "SORC qualified" to " designated" No page 3-6 A position paper was developed which provides explanation l and logic concerning the recognized need to make this change l while continuing to ensure that the appropriate degree of QA '
experience and knowledge is provided to SORC.
3.2.4, para 1 & 5, Changed Division Manager of Quality Assurance to Senior No page 3-6 and 3-7 Manager of Quality Assurance l Organizational title change.
3.2.4, para 2, Removed the term "/ Evaluation" No page 3-6 Evaluation is now part of QA audits /surveillances.
3.2.6, para 2 & 3, Removed the term "/ evaluations" and " assessments, No page 3-8 evaluations", respectively 3.2.6, Resolution Changed Division Manager of Quality Assurance to Senior No of Disagreements, Manager of Quality Assurance page 3-9 Organizational title change.
Attachramt A to NL5990045 Page 5 of 7 3.2.7 thru 3.2.13, Rearranged / renumbered sections to enhance readability. No page 3-9 thru 3-11 Combined Senior Manager of Site Support with Senior Manager of Safety Assessment into new section 3.2.10, titled Senior Manager of Safety Assessment / Site Support.
Combined Nuclear Fuels Supervisor with Senior Manager of Engineering into new section 3.2.11 (By combining those sections there are now 11 vs 13 sections in 3.2). In section 3.2.7, changed Site Manager to Vice President of Nuclear Energy and Vice President-Nuclear to Senior Vice President of Energy Supply, added Training and Nuclear Licensing and Safety as direct reports to the Vice President of Nuclear Energy.
Organizational title changes and assignment of functional responsibilities. No QA Program responsibilities have been deleted.
3.2.8 Added new section General Manager of Technical Services, No page 3-9 assigned Materials Services and all Engineering to this position responsibility.
Organizationai title change and assignment of functional responsibilities. No QA Program responsibilities have been deleted.
3.2.9, Added Performance Analysis and Scheduling to responsibility No page 3-10 for Plant Manager and removed responsibility for Station Engineering, which was added to the Senior Manager of Engineering in 3.2.11, changed Site Manager to Vice President of Nuclear Energy Organizational title change and assignment of functional responsibilities. No QA Program responsibilities have been deleted.
3.2.11, Changed reporting relationship of Senior Manager of No page 3-10 Engineering from Vice President of Nuclear Energy to General Manager of Technical Services Reassignment of functional responsibilities.
3.3, Changed Site Manager to Vice President of Nuclear Energy No page 3-11 Organizational title change.
Attachment A to NLS990045 Page 6 of 7 3.4, para 1 Relocated from Technical Specifications- Replaced existing No and 1. thru 6., responsibility wording with the wording from Tech Specs page 3-11 thru with the exception ofitem 1. which was retained from the 3-14 previous version of the Policy Document (page 3-13)
Information not altered, only relocated.
3.4.5., Changed Safety Review and Audit Board (SRAB) No page 3-13 reporting responsibility from the Senior Vice President of Energy Supply to the Vice President of Nuclear Energy Responsibility as NPPD's nuclear officer changed so that it would be assigned to the Vice President located at CNS.
Similarly, the responsibility for the Safety Review and Audit Board (SRAB) was also then reassigned.
3.5, para 2 Relocated from Technical Specifications- Replaced existing No and 1. thru 7., paragraph, which only references Tech Specs, with the actual page 3-14 thru wording from Tech Specs 3-18 Information not altered, only relocated.
3.5.1.b., Added words of commitment to Regulatory Guide 1.8, No page 3-15 revision 2 Added commitment per NPPD correspondence NLS980129 from J.H. Swailes to the U.S. NRC , dated August 24,1998.
4.1.2, Changed Division Manager of Quality Assurance to Senior No page 4-3 Manager of Quality Assurance and changed Vice President-Nuclear to Senior Vice President of Energy Supply Organizational title changes.
4.1.3, para 3, Changed Division Manager of Quality Assurance to Senior No page 4-4 Manager of Quality Assurance Organizational title changes.
4.1.3 a), para 3 & 4, Combined paragraphs 3 and 4 into new paragraph 3 No page 4-5 Reworded to more clearly depict QA overview.
4.1.3 b), para 1, Removed the term " evaluations" No page 4-5 Evaluations are now a part of QA audits /surveillances.
5.0, para 7, Changed Vice President-Nuclear to Senior Vice President No page 5-2 of Energy Supply and changed Division Manager of Quality Assurance to Senior Manager of Quality Assurance .
Organizational title changes. !
l w
Attachment A
( to NLS990045 Page 7 of 7
)
l
' l
\
j 6.0, Relocated from Technical Specifications- added, in their No page 6-1 thru entirety, new sections 6.1 and 6.2, as transferred from 6-5 Tech Specs Information not altered, only relocated.
6.2.g),2,i, Removed words which reference Section 3.5.4.a. This No page 6-4 referenced Tech Spec Section was removed by Tech Spec Amendment 102, but was inadvertenth got yet removed from the Policy Document Inclusion of previously approved change.
7.0, Relocated from Technical Specifications- added new No page 7-2 references 7.16 thru 7.18 and deleted the word Radiological from the title of reference 7.14 Information not altered, only relocated. ;
1 Figure 1, Changed Division Manager of Quality Assurance to Senior No page 8-1 Manager-Quality Assurance Organizational title change.
Table 2 c), Relocated from Technical Specifications- changed the wording No page 9-5 " Technical Specifications" to "Section 3.4 of this standard",
and removed the term " evaluations" l Information not altered, only relocated; inserted the correct l reference to location ofinformation; evaluations now a part of QA audits / sun'cillances.
l The following signatures represent those individuals who have personally reviewed the information contained in the attachment to correspondence NLS990045. Initials and date are provided on the top right-hand corner of the attachment indicating that each page has been reviewed.
Printed Name/ Title Initials Signature /Date M. D. Allen, QA Programs Supervisor l
i
I l
l ATTACHMENT 3 LIST OF NRC COMMITMENTS l 1
Correspondence No: NLS990045 The following table identifies those actions committed to by the District in this j 1
document. Any other actions discussed in the submittal represent intended or '
planned actions by the District. They are described to the NRC for the NRC's l information and are not regulatory commitments. Please notify the NL&S Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments, i
l COMMITTED DATE COMMITMENT OR OUTAGE None i
l l
l l
I l
l l PROCEDURE NUMBER 0.42 l REVISION NUMBER 6 l PAGE 9 OF 13 l t