Notice of Violation from Insp on 801215-18 & 810105-08
ML19350C045
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/10/1981
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19350C022 List:
References
50-287-80-30, NUDOCS 8103240776
Download: ML19350C045 (1)


Text

.

4 O

APPENDIX A NOTICE OF VIOLATION Duke Power Company Docket No. 50-287 Oc'onee Nuclear Station Unit 3 License No. DPR-55 As a result of the inspection conducted on December 15-18, 1980 and January 5-8, 1981, and in accordance with the Interim Enforcement Policy, 45 FR 66754 (October 7, 1980), the following violation was identified.

10 CFR 50, Appendix B, Criterion V as implemented by Topical Report Duke-1-A, Section 17, paragraph 17.1.5 requires in part that activities affecting quality shall be accomplished in accordance with the requirements imposed by instructions procedures and drawings. Paragraph 8 of procedure ISI-120 Revision 10, requires UT instruments to be calibrated on circumferential and axial holes of the calibration block. Also, that pipe welds be scanned in the circumferential and axial directions and the results documented

-accordingly.

Contrary to the above, activities affecting quality were not being accomp-lished in accordance with procedures in that examination records 4r pipe welds B4.5.71, B4.5.72 and B4.7.53 made no reference to axial or circumfer-ential calibrations and weld examinations performed.

This is a Severity Level V Violation (Supplement I.E.).

Pursuant to the provisions of 10 CFR 2.201',. Duke Power Company is hereby required to submit to this office within twenty-five days of the date of this Notice, a written statement or explanation in reply, including: (1) admission or denial of the alleged violation;-(2) the; reasons for the violation if. admitted; (3) the corrective steps which have been taken and the results achieved; (4) corrective steps which will be taken to avoid further violations; and (5) the-date when full compliance will be achieved. Under the authority of Section 182 of the Atomic Energy Act of 1954, as amended, this response shall be submitted under oath or affirmation.

Date:

}

C10824 09

-