Responds to NRC 791106 Ltr Re Violations Noted in IE Insp Repts 50-416/79-21 & 50-417/79-21.Corrective Actions: Drawing Revised to Reflect Altered Installation of Valve Q1E21F012
ML19257D283
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 11/30/1979
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19257D273 List:
References
AECM-79-138, NUDOCS 8002040022
Download: ML19257D283 (2)


Text

.

= x MISSISSIPPI POWER & LIGHT COMPANY Helping Build Mississippi P. O. B OX 164 0 J A C K S ON MIS SIS SIP PI 3 92D5 ~

PRODUCTION DEPARTMENT 7, '? C November 30, 1979 s E

Office of Inspection & Enforcement --

U. S. Nuclear Regulatory Con: mission ca Region II U 101 Marietta Street, N. W., Suite 3100 Atlanta, Georgia 30303

_~

ATTENTION: Mr. J. P. O'Reilly, Director

Dear Mr. O'Reilly:

SUBJECT:

Grand Gulf Nuclear Station File 0260/0266/15521 NRC Inspection Report of

. August 21 - September 7, 1979 Inspection AECM-79/138 The attached corrective actions are submitted in response to your letter dated November 6,1979, transmitting the IE Inspection report for the August 21 - September 7, 1979 Inspection.

We find no proprietary information contained therein.

Yours truly, L. F. Dale Nuclear Project Manager JRF/JDR:pa Attachment cc: Mr. N. L. Stampley Mr. R. B. McGehee Mr. T. B. Conner Mr. Victor Stello, Jr., Director Division of Inspection 6 Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 4 20 Q 22-soo2n o G F g 77oog Member Middle South Utilities System t"+ m &L CUFi~ , .,

s ATTACHMENT TO AECM-79/138 A. NRC Item 416/79-21-01 "LPCS Globe Valve F012 Incorrectly Installed" (1) Corrective Steps Taken and Results Achieved Bechtel Quality Assurance issued QAR F-152 on August 28, 1979 to Construction and QAR F-154 on August 30, 1979 to Project Engineering for, in part, determination of cause, formulation and implementation of corrective action, and formulation and implementation of actions taken to preclude recurrence. The fourteen-inch globe valve, Q1E21F012, could not be installed in compliance to the drawing because of an interference. As a result of conversations between Field Engineering and Project Engineering and conversations and correspondence between Project Engineering and General Electric, the subject valve was installed in its present state. The failure to comply with programmatic requirements occurred when the valve was installed prior to the drawings being revised.

(2) Corrective Steps Taken to Avoid Further Noncompliance Involved personnel have been verbally reinstructed in programmatic requirements. Drawing 9645-M-1350A has been revised to reflect installation as has Drawing 9645-M-1087.

Therefore, the valve, as installed, is currently per the isometric drawing and the piping and instrumentation diagram.

(3) Date to Achieve Full Compliance Full compliance was achieved on November 28, 1979.