NLS8600153, Forwards Results of '1,000 H Test' After SPDS Implementation for Confirmatory Review, Documentation That Info Displayed on SPDS Readily Perceived & Does Not Mislead Operators.Validation Test Plans & Results Also Encl

From kanterella
Jump to navigation Jump to search

Forwards Results of '1,000 H Test' After SPDS Implementation for Confirmatory Review, Documentation That Info Displayed on SPDS Readily Perceived & Does Not Mislead Operators.Validation Test Plans & Results Also Encl
ML20155G446
Person / Time
Site: Cooper Entergy icon.png
Issue date: 04/28/1986
From: Pilant J
NEBRASKA PUBLIC POWER DISTRICT
To: Muller D
Office of Nuclear Reactor Regulation
Shared Package
ML20155G449 List:
References
NLS8600153, TAC-51232, NUDOCS 8605060132
Download: ML20155G446 (2)


Text

- _ _ _ _ _ _ _ _ _ - _ ________ ___ ___ - ______ _ _____ - _ _ _ _ - _ _ ____________________ _ _ -

. y .. .

Nebraska Public Power District "

" "kh$hbbeO'** *"

S NLS8600153 April 28,1986 Office of Nuclear Reactor Regulation BWR Project Directorate No. 2 Division of BWR Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Mr. Daniel R. Muller

Dear Mr. Muller:

Subject:

Additional SPDS Information Cooper Nuclear Station NRC Docket No. 50-298, DPR-46

Reference:

1) Letter from J. M. Pilant to D. B. Vassallo

, dated November 15, 1985, " Safety Parameter l Display System - Cooper Nuclear Station.

I In accordance with Reference 1, the following additional SPDS f information is submitted:

Attachment Item 1 Results of the "1,000-hour Test" after SPDS implementation for confirmatory review.

2 Documentation that the information displayed on Cooper SPDS is readily perceived and does not mislead the operator (s) (Man-In-The-Loop Testing) .

3 Validation test plans and results.

It should be noted that the 1,000-hour Test was performed with the IE multiplexers supplied by a temporary power configuration. The results of this test remain applicable, however; as the final power supply to the IE multiplexers (divisional IE power) equals or exceeds the reliability of the temporary configuration.

Additional items of information, not presently available, will be submitted to complete the staff's review. These items will be submitted as they become available which is expected before June 15,1986. A list of these items is as follows: 0 t\

8605060132 860428 PDR ADOCK 05000298 P PDR

Mr. Dr.niel R. Muller Page 2 April 28,1986

1. - Summary of the reliability report being prepared by SAIC; describing methodology and results.
2. Summary of verification and validation discrepancies and resolutions addressed in various reports.

Should you have any questions or require additional information, please contact me.

Sincerely, W

M. Pilant Technical Staff Manager Nuclear Power Group JMP:mh28/1 (15)