Monthly Operating Repts for Jul 1983.W/830815 Ltr
ML20024F064
Person / Time
Site: Saint Lucie, Turkey Point, 05000000
Issue date: 08/15/1983
From: Grant N, Williams J, Williams J Jr
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
PNS-LI-83-551, NUDOCS 8309080172
Download: ML20024F064 (17)


Text

_

2 FLORIDA POWER & LIGHT COMPANY August 15, 1983 PflS-L1-83-551 Director, Office of Resource fianagement U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Sir:

Attached are the July,1983, Operating Status Reports and Operating Summary Reports for Turkey Point Units Nos. 3 and 4 and St. Lucie Units Nos. I and 2.

Very truly yours, I

J. W. Williams, Jr.

Vice President Nuclear Energy JWW/NWG/mpc Attachment cc: J. P. O'Reilly, Region II 50"L5[

8309080172 830815 l PDR ADOCK 05000250 R PDR PEOPLE. . SERVING *EOPLE

AVElt AGE DAILY UNIT POWER LEVEL I'

,D'OCKET NO. 50-250 UNIT Turkey Point Unit DA1E - 8/15/83 COMPLETED tty - N. W. Grant TELEPflONE "(305) 552-3675 i

MONTH July,1983 .

DAY AVERAGE DAILY POWER LEVEL~

' DAY AVER AGE DAILY POWER LEVEL IMWe Net) -(MWe-Net ) ,-

g _ 6,6_7_ _

g7 671 ,

670 665 2 18 .

669 ~

3 19 663 671 4 20 666 ..,

670 5 21 668 667 6 22 665 669 7 664 23 672

.c

' - 660 8 24 .

9 675 25 656 to 674 655 26

. 673 655

.gg 27 662 .

12 673 28 oog -

676 13 29 070 14 30 613

674 15 486 31 a 16 671 l

l INSTRUCTIONS On this formar. list the average daily unit power lesel in Mwe.yet for each day in the reporting month. Compute to the nearest whole megawait.

I .

(9/771

8 OPERATING DATA REPORT

"'mE @&-

COMPLETED IlY _N. W. Grant TELEPHONE (305) 552-3675 OPERATING STATUS

1. Unit Name: Turkey Point Unit 3 Notes Unit 3 operated at essentially full power
2. Reporting Period: .bl y , 14R'1 2200 except for a power reduction
3. Licensed Thermal Power (MWt): as discussed in the Unit
4. Nameplate Rating (Gross MWe): 760 693 Shutdown Report.
5. Design Electrical Rating (Net MWe):
6. Maximum Dependabic Capacity (Gross MWe): 700
7. Maximum Dependable Capacity (Net MWe): 666
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report.Give Reasons:
9. Power Level To Which Restricted,if Any (Nei MWe):
10. Reasons For Restrictions.If Any: __

This Month Yr to-Date Cnmulative

11. Hours In Reporting Period 744 5,087 93,392.6
12. Number Of Hours Reactor Was Critical 744.0 5,039.7 65,840
13. Reactor Reserve Shutdown Hours 0 '  ! 0 ' 844.4
14. Hours Generator On.Line 744.0 4,955.0 64,460.1
15. Unit Reserve Shutdown Hours 0 0 121.8
16. Gross Thermal Energy Ge'nerated (MWH) 1,627,091 10,866,725 .132,284,.637 '.
17. Gross Electrical Energy Generated (MWH) 516,160 _ 3,535,925 42,197,915
18. Net Electrical Energy Generated (MWH) '

491.484 3.370.028 39'.957.580 ,

19. Unit Service Factor 100.0 97.4 69.0 '
20. Unit Avalfability Factor 100.0 97.4 69 2
21. Unit Capacity Factor (Using MDC Net) -

99.2 101.5 66 2 '

22. Unit Capacity Factor (Using DER Net) 95.3 95.6 61.7.
23. Unit Forced Outage Rate 0 2.1 5.4'
24. Shutdowns Scheduled Over Next 6 Months (T3 pe.Date.and Duration of Each): '

Refueling, October,1983, 2 months

25. If Shut Down At End Of Report Period. Estimated Date of Startup:
26. Units in Test Status (Prior Io Commercial Operation): Forecast Achiesed INITIA L CRITICALITY INITIA L ELECTRICITY COMMERCI AL OPER ATION .

?

(9/77 )

h- .

s DOCKET NO. 50-250 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Turkey PoinU 3 DATE 8/15/03 COMPLETED BY N. W. Grant REPORT MONTH ilul y . 1491 (305) 552-3675 TELEPHONE

-. .5? Y Licensee ,E r, feo Cause & Corrective No. Date c- jg5 H

3s j Event p7 o3 Action to

$E E j di g Report = rE C fO Prevent Recurrence d

8 830730 F 0.0 A 5 HA HTEXCH Power was reduced for repairs to the turbine cooling water heat exchanger.

The unit then returned to full power.

i 2 3 4 F: Forced Reason: Method: Exhibit G. Instructions S. Scheduled A.Lyuipment Failure (Explain) 1-Manual for Preparation of Data

[1-Maintenance of Test 2 Manual Scram. Entry Sheets for Licensee C Refueling 3 Automatic Scram. Esent Report (LER) File (NUREG-D.Regularory Restriction 9-Other (Explain) 0161)

E-Operator Trainirig & License Examination

, F-Ad ministrative p ,

5 G Opeiational Error (Fsplain) s _ / o a a 4 4 eve.;,..ct Exhibit I . Same Source (9/77) Il-Ot her ( E xplain)

SUMMARY

OF OPERATING EXPERIENCE i DOCKET NO. 50-250 Ut{IT Turkey Point 3 DATE August 15, 1983 COMPLETED BY P. L. Pace TELEPIIONE (305) 552-3654 REPORT MONTII Jul v. 1983 Unit 3 operated at essentially full power for the entire month.

Major safety related maintenance activities included:

An area radiation monitor detector was replaced.

A leak on a charging system valve weld was repaired.

The B charging pump was overhauled and all valves replaced.

Inspections and requirements of IE Bulletins and NUREG-0737 are continuing.

Florida Power & Light Company comitments for NUREG-0737 implementation are continuing. Refer to correspondence between FPL and NRC for additional information.

f

e AVElt AGE DAILY UNIT POWER LEVEL E'

,D'OCKET NO. 50-251 gg,7 Turkey Point Unit

  1. 4 DA1E _ 8/15/83 l l

COMPLETED BY - N. W. Grant TELEPilONE (305)552-3675 i

)

MONm July, 1983 .

- I DAY AVER ACE DAILY POWER LEVEL DAY AVER AGE DAILY POWER LEVEL

  • ~

IMWe Net) -'MWe Net) 665 1 37 652 665 2 g3 . 655 3 667 .- 662*

4 20 666 ,

5 379 21 665 6

664 .,) 664 007 666 7

r 675 .. 653 3 24 677 '

9 658 33 677 .657 10 ,6

~

671 660 Il 27 3 ~, 674 667 28 677 13 29 667 667 667

, 14 39 653 668 15 3 652 16 4 e INSTRUCTIONS

- On this fonnat. list the aver.ege daily unit isower lesel in MWe-Net for each day in the reporting month. Compute to the nearest whofe megawatt.

(9/77) g- --

, - - , w- w vm-y . - ~ - - - -. - - - -- e,- -

w----.-r- ,, - - --

~

OPERATING DATA REPORT DOCKET NO. 50-251 DATE 8/15/83 COMPLETED IlY F. ' W. Grant TELEPHONE (.3nn 552-3675 OPERATING STATUS

1. Unit Name: Turkey Point 4 -

Notes Unit 4 operated at

2. Reporti~ng Period:

July, 1983 essentially full power 2200 except as noted in the

3. Licensed Thennal Power (MWt): Unit Shutdowns and Power.
4. Nameplate Rating (Gross MWe): 760 Reductions Report.
5. Design Electrical Rating (Net MWe): 693
6. Maximum Dependable Capacity (Gross MWe): 700
7. Mninwm Depcndable Capacity (Net MWe): 666
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since last Report, Give Reasons:
9. Power Level To Which Restricted,1f Any (Net MWe):
10. Reasons For Restrictions.If Any:

. This Month Yr. to-Date . Cumulative I14 Hours In Reporting Period 744 5,087 87,120

12. Number Of Hours Reactor Was Critical 740.0 1,847.3 61,702.6
13. Reactor Reserve Shutdown Hours ~0 0*' ' 166.6
14. Hours Generator On-Line 736.9 1,670.1 59,566.1
15. Unit Reserve Shutdown Hours 0 0 31.2
16. Gross Thennal Energy Ge'nerated (MWH) 1.610.351 3.495.131 125.413.375 -
17. Gross Electrical Energy Generated (MWH) 512 ._8 6.D _ _. 1.103'.380 39.878.892
18. Net Electrical Energy Generated (MWH) 488,067 1,042,038 37'767,211 99.0 32.8 68.4
19. Unit Service Factor
20. Unit Availability Factor 99.0 32.8 68.4 .
21. Unit Capacity Factor (Using MDC Net) -

98.5 31.4 67.1 m

22. Unit Capacity Factor (Using DER Net) 94.7 29.6 62.6
23. Unit Forced Outage Rate _ _.

1.0 7.6 4.0

24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Each): "
25. If Shut Down At End Of Report Pes:od. Estimated Date of Startup:
26. Units in Test Status (Prior to Commercial Operation): Forecast Achiesed INITIA L CRITICALITY INITIA L ELECTRICITY COMM ERCIAL OPERATION (9/77 l

~. .

i

=se UNIT SilUTDOWNS AND POWER REDUCTIONS ey Point #4 N ME DATE 0/ D/ D3 COMPLETED BY N. W. Grant REPORT MONDI July' 1983 TELEPHONE (305) 552-3675

- E c

, !E 3i; *Y5 Lisensee E t, o Cause & Correetive No. Date H

i 3g 2s& Event g?

mO

{"3 gO Action to yE E 5e g =j Report a ue Prevent Recurrence C

12 830705 F 7.1 A 1 250-83-10 SF ACCUMU Unit removed from service as re-quired by Technical Specifications due to low pressure in accumulator.

Unit thenreturned to service. .

~

I 2 3 4 f: Forced Reason: Method: Exhibit G-Instructions S. Scheduled A Equipment Failure (Explain) 1 -Manual for Preparation of Data B-Maintenance of Test 2-Manual Scram. Entry Sheets for Licensee C-Refueling 3-Automatic Scram. Event Report (LER) File (NUREG-D-Regulatory Restriction 9-Other ( E-plain ) 0161) li-Operator Training & License Examination

, F-Administrative p ,

5 G-Operational Error (E xplain) c /.o ao aseve.i..# Estubit I - Same Sourec (9/77) Il-Ot her (Explain)

SUMMARY

OF OPEIU1 TING EXPERIENCE i DOCKET NO. 50-251 UNIT Turkey Point 4 DATE ,Augus_t_15. 1983 COMPLETED BY P. L. Pace TELEPHONE (305) 552-3654 REPORT liONTH July, 1983 Unit 4 operated at power except as noted in the Unit Shutdowns Report.

Other maior safety related maintenance activities included:

A boric acid heat tracing circuit was reapired.

An accumulator nitrogen vent valve was replaced.

Inspections and requirements of IE Bulletins and flVREG-0737 are continuing.

Florida Power & Light Company Commitments for fluREG-0737 implementation are continuing. Refer to correspondence between FPL and flRC for additional information.

I

, . ~

~

t AVERAGE DAILY UNIT POWER LEVEL

- . s DOCKETNO. 50-335-

'. ugir St. Lucie Unit #1 I) ATE 8/15/83 COMPLETED liY ^Ib W. Grant ,

TELEPilONE' (305). 552-3675' -

I MONm July, 1983 .

DAY ,

AVER AGE DAILY POWER LEVEL DAY AVER AGE DAILY POWEk LEVEL (MWe Net) .(MWe Net) ,

I gj ..

y 3 19 4 . 20 '

6 22 y ...

,,, g s

24 9 ;25

~~

! 10 26

-~ '

.lg 37

~.

~~

12 28 _

13 29 4 34 30 -.

15 x 33 ,,

16 .

~

INSTRUCTIONS On this formai. list the average daily unit liower lesel in MWe Net.for each day in the reporting nninth'. Compute !o the nearest whole megawatt.

(9/77) '

h

.\

/

, , . , . - . . , - , , c_ _ . . _ _ . _- -. - , . . . -, ._ . - - , _ . . . . , r _ --

8 opt.RATlkG DATA REPORT -

DOCKET NO. 50-335

- DATE _.8/15/83 COMPLETED BY . fttant g7_552-3675

- s TELE!' HONE OPERATING STATUS

~ ~

N 5

~ Unit remained out of-St. _Lucie Unit 1

l. Unit Name:
2. Reporti'ng Period: July. 1983 service for refueling and 2700 scheduled maintenance. .
3. Licensed Thennal Power (MWt):
4. Nameplate Rating (Gross MWe): 890 . ~

. 5. Design Electrical Rating (Net MWe)': 830 .

6.' Mcximum Dependable Capacity (Gross MWe): 867

7. Maximum Dependable Capacity (Net MWe): 822
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

',9. Power Level To Which Restricted,if Any (Net MWe):

10; Reasons For R.estrictions. If Any: '

.This Month Yr..to Date Cmuulative i

y iIc flours In Reporting Period 744 5.087 57.935

_ ' :12. Number Of Hours Re' actor Was Critical 0 1,366.9 44,466.1

13. Reactor Reserve Shutdown Hours - '

0 -

0 -

205.3

14. Hours Generator On-Line 0 1,350 7 43,576.2
15. Unit Reserve Shutdown Hours D '

0 0 39.3 *

'5 16. Gross Thermal Energy Genented (MWil) 0 3,352,422 .108,667,938 .

17, Gross Electrical Energy Generated (MWH) 0 1,1603 280 _ 35,373,875

18. Net EIcetrical Energy Generated (MWH)

-3,204 _, 1,086,469 _ , 33,350,660-

  1. D*2 '

U :ZD D l 19. Unit Senice Factor L 20. Unit Availability Factor 0 26.6 75.3 q 21. Unit Capacity Factor (Using MDC Net) -

0 26.1 73.2 *

~

~

x 22. Unit Capacity Factor ('Using DER Net) 0 25.7 71.2

23. Unit Forced Outa'ge Rate 0 1.1 4.6'
24. Shutdowns Scheduled Oser Next 6 Months (T3 pe. Date.and Duration of Each): '

-~

l 25. If Shst Down At End Of R'eport Period.Estirnated Date of Startup: October,1983 -~

, 2tu Units in Test Status (Prior to Cornmercial Operation): Forecast Achiesed ,

A a.

^ .

~

^

f INITIA L CRITICA LITY

.m

'lNITIA L ELECTRICITY . *

- COMM ERCIA L OPERATION

-}. '

(9/77I s . . ,

. , , . , . ,. - _ . _ - . - - . - ,. . ~ . - , -_. ,

~"

UNIT SHUTDOWNS AND POWER REDUCTIONS . DOCKET NO. 50-335

  1. UNIT NAME St. Lucie #1 DATE R/15/83 COMPLETED BY N W rsrant REPORT MONTil Julv. 1983 TELEPilONE (305) 552-3675

~'

l "*

4 ri 3 =o r .

Licensee -

5*

, s 7 .s X c v. c o Cause & Corrective No. Date g, }l @ ,g g 5 Event 57 83 Action to uhU

'I 4

,. i E 55j e  ;

Report a /f '

////g)/i/?

19. Unit Service Factor 48.5
20. Unit Availability Factor 48.5 .
21. Unit Capacity Factor (Using MDC Net) - NA _
22. Unit Capacity Factor (Using DER Net) NA
23. Unit Forced Outage Rate 9.5
24. Shutdowns Scheduled Over Next 6 Months (T3 pe Date.and Duration of Each): '
25. If Shut Down At End Of Report Period.Estircated Date of Startup:
26. Units In Test Status (Prior to Commercial Operation): Forecast Achiesed INITIA L CRITICALITY 5/27/83 o _6/2/83 INITIA L ELECTRICITY 6/83 6/13/83 COMM ERCI AL OPER ATION Late July, 1983- 8/8/83

. (9/77 )

. 1 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKETNO. 50-389 UNIT NAME St. Lucie 112 DATE 8/15/83 REPORT MONTH Jul y, 1983 COMPLETED BY N. W. Grant TELEPHONE (305) 552-3675 n.

No. Date i

.$j 3g

}; [h 2 ;; a:

Licensee Event h

uy 4

c. ?

Cause & Corrective Action to H 5 Report # rE U 0

$ j di Prevent Recurrence C

12 830622 S 298.9 B 4 HC llTEXCH Unit removed from service to clean condensate pump strainers. Outage extended to repair reactor coolant pump seal injection'. .

13 830725 S 28.0 B 3 XX XXXXXX Conducted unit trip for power ascension testing. Unit remained off line for other testin'g and maintenance.

14 830726 F 3.7 A 3 HA TURBIN Unit tripped on high steam generator level. Unit returned to service.

15 830726 F 34.1 A 3 EG INSTRU Unit trip due to loss of a power panel. Outage extended for repair of condenser tube.

16 830728 S 18.3 B 2 XX XXXXXX Unit tripped for power ascension test.

I 2 3 4 F: Forced Reason: Method: Exhibit G . Instructions S: Scheduled A Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance vi Test 2-Manua scram. Entry Sheets for Licensee C. Refueling 3-Automatic Scram. Event Report (LER) File (NUREG-D-Regulatory Restriction QOther (Explain) 0161) 1:-Operator Training & License Examination F Administratise

, 5 G-Operational Er ror (Fsplain) s _ / o ,,o n o w .w .cl Exhibit I . Same Source (9/77) Il-Ot her ( E xplain )

P

SUMMARY

OF OPERATING EXPERIENCE i DOCKET NO. .

50-389 _

UNIT St. Lucie Unite 2 DATE August 15, 1983 COMPLETED BY P. L. Pace TELEPHONE (305) 552-3654 REPORT MONTH Julv 1983 Unit 2 conducted power ascension testing during the month.

See the Unit Shutdowns and Power Reductions report for details on unit outages.

Inspections and requirements of IE Bulletins and NUREG-0737 are continuing.

Florida Power & Light Company commitments for NUREG-0737 implementation are continuing. Refer to correspondence between FPL and NRC for additional information.

In accordance with requirements of NUREG-0737 Item II.K.3.3., there were no challenges to PORV or safety valves during the report month.

. . _ _